United States Fidelity & Guaranty Co. v. Thompson & Green MacHinery Co.

568 S.W.2d 821, 23 U.C.C. Rep. Serv. (West) 849, 1978 Tenn. LEXIS 613
CourtTennessee Supreme Court
DecidedMarch 29, 1978
StatusPublished
Cited by20 cases

This text of 568 S.W.2d 821 (United States Fidelity & Guaranty Co. v. Thompson & Green MacHinery Co.) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fidelity & Guaranty Co. v. Thompson & Green MacHinery Co., 568 S.W.2d 821, 23 U.C.C. Rep. Serv. (West) 849, 1978 Tenn. LEXIS 613 (Tenn. 1978).

Opinion

OPINION

BROCK, Justice.

This is an action to recover rent from an alleged lessee and its surety. The claim of Thompson and Green Machinery Company, a dealer in heavy construction equipment, arises out of defaults by James F. Gregory, Inc., a highway contractor, in the payment of monthly installments due plaintiff on thirty items of road-building equipment under twenty-six written agreements, plus certain repairs and parts furnished by Thompson and Green to Gregory. The equipment was used on seven separate state highway contracts on which Gregory was the principal contractor and on three state highway contracts on which Gregory was the subcontractor. United States Fidelity and Guaranty Company gave its bond in statutory form on the obligation of the contractor as required by T.C.A. § 54-519 and on the seven contracts which Gregory held with the State. USF&G also executed a performance bond for Gregory on the three highway jobs for which he was the subcontractor.

Thompson and Green filed suit against Gregory and USF&G in the Chancery Court for the amounts allegedly due under the agreements. Gregory defended that the “rentals” were actually “sales” and counterclaimed for damages arising from the breach of an alleged novation between Thompson and Green and Gregory, i. e., Thompson and Green’s refusal to conduct an auction of the equipment as allegedly agreed, with the proceeds to be applied first to the remaining debt owed Thompson and Green with excess payable to Gregory as his “equity” in the equipment. Gregory subsequently amended his answer and counterclaim, alleging that he had returned the equipment to Thompson and Green pursuant to an agreement for its disposal by auction and that Thompson and Green had failed to sell or dispose of the equipment as required by Article 9 of the Uniform Commercial Code. However, the latter insistence was not made in this Court, and, therefore, is not before us for determination.

Each of the twenty-six agreements between Thompson and Green and Gregory is a form contract denominated “Associated Equipment Distributors Uniform Lease Contract.” Each contract provides that Thompson and Green “proposes to lease and does lease” the described item of equipment upon payment of a monthly rental of a fixed amount for a specified minimum term, ranging from three to fifteen months. Except for provisions allowing for the lessor’s repossession for failure to pay rent or other breach of the lease by the lessee, the contracts are renewable on a month to month basis by the lessee. The lessee thus had the right to terminate the agreement upon expiration of the specified minimum term or the right to extend the lease for a period equivalent to the asset’s useful life. Gregory testified that his only obligation under the contracts in issue was to pay the *823 monthly rental for the minimum rental period and that he had no obligation to pay the purchase price of the equipment. At the end of the minimum rental period, Gregory could return the equipment and be liable only for the accrued rental.

Each contract also states the “total value,” exclusive of sales tax, of the equipment leased which was shown at trial to be the purchase price of the machinery in the event the lessee elected to purchase. No evidence as to the projected market value of the equipment was introduced. The contracts further obligate the lessee to keep the equipment insured and to pay all repair bills, taxes and other public charges and assessments on the equipment.

The contracts themselves contain no express option to purchase the equipment but proof of a collateral oral option to purchase was adduced at trial. USF&G’s evidence was that plaintiff orally agreed that all rentals paid would be credited against the purchase price and that when the aggregate rentals equalled the “total value” figure shown on the lease, defendant would have the option of receiving title upon payment of a small financing charge. Thompson and Green testified that it had an unwritten policy of extending an option to purchase to a lessee who had paid rentals on a given piece of equipment in an amount equal to the total value of the equipment, but insisted that the option was extended only if the lessee’s account were paid up and in good order.

