Wilson v. F & H Construction Co.

428 N.W.2d 914, 229 Neb. 815, 1988 Neb. LEXIS 338
CourtNebraska Supreme Court
DecidedSeptember 16, 1988
Docket87-047, 87-263
StatusPublished
Cited by19 cases

This text of 428 N.W.2d 914 (Wilson v. F & H Construction Co.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilson v. F & H Construction Co., 428 N.W.2d 914, 229 Neb. 815, 1988 Neb. LEXIS 338 (Neb. 1988).

Opinion

Shanahan, J.

In consolidated cases, Constance Wilson appeals from summary judgments granted to F & H Construction Company and Taylor Plumbing, Inc., in negligence actions brought by Wilson to recover for bodily injury sustained when she fell into a hole. Wilson also included the city of Omaha as a defendant, but the action against the city is not involved in Wilson’s appeal.

On February 9, 1982, F & H Construction, as general contractor, entered a contract with the housing authority of the city of Omaha for the construction of 42 units of scattered-site housing, which included construction of a six-plex. Wilson’s home is located immediately north of the six-plex site.

F & H subcontracted demolition of a brick house and earthwork for construction of the six-plex. During demolition of the brick house on the six-plex site, the subcontractor struck an underground waterline. Taylor Plumbing, another subcontractor of F & H Construction, capped that broken waterline. Taylor also capped the sewerline that had serviced the demolished brick house, but was not involved with any demolition or removal of structures from the site.

As part of its subcontract with F & H Construction, Taylor Plumbing connected the sewer and water services for the six-plex by tying into the city’s mains. Taylor Plumbing installed the six-plex waterline about 6 feet below ground, and then backfilled the area above the newly installed line by using a “hydraulic tamping tractor” and two other pieces of heavy equipment.

The Omaha housing authority approved and accepted the housing project in January 1983.

On February 13,1983, Wilson stepped onto the strip of land between the sidewalk and 24th Street in front of her home adjacent to the six-plex site, and was injured when the ground caved in and she fell into a waist-deep hole. According to Wilson’s husband, the ground in the area where Constance fell had never settled or sunk before the accident.

The City of Omaha was called and the depression was filled, *817 but the hole had to be filled two or three additional times because the ground kept sinking. Finally, on April 5, 1983, the accident site was excavated to ascertain the cause of the settling ground and accident in which Constance Wilson was injured. Representatives of F & H Construction, Taylor Plumbing, and the City of Omaha were present at the time of this investigatory excavation. Robert Taylor, president of Taylor Plumbing, described what he saw as the investigatory excavation reached the 6-foot level where Taylor Plumbing had installed the waterline from the six-plex to the city’s main at 24th Street: “[W]e went down lower and found a sewer stub that was open and the water was finding its way into this new excavation here down the hole into the sewer stub ... a stub not plugged up

The broken and uncapped sewer stub allowed water and earth to pass from above into the main sewerline, thereby causing subterranean erosion and resulting in the overlying ground’s sinking to fill the gap left by the earth which had moved through the open stub into the sewer. As a city employee related, the stub was part of “an old abandoned sewer line that came from a house that was sitting on a lot that had been torn down. We found that house line that was not plugged off, and dirt was going into that from that spot there.” Before the investigatory excavation, existence of the stub was unknown to F & H Construction and its subcontractors. The stub in question was buried 2 feet beneath the waterline installed by Taylor Plumbing. A plat or “job site quarter section,” prepared by the city and obtained by F «fe H Construction before its work at the six-plex site, showed the location of all known utility stubs, but did not show the stub where the earth caved in. Robert Taylor stated that there was no reason to suspect the stub was buried beneath the waterline installed by Taylor Plumbing, because the stub was not shown on the city’s plat or quarter section. Seepage did not indicate a problem, because the ground was dry at the 6-foot level when Taylor Plumbing installed the waterline.

