Wheeler Lumber Bridge & Supply Co. v. Seaboard Surety Co.

16 N.W.2d 519, 218 Minn. 443, 1944 Minn. LEXIS 509
CourtSupreme Court of Minnesota
DecidedNovember 17, 1944
DocketNos. 33,810, 33,811.
StatusPublished
Cited by11 cases

This text of 16 N.W.2d 519 (Wheeler Lumber Bridge & Supply Co. v. Seaboard Surety Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wheeler Lumber Bridge & Supply Co. v. Seaboard Surety Co., 16 N.W.2d 519, 218 Minn. 443, 1944 Minn. LEXIS 509 (Mich. 1944).

Opinion

Julius J. Olson, Justice.

Two cases are here for review upon appeals by plaintiffs from orders sustaining general demurrers to their complaints. The cases have been consolidated on appeal. Since both actions involve the same defendant, contract, and essential facts, we shall recite only the necessary allegations of the complaint in the Wheeler Lumber Bridge & Supply Company case, No. 33,811.

Plaintiff, a materialman, on July 6, 1942, furnished certain material purchased and used by D. F. McElroy & Company in performing a contract for the construction of certain concrete box culverts on a state highway. The contract was entered into August 19, 1941. Defendant is the surety on the performance bond. The contractor failed to pay the price or value of the material so furnished, and this action was brought against the surety. Certain events, chronologically listed, may be of aid to decision.

On July 15, 1942, the contractor’s work was finished and the equipment removed from the job. The highway department has since been in complete possession and control of the highway, and no one has suggested that the contractor failed in any way to- perform. On August 10, 1942, the project engineer executed what is referred to as “Contract Voucher No. 9 (Final),” certifying “that the items of work shown in the Statement of Work Performed herein have been actually furnished for the work comprising the above-mentioned projects in accordance with the plans and specifica *445 tions heretofore approved.” On September 25, 1942, defendant “as surety for D. F. McElroy & Company, Contractor on the above referenced project and contract, do hereby consent to final payment for work performed.” On September 26, the district engineer certified “that a final examination has been made of the above noted contract, that the contract has been completed, that the entire amount of work shown in this final voucher has been performed and the total value of the work performed in accordance with, and pursuant to, the terms of the contract is as shown in this final voucher.” On October 3, the contractor certified “that he has performed and completed all the work described herein in accordance with and pursuant to the terms of his contract, and does hereby accept this final voucher as being correct, full and complete and does make claim for final payment on this contract in accordance with this final voucher.” On October 6, the construction engineer certified to the “completion” of the contract and that “The total value of the work set forth in this final voucher is in accordance with the terms of said contract.” On the same day, the chief engineer recommended “the above contract for acceptance and final payment.” On October 7, the commissioner of highways “approved” the voucher “for final payment and the work is accepted.” On December 9, plaintiff filed with the commissioner of insurance a notice of claim in accordance with the provisions of Minn. St. 1941, § 574.31 (Mason St. 1940 Supp. § 9705). The precise question here is whether this notice was filed within the time limited by that statute. So far as here material it reads:

“No action shall be maintained on any such bond unless within 90 days after the completion of the contract and acceptance thereof by the proper public authorities, the claimant shall file a written notice specifying the nature and amount of his claim and the date of furnishing the last item thereof * * *.” (Italics supplied.)

Obviously, the contract was completed in July. No one claims otherwise. When was it accepted “by the proper public authorities”? Defendant contends that it was accepted in July; plaintiff *446 that it was not accepted until October 7, and hence that the notice was filed in due time.

When, on July 15, the project engineer concluded that the job was finished and he then informed the contractor that the men and equipment could be removed from the job, there still remained important matters to be done. Obviously, computations then had to be made of work done and material used in the performance of the job. Partial payments had to be checked in order that the final balance due the contractor might be arrived at. And, as we haye seen, on August 10 the project engineer, having finished his computations, executed, “in the course of his employment and in accordance with the customary and usual procedure” of the department, the final estimate. Within it many facts are included. There we find that the original contract price of $13,424.35 had been increased to $21,415.02 because of extra work and supplemental agreements made relating thereto. The engineer credited to the state “previous payments” amounting to $19,593.32, thus leaving as the “net amount due” the contractor $1,821.70. This was the amount to the final payment of which defendant, “as surety,” consented on September 25 “for work performed” on this job by its principal.

Then, too, we have the department’s rules and “specifications for highway construction.” These are integrated into its procedural forms as requirements. Under Section 1907.2 thereof, termed a “Final Acceptance,” the engineer on the job is required to “make a final inspection of the entire work, and he will certify in writing as to the said completion, after which he will prepare a final estimate containing quantities of each and every item of ivork performed by the Contractor.” Estimates upon which payments have been made “are partial estimates and are subject to correction in the final estimate.” Section 1908, labeled “Final Payment,” provides :

“Upon the execution of 'The Certificate of Final Acceptance’ by the contractor and his presentation of the written approval of the Surety or Sureties, the state will make final payment; * *

*447 The highway department has extensive and widespread activities to promote and protect. Within its large personnel are many men of special training and qualifications. Sums running into millions of dollars are annually spent in the maintenance and enlargement of its highway programs. In the language of the trial court:

* * What is involved is the efficient administration of a department of government. .
•X' 44 44 44 44
“* * * The public ‘authorities’ must ascertain the fact of the completion of the project; having determined that the project has been completed according to contract, they are in duty bound to accept it; having accepted the project they must ascertain the true value of the work and material furnished; and having arrived at an agreed figure for these items, they must be sure that there are no offsets, counterclaims or unfulfilled covenants; and after all the ‘foregoing’ have been checked agreeably to the contractor, the obligee and the surety, then the net amount due must be paid out of the highway fund.”

That plaintiff’s notice of claim was filed with the commissioner of insurance in the form required by statute is clearly shown. If timely filed, the demurrer should have been overruled. Upon timeliness of filing this action hinges. When did the 90-day period of limitation begin to run? Clearly, the statute requires both com pletion of the contract and acceptance of the job before the limitation begins.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Safety Signs, LLC v. Niles-Wiese Construction Co.
840 N.W.2d 34 (Supreme Court of Minnesota, 2013)
Safety Signs, LLC v. Niles-Wiese Construction Co.
820 N.W.2d 854 (Court of Appeals of Minnesota, 2012)
Spartan Mechanical, Inc. v. St. Paul Fire & Marine Insurance Co.
414 N.W.2d 476 (Court of Appeals of Minnesota, 1987)
Maxson Corp. v. Gary King Construction Co.
363 N.W.2d 901 (Court of Appeals of Minnesota, 1985)
Alexander Construction Co. v. C & H Contracting, Inc.
354 N.W.2d 535 (Court of Appeals of Minnesota, 1984)
A. J. Chromy Construction Co. v. Commercial Mechanical Services, Inc.
260 N.W.2d 579 (Supreme Court of Minnesota, 1977)
Mankato Citizens Telephone Co. v. Commissioner of Taxation
145 N.W.2d 313 (Supreme Court of Minnesota, 1966)
Elk River Concrete Products Co. v. American Casualty Co. of Reading
129 N.W.2d 309 (Supreme Court of Minnesota, 1964)
Elk River Concrete Products Co. v. American Cas. Co. of Reading
114 N.W.2d 655 (Supreme Court of Minnesota, 1962)
Stabs v. City of Tower
40 N.W.2d 362 (Supreme Court of Minnesota, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
16 N.W.2d 519, 218 Minn. 443, 1944 Minn. LEXIS 509, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wheeler-lumber-bridge-supply-co-v-seaboard-surety-co-minn-1944.