Elk River Concrete Products Co. v. American Cas. Co. of Reading

114 N.W.2d 655, 262 Minn. 310, 1962 Minn. LEXIS 711
CourtSupreme Court of Minnesota
DecidedApril 6, 1962
Docket38,484, 38,485, 38,486
StatusPublished
Cited by2 cases

This text of 114 N.W.2d 655 (Elk River Concrete Products Co. v. American Cas. Co. of Reading) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elk River Concrete Products Co. v. American Cas. Co. of Reading, 114 N.W.2d 655, 262 Minn. 310, 1962 Minn. LEXIS 711 (Mich. 1962).

Opinion

Thomas Gallagher, Justice.

Plaintiffs, Elk River Concrete Products Company, Sta-Vis Oil Company, and Northfield Iron & Culvert Company, all corporations, are claimants under separate public contractor’s bonds executed by defendant, American Casualty Company of Reading, Pennsylvania, a corporation, as surety, for and on behalf of H. J. Fredrickson, contractor in three separate highway contracts with the Department of Highways of the State of Minnesota, for unpaid charges for materials furnished Fredrickson under such contracts.

For its defense American Casualty Company, hereafter referred to as American, asserted that plaintiffs had not filed their respective claims within 90 days after the completion of the respective contracts and their acceptance by the proper public authorities as required under Minn. St. 574.31, which provides:

“No action shall be maintained on any such bond unless within 90 days after the completion of the contract and acceptance thereof by the proper public authorities, the claimant shall file a written notice specifying the nature and amount of his claim and the date of furnishing the last item thereof, * *

In support of this contention American relies upon certain specifications which form part of the contracts and which provide:

*312 “1907.4 Final Acceptance of the Project

“When an inspection by the Engineer shows that all work required by the Contract has been completed in accordance with the terms thereof, he will so certify and the Commissioner will forthwith accept the workmanship and materials in the entire Project and relieve the Contractor from any future responsibility therefor.” (Italics supplied.)

“1908 Final Payment

“After the Project has been accepted, the Engineer will prepare a final statement showing the quantities of each and every item of work performed by the Contractor. * * *

“Upon the execution of the ‘Certificate for Final Payment’ by the Contractor and his presentation of the written approval of the Surety or Sureties, the State will make final payment; * * (Italics supplied.)

Based upon the foregoing requirements, American contends that undisputed facts here compel a determination that the various contracts were completed and accepted on the date the final vouchers were submitted to the contractor by the Department of Highways in accordance with the specifications which clearly indicate the intent of the Department of Highways to accept the project; and that such final vouchers, together with the transmittal letters accompanying them, constituted the final expression by the Department of Highways of its acceptance of the contracts; or that in any event at least the acceptance would have been complete upon the expiration of 90 days from such events.

It is stipulated between the parties that in connection with the three contracts the Department of Highways had submitted final vouchers to H. J. Fredrickson, the contractor; that American had then consented in writing to final payment to the contractor of such vouchers; that in each of the contracts a final certificate executed by the project engineer, the district engineer, and the construction engineer, together with final reports, had been filed with the Department of Highways; that Fredrickson had never returned the final vouchers submitted to him to the Department of Highways; and that the state had never paid him the amount due thereon. It is also undisputed that the respective *313 claims of plaintiffs were not filed until long after 90 days from the occurrence of the events above described; but that in the interval plaintiffs made numerous inquiries of the Department of Highways to ascertain if the contracts had been accepted by the commissioner and on each of such occasions were advised that the contracts had not been accepted.

Based upon the stipulated facts, the trial court granted summary judgment for Elk River Concrete Products Company on its first and third causes of action; for Sta-Vis Oil Company on its two causes of action; and for Northfield Iron & Culvert Company on its first cause of action. In its memorandum opinion, the trial court set forth the following:

“It is clear that the ninety day period does not begin to run until there has been both the completion of the contract and the acceptance thereof by the proper public authorities. The statute does not further define either completion or acceptance.

* * ^ * ‡

“As is evidenced by the substantial number of exhibits which are attached to the stipulations, all of the details which were necessary to be completed before the final estimate was sent to the contractor were concluded. Likewise, it appears that all computations relating to the work done and materials used were made, partial payments which were made were deducted from the amount due and a final figure as far as the Highway Department was concerned were arrived at. The submission of the final voucher to the contractor pursuant to * * * the Specifications together with the itemized final statement of work performed certainly indicates the views of the Highway Department as to the entire quantity and value of each and every item performed under the contract. * * * There appears to be no disagreement between the parties that the contracts were completed and that the date of completion was no later than the time the final voucher was sent out by the Highway Department. The only issue remaining and the decisive one is when were the contracts accepted, if they were in fact accepted.

“American urges that everything relating to the contracts was done *314 and all that remained undone was the signature of the Commissioner or the Assistant Commissioner certifying that the contract was accepted. American contends that there was only a ministerial act remaining to be done. For an act to be solely ministerial it must be an act in which there is no discretion. * * * A casual examination of the provisions of M. S. A. 161.20 et seq. indicates that he is not a mere ministerial officer and his acts of approval or acceptance in matters conferred by law necessarily involve discretion. * * *

“It is further contended that in view of * * * the specifications there was a final acceptance of the contracts when the inspection by the engineer showed that all work required by the contract had been completed and the final voucher was submitted to the contractor. * * * that this follows because Section 1908 of the Specifications provides that final payment is to be made after the project has been completed and then provides the steps to be taken for such final payment. * * * that it follows that acceptance was in fact made when the final voucher was sent out to the contractor. * * * that if acceptance was not had then, then it was had after expiration of the ninety day period within which the contractor had to make adjustments. * * * Until the Highway Department determined what adjustments, if any, were to be allowed and what they represented in money, it is not reasonable to expect that the contract would be accepted by the Commissioner. * * * it would seem that acceptance of the project would not necessarily mean acceptance of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maxson Corp. v. Gary King Construction Co.
363 N.W.2d 901 (Court of Appeals of Minnesota, 1985)
Elk River Concrete Products Co. v. American Casualty Co. of Reading
129 N.W.2d 309 (Supreme Court of Minnesota, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
114 N.W.2d 655, 262 Minn. 310, 1962 Minn. LEXIS 711, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elk-river-concrete-products-co-v-american-cas-co-of-reading-minn-1962.