Nicks v. Baird Co.

52 S.W.2d 147, 165 Tenn. 89, 1 Beeler 89, 1931 Tenn. LEXIS 175
CourtTennessee Supreme Court
DecidedJuly 23, 1932
StatusPublished
Cited by9 cases

This text of 52 S.W.2d 147 (Nicks v. Baird Co.) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nicks v. Baird Co., 52 S.W.2d 147, 165 Tenn. 89, 1 Beeler 89, 1931 Tenn. LEXIS 175 (Tenn. 1932).

Opinion

Mb,, Justice Swiggabt

delivered the opinion of the Court.

Complainant is the owner of a steam boiler which he rented to Baird and Company, for use in the execution of a contract to construct a state highway bridge. The boiler was used to generate power to force water through hollow piles; the water serving to remove the earth beneath the piles, so that they could be lowered to a depth that would permit the operation of an ordinary pile driver. The regular equipment of Baird and Company included a pile driver, operated by a boiler and engine, but the piles being too long to be started by the pile driver, the additional boiler was necessary to operate the water pump. The contract was that complainant, otherwise employed on the bridge construction at a per diem wage, should receive forty cents an hour for the use of the boiler. This rental charge, amounting to $646, is the subject of this suit. •

Complainant was awarded a decree by the Chancellor against Baird and Company, but recovery was denied against the surety on the construction bond, on the ground that the bond does not cover the amount due by the contractor for rental of machinery. On complainant’s appeal, the decree of the Chancellor was affirmed by the Court of Appeals. We have heretofore granted complainant’s petition for the writ of certiorari, to review the decree of the latter court.

*92 The bond of the surety, Southern Surety Company, is the statutory bond authorized by Acts 1917, chapter 74. Southern Const. Co. v. Halliburton, 149 Tenn., 319. The condition of the bond which is material to this case is that the contractor “shall well and truly pay every person furnishing material or performing labor in and about the construction of said roadway, all and every sum or sums of money due him, them or any any of them, for all such labor and materials for which the contractor is liable.” The statute cited required that the contractor execute bond, conditioned to secure “the payment for all materials purchased and for all labor employed in the contemplated work. ’ ’

Complainant contends that the boiler was material used in the construction of the bridge, and that all that was purchased was its use for the requisite number of hours, which was consumed in the execution of the construction contract.

In Southern Const. Co. v. Halliburton, supra, analogy was found between the liability of the surety on this statutory bond and the liability of a property owner under the mechanic’s lien statutes, and it was held that the surety is liable only for “material consumable in the use or intended to be consumed in the use.” The Court said: “It would be too broad a construction of this statute to fasten such a liability upon the general contractor and the surety for materials which the subcontractor purchased, which were not used up in the job, and remained the property of the subcontractor to be thereafter used by him in other work.”

The mechanic’s lien statutes, the statutes creating liens on railroads in favor of the furnishers of labor and materials in their construction, and the statutes requir *93 ing the execution of bonds by persons engaged in public works, have been found to contain similar provisions with respect to the protection afforded furnishers of materials, and it has been clearly intimated by this Court that a uniform construction and application of the several statutes in this regard is both possible and desirable. Consolidated Engineering Co. v. Wedow Myers, 154 Tenn., 358, 289 S. W., 508; Hamblen Motor Co. v. Miller & Harle, 150 Tenn., 602, 266 S. W., 99.

On the authority of Pittsburg Coal Co. v. So. Asphalt & Const. Co., 138 Tenn., 154, 196 S. W., 490, coal used for generating steam in complainant’s boiler was material used in the performance of the bridge contract, within the application of the statute and bond. If pumps operated by man power rather than by steam had been used, the wages of the men so employed would have been covered by the bond. The boiler was material, by the use of which the energy in the coal was released and directed as a substitute for the labor of men, and contributed to the execution of the contract in the same relative degree as did the coal fed into its fire box. Compensation of the owner who supplied it is therefore within the principle given effect by the legislature, in its enactment of the statute requiring the execution of bond for the protection of furnishers of labor and .material.

In Pittsburg Coal Co. v. So. Asphalt & Const. Co., supra, the Court, recognizing the change in methods of constructing buildings and other improvements from time to time, expressed the view that legislation for the protection of materialmen and laborers is not rigid but is flexible, to be enforced in such manner as to afford the protection intended. The Court said: “The statute under consideration was passed for the protection of laborers *94 and the furnishers of material on public works, and the inquiry should not be limited to the method by which the contract is performed.”

The essential requirement that materials be consumed in the execution of the principal contract, in order that their cost be secured by a lien on the building constructed, or by the contractor’s bond for a public works project, is supported by two obvious reasons. If the material furnished is not consumable in the use, it is furnished on the general credit of the contractor and not merely in aid of the performance of the particular contract. And if on the completion of the building or project the material, still possessing value, remains the property of the contractor, liability for its cost should be and is his liability alone, unless under the conditions recognized in York Lumber & Mfg. Co. v. McKnight & Mertz, 139 Tenn., 687, 203 S. W. 254, and in Cass v. Smith, 146 Tenn., 218, 230, 240 S. W., 778. But neither of these rea--sons is present when all that is purchased is the use of material in the execution of the particular contract, under an agreement of hire or lease. In such case all that is purchased is consumed in the use, in aid of the contract, and under the facts of the case before us nothing is sought to be charged against the bond except the value of material furnished the contractor in the performance of his contract.

The fact that this Court has not heretofore been called upon to rule the question presented by complainant’s claim should not prejudice its consideration.

In Illinois Surety Company v. John Davis Company, 244 U. S., 376, 61 L. Ed., 1206, a contractor for the construction of the Naval Training Station, at Chicago, executed bond under a federal statute which required that *95

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Winter v. Smith
914 S.W.2d 527 (Court of Appeals of Tennessee, 1995)
CPS Distributors, Inc. v. Federal Insurance Co.
685 P.2d 783 (Colorado Court of Appeals, 1984)
Thompson v. Commissioner
1983 T.C. Memo. 81 (U.S. Tax Court, 1983)
Scott v. Travelers Indemnity Company
384 S.W.2d 38 (Tennessee Supreme Court, 1964)
Thompson & Green Machinery Co. v. M. P. Smith Construction Co.
311 S.W.2d 614 (Court of Appeals of Tennessee, 1957)
Peter Kiewit Sons' Co. v. National Casualty Co.
8 N.W.2d 192 (Nebraska Supreme Court, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
52 S.W.2d 147, 165 Tenn. 89, 1 Beeler 89, 1931 Tenn. LEXIS 175, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nicks-v-baird-co-tenn-1932.