USF&G conceded that if the equipment contracts were true leases, the unpaid rentals of equipment by a public contractor constituted “materials furnished” within the meaning of its statutory bond and that it would therefore be liable to plaintiff. USF&G insisted, however, as did Gregory, that the contracts in question, although leases in form, were not true leases and that the parties intended that the transactions create security interests in the equipment, liability for which was not covered under its bonds.

Alternatively, USF&G argued that Thompson and Green’s recovery should be diminished by: (1) $112,817.76 — representing claims of Thompson and Green against Gregory not timely filed as required by T.C.A. § 54-522, and (2) $71,071.59 — representing payments made by Gregory and applied by Thompson and Green to an account not covered under the terms of the surety’s bond which Thompson and Green should have applied to the secured debt.

The Chancellor determined that the equipment contracts were true leases and, thus, that Thompson and Green was entitled to recover its provable claims for unpaid rent and for services, parts and repairs rendered Gregory during the terms of the leases. The Chancellor dismissed Gregory’s counter-claim based upon the alleged novation, finding, as a matter of fact, that no contract to conduct an auction of the equipment was ever consummated between the parties. Refusing both arguments for diminution of plaintiff’s recovery against USF&G, the Chancellor entered judgment against both Gregory ($403,382.23 plus interest) and USF&G ($273,753.84).

Only USF&G appealed. The Court of Appeals affirmed the Chancellor in part, but did allow USF&G a credit for the $71,-071.59 applied by Thompson and Green to unsecured obligations of Gregory, thus reducing the judgment against USF&G to $202,682.25 plus interest.

Both parties filed petitions for certiorari. Finding no error by the Court of Appeals with regard to its allowance of the credit in favor of the surety, we granted only the petition of USF&G.

I

The primary significance, in this case, of the distinction to be drawn between a true lease and a conditional sale with a “lease” employed as a security device is to be found in our law requiring highway contractors to provide a surety bond “for the full and faithful performance of every part and stipulation of the contract, especially the payment for all materials furnished and for all labor employed in the contemplated work.” T.C.A. § 54-519. In Southern Construction *824 Co. v. Halliburton, 149 Tenn. 319, 332, 258 S.W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brandt v. Bib Enterprises, Ltd.
986 S.W.2d 586 (Court of Appeals of Tennessee, 1998)
Rent-A-Center, Inc. v. Mahoney (In Re Mahoney)
153 B.R. 174 (E.D. Michigan, 1992)
In re Puckett
838 F.2d 471 (Sixth Circuit, 1988)
In Re Standard Financial Management Corp.
79 B.R. 100 (D. Massachusetts, 1987)
In Re Farrell
79 B.R. 300 (S.D. Ohio, 1987)
Jahn v. M.W. Kellogg Co.
822 F.2d 16 (Sixth Circuit, 1987)
Sky Transpo, Inc. v. City of Knoxville
703 S.W.2d 126 (Tennessee Supreme Court, 1985)
Thompson v. Commissioner
761 F.2d 259 (Sixth Circuit, 1985)
United States Court of Appeals, Sixth Circuit
761 F.2d 259 (Sixth Circuit, 1985)
Thompson v. Commissioner
1983 T.C. Memo. 81 (U.S. Tax Court, 1983)
In Re Winston Mills, Inc.
6 B.R. 587 (S.D. New York, 1980)
Goodwin Bros. Leasing, Inc. v. H & B INC.
597 S.W.2d 303 (Tennessee Supreme Court, 1980)
U C Leasing, Inc. v. Laughlin
606 P.2d 167 (Nevada Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
568 S.W.2d 821, 23 U.C.C. Rep. Serv. (West) 849, 1978 Tenn. LEXIS 613, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fidelity-guaranty-co-v-thompson-green-machinery-co-tenn-1978.