Carter County v. Oliver-Hill Const. Co.

143 Tenn. 649
CourtTennessee Supreme Court
DecidedSeptember 15, 1920
StatusPublished
Cited by12 cases

This text of 143 Tenn. 649 (Carter County v. Oliver-Hill Const. Co.) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carter County v. Oliver-Hill Const. Co., 143 Tenn. 649 (Tenn. 1920).

Opinion

Mr. Justice McKinney

delivered the opinion of the Court.

In October, 1915, the Oliver-Hill Construction Company' entered into a written contract with the road commissioners of Carter county for the construction of certain roads and highways in said county., and the Hartford Accident & Indemnity Company became surety on the bond of the construction company, which bond provided, among other things, as follows:

“In addition to guaranteeing the faithful performance of the contract as appears from same hereto attached and hereinbefore set forth, it is also understood and agreed that this bond shall protect all laborers and materialmen who furnish labor and materials used in the construction of roads contracted for, and the surety herein guarantees the full payment of all laborers and materialmen by the principal heerin as required by Acts of the Generali Assembly of the State of Tennessee of 1899, chapter 182.”

It appears that the construction company lost considerable money on this contract, and about the time said roads were completed, to-wit, September 19,1917, an involuntary [652]*652petition in bankruptcy was filed against it in the federal court by some of its creditors, and about the same time a number of suits were instituted against it and the surety on said bond in the state courts, by those who claimed to have furnished labor or materials on the contract, for which the surety company was liable.

Thereafter the said surety company filed a general creditors’ bill enjoining all of said suits in the State courts, and praying that all claims be adjudged in that suit.

Subsequently the said surety company filed a petition in the bankruptcy proceeding, in which it prayed that the balance due the construction company on account of said road contract be collected by the trustee in bankruptcy, and that said fund, when so collected, be applied in payment of claims for labor and material furnished on said contract before general creditors should be permitted to participate, and thus relieve it, as far as possible, as surety oh said bond.

The fourth prayer of said petition is as follows:

“That all persons asserting claims against said fund, or against this complainant as the surety on the bond here-inbefore referred to, whether such claims be for lábor and material furnished on the contract or whether a lien is asserted against said fund on some other ground, be required to file and prove their said claims in this cause, and that the rights of such claimants be ascertained and determined by appropriate proceedings.”

It is also prayed-in said petition: “That the defendants who have brought suits in the State courts against the construction company and this complainant on the [653]*653bond, Exhibit A hereto, be enjoined and inhibited from further prosecution of said suits, and that all other persons be enjoined from instituting and prosecuting any suit on said bond, or against said fund, except by petition in this court and cause.”

Various creditors of the construction company filed petitions in said bankruptcy court, setting forth in detail their claims against said construction company for labor and material furnished on said contract.

The referee in bankruptcy declined to enjoin the suits in the State courts, and no injunction was ever awarded by the presiding judge.

The various suits in the State courts were consolidated and heard together, and a decree was entered by the chancellor, adjudicating the rights of the parties in a general way, and referring the cause to the master for an accounting in conformity with the principles announced in his opinion' and decree based thereon, and in advance of the report on reference the chancellor, in the exercise of his. discretion, permitted the surety company to appeal to this court.

The first assignment of error made by the surety company goes to the action of the chancellor in overruling its plea of res judicata, it being insisted that the matters here involved were determined in the bankruptcy proceeding.

, To this we cannot assent. Both the referee and the trial judge allowed only such claims for labor or material as were admitted by the surety company, and neither undertook to adjudicate the rights and equities as between the creditors and the surety company.

[654]*654In said bankruptcy proceeding it was agreed that the balance due the construction company from the county was fll,130.40. With the approval of the surety company, the referee allowed claims aggregating $9,600.99. The order of the referee, after setting forth the names of the creditors and the sums allowed each, recites:

“It appears that there are items not embraced in the amounts above set forth in the claims of Barnes-Boring Hardware Company and Summers-Parrott Hardware Company which the claimants insist went into the road construction so as to give the claimants 'lien on the funds arising from the road contract1; but the petitioner, Hartford Accident & Indemnity Company, insists that these items are not secured by lien and it does not ask payment thereof under its petition. Action on these disputed items is therefore reserved by the court until the order and status of other labor and material claims and alleged assignments against the remainder of the fund have been established and fixed by the court. The trustee will pay out of said Carter county 'fund said claims, the names and amounts of which are above set forth.”

The Barnes-Boring Hardware Company filed a petition to review the action of the referee, and, in passing upon its claim, the court said:

“The Barnes-Boring Hardware Company was not entitled to a decree directing the payment of its claim for materials alleged to have been furnished the bankrupt beyond the $4,763.13, which the indemnity company sought to have so paid. Regardless of the question whether any [655]*655of tlie additional items were for materials used in the contract within the meaning of the act of 1899., the hardware company itself had no lien therefor, and the payment of the same should only be directed upon the application of the indemnity company in enforcement of its equitable right as surety, and since it did not seek the payment of such additional claims but on the contrary resisted the payment of the same, such items' should clearly only be allowed as unsecured claims against the bankrupt.”

The court, in passing- upon the claim of the Monarch Mills Company, said:

“Furthermore as the indemnity company did not seek the. payment of these claims, in the enforcement of its equitable right, they could in no event have been allowed as secured claims against the bankrupt, at the instance of the claimants themselves.”

What we have quoted above shows conclusively that the court allowed only such claims as the surety company admitted, and controverts the idea that the court undertook to adjudicate as between creditors of the construction company and the surety on its bond.

A number of reasons could be given as to why the plea of res judicata

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nicks v. Baird Co.
52 S.W.2d 147 (Tennessee Supreme Court, 1932)
County of Lake v. Southern Surety Co.
265 Ill. App. 286 (Appellate Court of Illinois, 1932)
J.F. Tolton Inv. Co. v. Maryland Casualty Co.
293 P. 611 (Utah Supreme Court, 1930)
West v. Detroit Fidelity & Surety Co.
225 N.W. 673 (Nebraska Supreme Court, 1929)
Massachusetts Bonding & Ins. v. Steele
293 S.W. 647 (Court of Appeals of Texas, 1927)
Mass. Bonding Ins. v. Steele
293 S.W. 647 (Court of Appeals of Texas, 1927)
Fidelity & Deposit Co. of Maryland v. Bailey
133 S.E. 797 (Supreme Court of Virginia, 1926)
U. S. Fidelity & Guaranty Co. v. Henderson County
276 S.W. 203 (Texas Commission of Appeals, 1925)
Hansen v. Remer
200 N.W. 839 (Supreme Court of Minnesota, 1924)
Hamblen Motor Co. v. Miller & Harle
150 Tenn. 602 (Tennessee Supreme Court, 1924)
Southern Const. Co. v. Halliburton
149 Tenn. 319 (Tennessee Supreme Court, 1923)
Cass v. Smith
146 Tenn. 218 (Tennessee Supreme Court, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
143 Tenn. 649, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carter-county-v-oliver-hill-const-co-tenn-1920.