West v. Detroit Fidelity & Surety Co.

225 N.W. 673, 118 Neb. 544, 1929 Neb. LEXIS 151
CourtNebraska Supreme Court
DecidedMay 29, 1929
DocketNo. 26593
StatusPublished
Cited by10 cases

This text of 225 N.W. 673 (West v. Detroit Fidelity & Surety Co.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
West v. Detroit Fidelity & Surety Co., 225 N.W. 673, 118 Neb. 544, 1929 Neb. LEXIS 151 (Neb. 1929).

Opinion

Redick, District Judge.

Action against the surety of the subcontractor to recover for labor and material furnished in the construction of a public highway. The petition declares upon fourteen causes of action, two of which belong to the plaintiffs and the twelve others being assigned to the plaintiffs for the purpose of suit. The plaintiffs dismissed the eleventh and fourteenth causes of action, and a verdict was rendered for plaintiff against the defendant on the other twelve, upon [546]*546which verdict judgment was rendered, and the defendant appeals.

The state of Nebraska and Otoe county entered into a contract with Stevens Brothers for the graveling of a certain road from Dunbar to Syracuse in Otoe county, Stevens Brothers and the Northwestern Casualty & Surety Company executed a bond to the department of public works of the state for the faithful performance of said contract. Stevens Brothers sublet the contract to the Interstate Construction Company, and the defendant, Detroit Fidelity & Surety Company, executed a bond to Stevens Brothers containing the following condition:

“Now, therefore, if said Interstate Construction Company as principal, shall in all respects fulfil its said contract according to the terms and tenor thereof, and shall faithfully discharge the duties and obligations therein assumed, and shall pay for all labor, equipment, gasoline, oils, materials and supplies used or employed on said contract, then the above obligation is to ibe void and of no effect; otherwise, to be and remain in full force and virtue of law.”

“The surety on this bond given to guarantee the faithful performance and execution of the work included in the contract shall be deemed and held, any contract to the contrary notwithstanding, to consent without notice: To any extension of time to the contractor in which to perform the contract when each particular extension does not exceed sixty days.”

The bond recited the awarding of the subcontract by Stevens Brothers to the construction company, and made it a part of the bond. The original contract between the state and Stevens Brothers provided for the completion of the work by September 1,1925, but also provided that such time might be extended by the department of public works, and the subcontract contained the following provision: “We,

Stevens Brothers, agree to give any extensions of time we may receive from the department of public works to the subcontractors.” Five extensions of time were granted as follows: To October 1, 1925; to December 1, 1925; to Feb[547]*547ruary 1, 1926; to April 1, 1926, and to June 1, 1926. The work was completed about June 1, 1926, but the claims for labor and material now held by the plaintiffs remained unpaid, and the action is brought to recover the same from .the surety.

The defendant, for the reversal of the judgment, presents three grounds which we deem it necessary to consider:

1. That the petition does not show that the plaintiffs have a right to maintain the action. The point made is that under section 3224, Comp. St. 1922, providing that, in contracts for public work to which the general provisions of the mechanics’ lien laws do not apply, and where the mechanics and laborers have no lien to secure the payment of their wages, and materialmen who furnish material for said work have no lien to secure payment for the material furnished in such work, a bond shall be required which shall be conditioned for the payment of all laborers and mechanics and for material used in performing the contract, and providing that such bond “may be sued on by any person entitled to the benefit of this chapter. The action shall' be in the name of the party claiming the benefit of this chapter” — plaintiffs are not within the class who may sue. The chapter containing the above section includes the mechanics’ lien law, and the argument is that, inasmuch as plaintiffs are not entitled to a mechanics’ lien, they have no right of action upon the bond. We think the contention unsound. The very purpose of the section in question was to protect persons who were not entitled to mechanics’ liens, and this purpose would be entirely defeated if this construction were adopted. The plain intention of the legislature as expressed here will control general terms; moreover, the greater includes the less, and the right is extended to any one who claims the benefit of any provision of the chapter.

It is further contended on this point that the bond is a substitute for mechanics’ liens, and that, inasmuch as the right to a mechanics’ lien is not assignable (Noll v. Kenneally, 37 Neb. 879), the right to sue upon the bond is not. Neither the case above referred to, nor any other to which [548]*548our attention, has been called, holds that the account which may furnish the basis for a mechanics' lien is not assignable, but merely that the assignor could not thereafter prove a lien because he had disposed of the claim and that the assignment of the debt did not have the effect to transfer a right to perfect and enforce a lien. In this case the assignment of the various claims to the plaintiffs invested them with the right to sue thereon in their own names, as provided by section 8526, Comp. St. 1922. It is well established in this state that a bond such as the one in suit is a contract made for the benefit of the parties furnishing labor and materials in performance of the principal contract, and that such persons have a right to sue thereon in their own names. Rohman v. Gaiser, 53 Neb. 474, was an action on a bond given for the performance of a public building contract, conditioned for the payment of labor and materials furnished the contractor, and it was held: “One not a party to a contract may maintain an action thereon when such contract was made for his benefit or the benefit of a class to which he belongs.”

2. That because of the fact that three of the extensions granted were for 61, 62, and 61 days, respectively, the surety upon the bond was thereby released. A number of cases are cited to the proposition that an extension of a contract between the parties thereto, based upon a valuable consideration, without the knowledge or consent of the surety, releases the surety, which is undoubtedly a correct statement of the general rule. Among other cases defendant cites Schwartz v. American Surety Co., 231 Mass. 490, where the condition of the bond of a building contractor was for the faithful performance of a contract to build a house to be completed by November 1, and it was held that an extension of the time for the completion of the house until Christmas of that year discharged the-surety. The bond in that case was not conditioned for the payment of the material and labor entering into the construction of the building, and the rights of persons furnishing the same were not in controversy. Also, Forburger Stone Co. v. Lion [549]*549Bonding & Surety Co., 103 Neb. 202, in which it was held that, as between the contractor and the surety, a failure to give a notice provided by the contract would release the surety; but, as the contract for the performance of which the bond was given provided that the contractor should pay for all materials which he used in the building, it was further held’ that the contract was of a dual nature, and that materialmen who had furnished material prior to the default in the giving of the notice were not affected thereby and might recover to that extent upon the bond as having been made for their benefit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Quality Equipment Co. v. Transamerica Insurance
502 N.W.2d 488 (Nebraska Supreme Court, 1993)
McElhose v. Universal Surety Co.
158 N.W.2d 228 (Nebraska Supreme Court, 1968)
International Harvester Co. v. L. G. DeFelice & Son, Inc.
197 A.2d 638 (Supreme Court of Connecticut, 1964)
Chicago & North Western Railway Co. v. Mallory
23 N.W.2d 735 (Nebraska Supreme Court, 1946)
Peter Kiewit Sons' Co. v. National Casualty Co.
8 N.W.2d 192 (Nebraska Supreme Court, 1943)
Fremont Foundry & Machine Co. v. Saunders County
285 N.W. 115 (Nebraska Supreme Court, 1939)
Luikart v. Massachusetts Bonding & Insurance
263 N.W. 124 (Nebraska Supreme Court, 1935)
Rogers v. Rowland
10 P.2d 988 (Washington Supreme Court, 1932)
County of Lake v. Southern Surety Co.
265 Ill. App. 286 (Appellate Court of Illinois, 1932)
Pickus v. State
215 N.W. 129 (Nebraska Supreme Court, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
225 N.W. 673, 118 Neb. 544, 1929 Neb. LEXIS 151, Counsel Stack Legal Research, https://law.counselstack.com/opinion/west-v-detroit-fidelity-surety-co-neb-1929.