The stub apparently serviced an old building, a structure torn down anywhere from 5 to 50 years before F <& H’s construction work concerning the six-plex. No one knows who tore down the *818 old building, and the only indication that a structure once sat on the project site was some debris uncovered near the surface during grading of the site. In postaccident investigation, an excavatory crew traced the stub by starting at the street and digging back toward the six-plex, but the sewer pipe that had run from the stub to the old building had been removed and no additional pipe was discovered. The investigatory excavation did not disclose any waterlines or sewerlines which connected the old building to the uncapped stub. The exact distance from the discovered broken stub to the six-plex site is not definite and may range from 20 to 30 feet.

In her summary judgment affidavit, Wilson states that “ [w]hile the.bulldozer was digging up the foundation of the old, previously demolished house on the site, I observed that it unearthed old brick and mortar and pieces of tile pipe which were hauled off the job site.”

In her second amended petition, Wilson alleged that F & H Construction and Taylor Plumbing caused her injuries by failing to properly tamp the ground after they completed the construction project, by failing to properly cap the broken sewerline, and by operating heavy machinery in the area in which the broken stub was found.

F & H Construction and Taylor Plumbing moved for summary judgment, claiming that no genuine issue of fact existed regarding their alleged liability for Wilson’s injuries. The district court sustained both motions and dismissed F & H Construction and Taylor Plumbing from the case.

Wilson contends that the stub was broken by Taylor Plumbing when it installed the waterline above the stub and used three pieces of heavy equipment to backfill the installation area. Wilson argues that F & H Construction and Taylor Plumbing knew or should have known that they were excavating above an old sewerline and that they should have discovered and capped the previously broken stub, thereby preventing the cave-in which caused Wilson’s injuries.

A summary judgment is properly granted when the pleadings, depositions, admissions, stipulations, and affidavits in the record disclose that there is no genuine issue concerning any material fact or the ultimate *819 inferences deducible from such fact or facts and that the moving party is entitled to judgment as a matter of law. [Citations omitted.] In appellate review of a summary judgment, the court views the evidence in a light most favorable to the party against whom the judgment is granted and gives such party the benefit of all reasonable inferences deducible from the evidence. [Citation omitted.]

Union Pacific RR. Co. v. Kaiser Ag. Chem. Co., ante p. 160, 162-63, 425 N.W.2d 872, 875 (1988). See, also, Neb. Rev. Stat. §

Related

McClure v. Forsman
662 N.W.2d 566 (Nebraska Supreme Court, 2003)
Riley v. State
506 N.W.2d 45 (Nebraska Supreme Court, 1993)
Quality Equipment Co. v. Transamerica Insurance
502 N.W.2d 488 (Nebraska Supreme Court, 1993)
Dowis Ex Rel. Dowis v. Continental Elevator Co.
486 N.W.2d 916 (Nebraska Supreme Court, 1992)
Anderson v. Service Merchandise Co., Inc.
485 N.W.2d 170 (Nebraska Supreme Court, 1992)
Murphy v. Spelts-Schultz Lumber Co.
481 N.W.2d 422 (Nebraska Supreme Court, 1992)
Wiles v. Metzger
473 N.W.2d 113 (Nebraska Supreme Court, 1991)
Eastroads, Inc. v. City of Omaha
467 N.W.2d 888 (Nebraska Supreme Court, 1991)
First Corporate Finance, Inc. v. Rogers
467 N.W.2d 853 (Nebraska Supreme Court, 1991)
Pelzek v. American Legion
463 N.W.2d 321 (Nebraska Supreme Court, 1990)
Mason State Bank v. Sekutera
461 N.W.2d 517 (Nebraska Supreme Court, 1990)
Burns v. Veterans of Foreign Wars
438 N.W.2d 485 (Nebraska Supreme Court, 1989)
DeCamp v. Lewis
435 N.W.2d 883 (Nebraska Supreme Court, 1989)
Everlasting Golden Rule Church v. Dakota Title & Escrow Co.
432 N.W.2d 803 (Nebraska Supreme Court, 1988)
Bedrosky v. Hiner
430 N.W.2d 535 (Nebraska Supreme Court, 1988)
Hutmacher v. City of Mead
430 N.W.2d 276 (Nebraska Supreme Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
428 N.W.2d 914, 229 Neb. 815, 1988 Neb. LEXIS 338, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilson-v-f-h-construction-co-neb-1988.