Winter v. Smith

914 S.W.2d 527, 1995 Tenn. App. LEXIS 553
CourtCourt of Appeals of Tennessee
DecidedAugust 23, 1995
StatusPublished
Cited by51 cases

This text of 914 S.W.2d 527 (Winter v. Smith) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Winter v. Smith, 914 S.W.2d 527, 1995 Tenn. App. LEXIS 553 (Tenn. Ct. App. 1995).

Opinion

OPINION

KOCH, Judge.

This appeal concerns two consohdated lawsuits arising from the construction of an equestrian center in Williamson County. The first suit involves the landowner and a contractor who was terminated before the project’s completion. The second suit involves the landowner, the terminated contractor, and two of the contractor’s unpaid supphers. After receiving a jury’s answers to special interrogatories, the Chancery Court for Williamson County found that the contractor was contractually indebted to his unpaid suppliers, that the suppliers were entitled to liens on the project, and that the landowner must indemnify the contractor for *531 his payments to the suppliers. Both the landowner and the contractor have appealed. The landowner raises issues on this appeal concerning the existence and scope of the parties’ respective indemnification rights and the lien rights of one of the suppliers; while the contractor takes issue with the dismissal of his damage claims against the landowner. We affirm the judgment except for the trial court’s conclusions with regard to the contractor’s indemnification rights.

I.

Helene Winter decided to build an equestrian center in Williamson County after her teenage daughter became interested in show jumping. She arranged to purchase fifty-five acres of undeveloped property on Old Hills-boro Road. She intended to construct the center herself and then to lease it to a family corporation called Schandwin Farm, Inc. 1 Her plans called for the construction of a stable with an indoor ring, three outdoor show rings, paddocks, a manager’s residence, and other related improvements including fences and an access road.

Ms. Winter decided to oversee and coordinate the improvements on the property herself even though she had little experience with construction. She retained one contractor to build the barn and another to erect all the fences on the property. Since the project called for extensive site preparation, she retained a third contractor to perform all the excavation, grading, and road construction. These lawsuits relate to the excavation and grading contract.

Ms. Winter contacted Tommy Smith in late October 1989 about doing the grading and excavation work for the project. Mr. Smith had been a foreman for a large construction company and was then operating his own business called Smith Dozier [sic] Service. He had been licensed as a contractor until 1987 but was not licensed when Ms. Winter contacted him. Ms. Winter and Mr. Smith met at the job site to discuss the project, and while the precise terms of their agreement are not clear, Mr. Smith agreed to do excavation work for Ms. Winter and to charge her $50.00 per hour for the use of his bulldozer. 2

Ms. Winter’s surveyor placed the grading stakes on the property, and Mr. Smith began work on November 2, 1989. After wet weather interrupted the work for several days, Ms. Winter telephoned Mr. Smith on November 16, 1989 to find out why he was not working. Despite Mr. Smith’s explanation that wet soil conditions hampered the grading and excavating, Ms. Winter insisted that Mr. Smith continue working despite the weather because she was planning to have horse shows in the spring and wanted the barn built as soon as possible.

Ms. Winter customarily made daily visits to the job site when she was in town, and she and Mr. Smith met at the job site on November 17,1989. She paid Mr. Smith $2,000 and asked him for an estimate of the cost to complete the project. Ms. Winter assumed that the estimate would include all the work for the project; while Mr. Smith assumed that Ms. Winter wanted an estimate for the cost of completing only the barn pad, the parking lot at the barn, and the road from Old Hillsboro Road to the barn.

On November 22, 1989, Mr. Smith gave Ms. Winter an estimate that the lump sum cost to complete the work would be $91,726. Ms. Winter decided against accepting the lump sum quote and to continue paying Mr. Smith in accordance with their original agreement after her surveyor commented that the estimate seemed high and after Mr. *532 Smith told her that she would end up spending less if he worked on a “time and materials” basis. During this meeting, Ms. Winter instructed Mr. Smith to continue building the road from the barn to the back of the property and discussed building the three show rings.

