United States Fidelity & Guaranty Co. v. Couch, Inc.

472 So. 2d 614, 1985 Ala. LEXIS 3591
CourtSupreme Court of Alabama
DecidedApril 5, 1985
Docket83-1027, 83-1028
StatusPublished
Cited by1 cases

This text of 472 So. 2d 614 (United States Fidelity & Guaranty Co. v. Couch, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fidelity & Guaranty Co. v. Couch, Inc., 472 So. 2d 614, 1985 Ala. LEXIS 3591 (Ala. 1985).

Opinion

BEATTY, Justice.

Appeals by defendants, Harrington Construction Corporation (Harrington) and United States Fidelity & Guaranty Company (USF & G), from judgments for the plaintiff, Couch, Inc., in the plaintiff’s action brought to recover money damages, interest, and attorneys’ fees under a payment bond. We reverse and remand.

On October 16, 1981, Harrington entered into a contract with the City of Samson, Alabama, under which Harrington was engaged to make certain sewer improvements. On that same date, Harrington contracted with USF & G for a surety bond to insure payment on the project. This payment bond, executed on a Farmers Home Administration form, designated Harrington as principal and USF & G as surety, binding them to the City of Samson, as owner, and the United States of America, as government, and “unto all persons, firms, and corporations who or which may furnish labor, or who furnish materials to perform as described under the contract.” Later, on November 17, 1982, Harrington subcontracted with Couch, Inc., for the paving work required under Harrington’s contract with the City.

On December 22, 1982, Couch notified Harrington of its completion of the paving work and requested payment of $18,890. Payment was not made, and Couch again requested payment on March 31, 1983. Harrington neither responded nor made payment.

[615]*615Couch, on April 8, 1983, made a claim for payment upon USF & G by letter, with copies of the claim being sent to Harrington and the City of Samson. USF & G received the claim on April 12, 1983. Then, Couch filed this action on April 20, 1983, for breach of contract against Harrington and USF & G.

Following the denial of the defendants’ motion to dismiss, USF & G made a formal offer to allow judgment against it in the amount of $18,890. This amount was paid into court. Couch refused this offer, because it did not include an amount representing interest and attorneys’ fees. Partial summary judgment was then granted to Couch, with the amount of attorneys’ fees reserved for jury determination. A jury returned a verdict in favor of Couch for attorneys’ fees in the amount of $4,500. Harrington and USF & G appeal from the judgments entered upon that verdict. Couch has filed in this Court, under Rule 21(c), A.R.A.P., its petition for additional attorneys’ fees of $750 for services on this appeal.

It is important to observe that the contract made by the City of Samson and Harrington was one with a political subdivision for public works; therefore, Code of 1975, § 39-1-1, came into play:

“(a) Any person, firm or corporation entering into a contract with the state or any county or municipal corporation or subdivision thereof in this state for the repair, construction or prosecution of any public buildings or public work, highways or bridges shall be required, before commencing such work, to execute a performance bond, with penalty equal to 100 percent of the amount of the contract price, and, in addition thereto, another bond with good and sufficient surety, payable to the state, county or municipal corporation or subdivision letting the contract, in an amount not less than 50 percent of the contract price, with the obligation that such contractor or contractors shall promptly make payments to all persons supplying him or them with labor, materials or supplies for or in the prosecution of the work provided for in such contract and for the payment of reasonable attorneys’ fees incurred by successful claimants or plaintiffs in civil actions on said bond.
“(b) Any person, firm or corporation that has furnished labor, materials or supplies for or in the prosecution or repair of any public building or public work, highways or bridges and payment for which has not been made shall be authorized to institute a civil action upon said bond in his or their name or names and to have their rights and claims adjudicated in such civil action and judgment entered thereon; provided, that no civil action shall be instituted on said bond until after 4-5 days’ written notice to the surety thereon of the amount claimed to be due and of the nature of the claim. Such civil action shall be commenced not later than one year from the date of final settlement of said contract. The giving of said notice by registered or certified mail, postage prepaid, addressed to the surety at any of its places of business or offices shall be deemed sufficient under this section. In the event the surety or contractor fails to pay such claim in full within 45 days from the mailing of such notice, then such person or persons shall be entitled to recover of the contractor and surety, in addition to the amount of said claim, a reasonable attorneys’ fee, together with interest on such claim from the date of such notice.” (Emphasis added.)

USF & G and Harrington do not deny that Couch is owed the $18,890 for work it completed. Their argument here is that Couch did not give the notice required by the above-quoted statute before bringing this civil action, and thus it was error to allow the interest and attorneys’ fees allowed by § 39-1-1.

On the other hand, Couch argues that because § 39-1-1 was not expressly incorporated in either the Samson-Harrington contract or the Harrington-Couch contract, it does not control. Rather, Couch main[616]*616tains that its contract with Harrington and the terms of the payment bond between Harrington and USF & G control.

The contract between Harrington and Couch contains this language:

“Payment to be made as follows:
“Monthly Estimates — Payment is due within 15 days of receipt of monthly estimate. Final retainage is due within 15 days of acceptance of job. Interest will accrue from the due date at the rate of 1½% per month (18% per annum).”

This provision was followed by an “Acceptance of Proposal,” which contained the following:

“(Should the undersigned fail to pay this indebtedness, or any part thereof, when due, the entire unpaid balance shall become due and payable; in which case the undersigned [Harrington] agrees to pay all cost of collecting, including a reasonable attorney's fee, plus interest at 1½% per month (18% per year) from due date.)”

As to the notice argument of Harrington and USF & G, Couch counters that the payment bond of USF & G itself specified how and to whom notice was to be given, viz.:

“PROVIDED, that beneficiaries or claimants hereunder shall be limited to the SUBCONTRACTORS, and persons, firms, and corporations having a direct contract with the PRINCIPAL or its SUBCONTRACTORS.
“PROVIDED FURTHER, that no suit or action shall be commenced hereunder by any claimant: (a) Unless claimant, other than one having a direct contract with the PRINCIPAL ... shall have given written notice to any two of the following: the PRINCIPAL, the OWNER, or the SURETY above named within ninety (90) days after such claimant did or performed the last of the work or labor_” (Emphasis added.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barber v. Barber
684 So. 2d 150 (Court of Civil Appeals of Alabama, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
472 So. 2d 614, 1985 Ala. LEXIS 3591, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fidelity-guaranty-co-v-couch-inc-ala-1985.