Safety Signs, LLC v. Niles-Wiese Construction Co.

820 N.W.2d 854, 2012 WL 4052886, 2012 Minn. App. LEXIS 107
CourtCourt of Appeals of Minnesota
DecidedSeptember 17, 2012
DocketNo. A12-0370
StatusPublished
Cited by1 cases

This text of 820 N.W.2d 854 (Safety Signs, LLC v. Niles-Wiese Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Safety Signs, LLC v. Niles-Wiese Construction Co., 820 N.W.2d 854, 2012 WL 4052886, 2012 Minn. App. LEXIS 107 (Mich. Ct. App. 2012).

Opinion

OPINION

BJORKMAN, Judge.

Appellant insurance company challenges the district court’s denial of summary judgment to appellant and grant of summary judgment to respondent subcontractor on respondent’s payment-bond claim. Because service of the notice of claim was defective, we reverse.

FACTS

The City of Owatonna hired Niles-Wiese Construction Company as the general con-. tractor for the construction of an airport runway and taxiway. Pursuant to Minn. Stat. § 574.26, subd. 2(2) (2010), Niles-Wiese obtained a payment bond from appellant Westfield Insurance Company. The payment bond — a contract between Westfield and the city — requires Westfield to pay subcontractors and materialmen for any work done pursuant to the general contract for which Niles-Wiese does not pay.

After Westfield issued the payment bond, Niles-Wiese entered into a subcontract with respondent Safety Signs, LLC to perform traffic-control and pavement-marking work on the airport project. In February 2009, Safety Signs sent a notice of payment-bond claim (notice) to Niles-Wiese and Westfield by certified mail. Safety Signs sent the notice to Niles-Wiese’s primary business address rather than the address listed on the payment bond, as required by Minn.Stat. § 574.31, subd. 2(a). Despite this failure to comply with the statute, both Niles-Wiese and Westfield acknowledged receipt of the notice, and Niles-Wiese paid the requested amount.

On January 7, 2010, Safety Signs sent noticé of another payment-bond claim to Niles-Wiese and Westfield by certified mail. As it did in February 2009, Safety Signs sent notice to Niles-Wiese’s primary business address. This time, the notice was returned as undeliverable. Westfield received its notice on January 11, 2010, and acknowledged receipt thereof. West-field refused to pay the claim even though it was undisputed that Safety Signs satisfactorily completed its work and Niles-Wiese failed to pay the full amount due to Safety Signs.

Safety Signs commenced this action seeking to recover the amount due under the subcontract plus interest. Westfield moved for summary judgment, asserting that the payment-bond claim fails because the notice was untimely and was not served on Niles-Wiese at the address listed on the payment bond. The district court denied this motion, reasoning that the notice was timely because it was mailed within the statutory notice period and failure to serve Niles-Wiese at the address listed on the payment bond was not fatal to Safety Signs’ claim. Safety Signs subsequently moved for summary judgment, which the district court granted, ordering Westfield to pay the amount due under the subcontract along with penalty interest, attorney fees, costs, and disbursements. This appeal follows.

ISSUES

I. Was Safety Signs’ notice timely because it was mailed, though not re[857]*857ceived, within the 120-day statutory period?

II. Was Safety Signs’ service of notice fatally defective because the notice was sent to Niles-Wiese’s primary business address rather than the address listed on the payment bond?

ANALYSIS

On appeal from summary judgment, this court reviews de novo whether there are genuine issues of material fact and whether judgment is appropriate as a matter of law. STAR Ctrs., Inc. v. Faegre & Benson, L.L.P., 644 N.W.2d 72, 76-77 (Minn.2002).

The Public Contractors’ Performance and Payment Bond Act (the bond statute) requires contractors to obtain payment bonds for public-works contracts. Minn.Stat. § 574.26, subd. 2(2). The purpose of the bond statute “is to protect laborers and materialmen who perform labor or furnish material for the execution of a public work to which the mechanics’ lien statute does not apply.” Nelson Roofing & Contracting, Inc. v. C.W. Moore Co., 310 Minn. 140, 144, 245 N.W.2d 866, 868 (1976) (quotation omitted). Recovery on a payment bond is conditioned upon the claimant providing timely notice of its claim to both the contractor and the surety. Minn. Stat. § 574.31, subd. 2(a).

I. Safety Signs’ service of notice was timely.

A payment-bond claim may not be maintained unless, “within 120 days after completion, delivery, or provision by the [claimant] of its last item of labor and materials, for the public work, the [claimant] serves written notice of claim under the payment bond personally or by certified mail upon the surety that issued the bond and the contractor.” Id. The 120-day deadline is strictly enforced. Edward Kraemer & Sons, Inc. v. Ashbach Constr. Co., 608 N.W.2d 559, 561, 563 (Minn.App. 2000) (holding that notice mailed 122 days after completion of work was untimely, without addressing whether service is effective upon mailing or upon receipt), review denied (Minn. June 13, 2000).

Westfield argues that Safety Signs’ service of notice — which was mailed but not received within 120 days after the completion of Safety Signs’ work — is untimely because service is effective upon receipt rather than upon mailing. We disagree. Although this presents an issue of first impression, we find instructive the supreme court’s holding that service of a mechanic’s lien notice is effective upon mailing. Eischen Cabinet Co. v. Hildebrandt, 683 N.W.2d 813, 818 (Minn.2004). The Eischen court reasoned that (1) the mechanic’s lien statute is remedial and should therefore be liberally construed in favor of the claimant; (2) the requirement that a mechanic’s lien notice be served personally or by certified mail makes little sense other than to ensure that the sender will have proof of the date of service; and (3)the rules of civil procedure and general legal authorities make service effective upon mailing in similar circumstances. Id. (citing Minn. R. Civ. P. 5.02; 66 C.J.S. Notice § 30(a) (1998)). Like the mechanic’s lien statute, the bond statute is remedial and should be liberally construed. Wheeler Lumber Bridge & Supply Co. v. Seaboard Sur. Co., 218 Minn. 443, 449, 16 N.W.2d 519, 522 (1944). And like the mechanic’s lien statute, the bond statute requires personal service or service by certified mail. Minn.Stat. §§ 514.08, subd. 1(2), 574.31, subd. 2(a) (2010).

Westfield asserts that because Minn.Stat. § 574.31, subd. 2(d) (2010), ties the period during which a surety must [858]*858object to a claimant’s request to extend the limitations period to the surety’s receipt of notice, we should construe the statute to make service effective upon receipt. But “distinctions in language in the same context are presumed to be intentional, and we apply the language consistent with that intent.” In re Stadsvold, 754 N.W.2d 323, 328-29 (Minn.2008). The fact that the legislature used the word “receipt” in subdivision 2(d) but omitted it in subdivision 2(a) indicates its intent not to make service under subdivision 2(a) effective upon receipt.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Safety Signs, LLC v. Niles-Wiese Construction Co.
840 N.W.2d 34 (Supreme Court of Minnesota, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
820 N.W.2d 854, 2012 WL 4052886, 2012 Minn. App. LEXIS 107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/safety-signs-llc-v-niles-wiese-construction-co-minnctapp-2012.