On November 30, 1989, Mr. Smith gave Ms. Winter a statement for $12,522.50 for the work from November 2 through November 30, 1989. The statement included charges for a bulldozer, a loader, a scraper, a track, and a roller. Mr. Smith had obtained several of these pieces of equipment from Dixie Earthmovers, Inc. While he and Ms. Winter had agreed on the .hourly charges for the equipment, Ms. Winter was not aware that the charge for the equipment obtained from Dixie Earthmovers included Mr. Smith’s markup. Ms. Winter paid Mr. Smith $12,-522.50 on December 1,1989.

The project called for a large amount of crashed stone and gravel for the road, the parking lot, the bam pad, and the show rings. The parties’ original agreement required Ms. Winter to furnish these materials. When the work progressed to the point where the stone was required, Ms. Winter arranged with Bentley and Son Tracking & Construction (“Bentley”) to begin delivering stone to the job site. Bentley, however, would only do business with Ms. Winter on a COD basis, and thus she was required to be at the job site every day to write a check for the stone that had been delivered.

Mr. Smith paid Bentley for stone on one occasion because Ms. Winter could not come to the job site. On December 12, 1989, Ms. Winter complained to Mr. Smith about Bentley’s prices, and Mr. Smith informed her that Buford Tracking (“Buford”) could furnish the same material for $6.00 per ton. Since Ms. Winter had been paying Bentley $6.55 per ton for stone, she decided to begin purchasing the stone from Buford.

Buford, however, would not agree to extend credit to Ms. Winter and insisted on billing Mr. Smith directly for the stone. In order to avoid the inconvenience of paying for the stone on a daily basis, Ms. Winter and Mr. Smith eventually agreed that Mr. Smith would purchase the stone. Ms. Winter agreed to pay $6.00 per ton for the stone, and Mr. Smith agreed to include the charges for the stone in his periodic statements. Ms. Winter assumed that Mr. Smith had agreed to charge her no more than his actual cost for the stone; while Mr. Smith understood that Ms. Winter had agreed to pay $6.00 per ton for stone, regardless of his actual cost.

On December 13, 1989, Mr. Smith gave Ms. Winter another statement for $10,973 covering the work from December 1 through December 12, 1989. On the same day, Ms. Winter gave Mr. Smith a check for $11,-153.50 in payment for the work covered by the statement and to reimburse Mr. Smith for the stone he had purchased from Bentley on December 6, 1989, when she was unable to be on-site to write the check.

The grading work continued to be delayed by bad weather. Ms. Winter was not pleased with the progress, and on January 10, 1990, she told Mr. Smith that she intended to contact Buford to arrange for more earth moving equipment. Mr. Smith explained that using more equipment would increase Ms.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Julie Buhler v. Lefkovitz & Lefkovitz, PLLC
Court of Appeals of Tennessee, 2025
Karl Robert Kokko v. Thomas L. Moore, Jr.
Court of Appeals of Tennessee, 2025
Wade v. Newport Group, Inc.
W.D. Tennessee, 2025
Joe H. Edwards v. Angela L. Underwood
Court of Appeals of Tennessee, 2025
Pryority Partnership v. AMT Properties, LLC
Court of Appeals of Tennessee, 2021
Jimmy Wayne Helton v. Earl Lawson
Court of Appeals of Tennessee, 2019
State of Tennessee v. Curtis Logan Lawson
Court of Criminal Appeals of Tennessee, 2019
McKinnie v. State Farm Fire & Cas. Co.
298 F. Supp. 3d 1138 (M.D. Tennessee, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
914 S.W.2d 527, 1995 Tenn. App. LEXIS 553, Counsel Stack Legal Research, https://law.counselstack.com/opinion/winter-v-smith-tennctapp-1995.