Quality Equipment Co. v. Transamerica Insurance

502 N.W.2d 488, 243 Neb. 786, 1993 Neb. LEXIS 193
CourtNebraska Supreme Court
DecidedJuly 16, 1993
DocketS-91-424
StatusPublished
Cited by3 cases

This text of 502 N.W.2d 488 (Quality Equipment Co. v. Transamerica Insurance) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quality Equipment Co. v. Transamerica Insurance, 502 N.W.2d 488, 243 Neb. 786, 1993 Neb. LEXIS 193 (Neb. 1993).

Opinion

Shanahan, J.

Quality Equipment Company sued Transamerica Insurance Company on public contractor’s bond issued by Transamerica for the contractor, Allstate Paving, Inc., pursuant to Neb. Rev. Stat. § 52-118 (Reissue 1988) for material and equipment furnished to a subcontractor on two highway projects for the State of Nebraska. Section 52-118(1) states:

It shall be the duty of the State of Nebraska, or any department or agency thereof . . . empowered by law to enter into a contract for the erecting and furnishing, or the repairing of any public building, bridge, highway, or other *787 public structure or improvement... to which the general provisions of the mechanics’ lien laws do not apply ... to take from the person, persons, firm, or corporation to whom the contract is awarded a bond, in a sum not less than the contract price, with a corporate surety company, conditioned for the payment of all laborers and mechanics for labor that shall be performed and for the payment for material and equipment rental which is actually used or rented in the erecting, furnishing, or repairing of the public structure or improvement or in performing the contract.

Transamerica’s bonds expressly secured payment by Allstate and Transamerica “for the payment of material and equipment rental which is actually used or rented in performing the contract.”

The district court for Douglas County granted summary judgment to Quality, and Transamerica and Allstate appeal.

FACTUAL BACKGROUND

In 1989, the Nebraska Department of Roads entered into two contracts with Allstate for road repairs to two sections of Interstate 80. In accordance with § 52-118, Transamerica, as surety, issued two bonds for its principal, Allstate, to secure payment for materials in the highway projects.

Barajas Enterprises, Inc., and Tyler Construction Company formed a joint venture and subcontracted with Allstate to perform certain sawing and sealing work on the 1-80 projects. Quality supplied the Barajas-Tyler joint venture with material, including nine sets of diamond saw blades and rental equipment for both highway projects. Another supplier, Con-Spec, delivered the same types of material to the joint venture, including six sets of diamond saw blades and equipment. Before completing its work, the Barajas-Tyler venture abandoned the proj ects.

Quality subsequently sued Transamerica on the bonds, seeking $35,541.90 for materials and rental equipment. Transamerica answered and then tendered the defense of the action to Allstate, which intervened in the action, undertook the defense, and impleaded Barajas and Tyler as third-party *788 defendants. In its answer, Transamerica asserted that 15 sets of saw blades greatly exceeded the number required for work by the joint venture and that Quality’s price was unreasonable. Transamerica also claimed that certain rental equipment was not “actually used” in the projects because the equipment sat idle after the joint venture abandoned its work.

Quality moved for summary judgment against Transamerica and submitted the affidavit of Gabriel Barajas, the president of Barajas Enterprises. In his affidavit, Barajas stated, “All of the materials referred to in Exhibits ‘B’ through ‘Q’ and. all the rental equipment referred to in Exhibits ‘S’ through ‘W’ were delivered to the construction site and were used by the joint venture in its performance of the work under the subcontracts referred to above.” Exhibits B through Q included invoices showing that Quality delivered at least nine clipper diamond blades to Barajas. Quality also submitted the affidavit of its salesman, Michael Nowak, who stated that he delivered all the materials in question to Barajas at the construction site and that when the deliveries were made, the joint venture was working at the construction site. Finally, Quality submitted the affidavit of its president, Tyler Bouman, who stated that the charges listed on the attached invoices were “fair and reasonable and were below the manufacturer’s suggested retail price.”

Transamerica submitted several affidavits in opposition to Quality’s summary judgment motion. In his affidavit, Allstate’s project superintendent, Terry Kraemer, stated that a second supplier, Con-Spec, delivered six sets of blades to Barajas and that according to the estimates of Quality’s own sales representative, the joint venture would have used no more than eight sets of blades to complete the total cutting of 75,000 lineal feet in the project. Kraemer himself estimated that only six sets of blades would have been used for the cutting and that the difference in the number of blades, that is, the number allegedly delivered by Quality vis-a-vis the number required for work in the project, “is too far off to be the result of happenstance. The unaccounted for sets of blades could not have been used for the 1-80 projects.” Additionally, both Kraemer and E.J. Cruikshank, who in 1989 worked for a company which sold diamond saw blades in California, stated *789 that the price charged by Quality for the blades was “high and unreasonable.”

After considering the affidavits and exhibits submitted by the parties, the trial court concluded that the materials in question had been supplied to and accepted by the joint venture and that, therefore, Quality was entitled to the contract price for those materials.

ASSIGNMENTS OF ERROR

Transamerica and Allstate contend that the district court erred in (1) misconstruing § 52-118 by ruling that delivery of materials to the construction site and the subcontractor’s acceptance conclusively established liability under the general contractor’s bond, regardless of whether the materials were actually used in work on the highway projects; (2) entering summary judgment for Quality when the evidence indicated that not all the materials supplied at the project could have been used in the project and the equipment rental charges extended beyond the point at which the subcontractor abandoned the project; and (3) refusing to allow Transamerica to amend its answer and assert an affirmative defense of estoppel.

STANDARD OF REVIEW

A summary judgment is properly granted when the pleadings, depositions, admissions, stipulations, and affidavits in the record disclose that there is no genuine issue concerning any material fact or the ultimate inferences deducible from such fact or facts and that the moving party is entitled to judgment as a matter of law. [Citations omitted.] In appellate review of a summary judgment, the court views the evidence in a light most favorable to the party against whom the judgment is granted and gives such party the benefit of all reasonable inferences deducible from the evidence.

Union Pacific RR. Co. v. Kaiser Ag. Chem. Co., 229 Neb. 160, 162-63, 425 N.W.2d 872, 875 (1988). Accord, Shelter Ins. Co. v. Frohlich, ante p. 111, 498 N.W.2d 74 (1993); Parrish v. Omaha Pub.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maloley v. Shearson Lehman Hutton, Inc.
523 N.W.2d 27 (Nebraska Supreme Court, 1994)
Healy v. Langdon
511 N.W.2d 498 (Nebraska Supreme Court, 1994)
Arizona Motor Speedway, Inc. v. Hoppe
506 N.W.2d 699 (Nebraska Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
502 N.W.2d 488, 243 Neb. 786, 1993 Neb. LEXIS 193, Counsel Stack Legal Research, https://law.counselstack.com/opinion/quality-equipment-co-v-transamerica-insurance-neb-1993.