Groendyke Transport, Inc. v. Merchant

1962 OK 32, 380 P.2d 682, 1962 Okla. LEXIS 549
CourtSupreme Court of Oklahoma
DecidedFebruary 6, 1962
Docket39264
StatusPublished
Cited by22 cases

This text of 1962 OK 32 (Groendyke Transport, Inc. v. Merchant) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Groendyke Transport, Inc. v. Merchant, 1962 OK 32, 380 P.2d 682, 1962 Okla. LEXIS 549 (Okla. 1962).

Opinion

HALLEY, Justice.

Hal Merchant (plaintiff) and Groendyke Transport, Inc. (defendant) entered into a written agreement whereby plaintiff leased certain motor vehicle equipment to defendant for a term of five years beginning July 1, 1957. The parties made a simultaneous oral agreement for a like term whereby plaintiff would serve as defendant’s representative and terminal manager at Duncan, Oklahoma. Plaintiff’s income was provided for in the written agreement as a certain percent of the gross revenue produced by plaintiff’s equipment less expenses of operating the equipment.

Under date of May 29, 1958, defendant wrote a letter to plaintiff terminating the written and oral agreements as of July 1, 1958. Plaintiff received income in the form of net profits under the terms of the written agreement to July 1, 1958. Shortly thereafter he filed suit for damages 'for the breach of contract by defendant. • In his amended petition he sued for $93,544.96 on his first cause of action for loss of'future profits, and he sued for $57,629.57 as a second cause of action for loss suffered in selling his motor vehicle equipment.

Jury was waived and the action tried to the court. Judgment was entered in favor of plaintiff on his first cause of action for $84,989.32 and in favor of defendant on plaintiff’s second cause of action. Each party filed a motion for. new trial which motions were overruled. Plaintiff did not appeal, but defendant appealed from the judgment and order overruling its motion for new trial.

We find that the contract between plaintiff and defendant was partly oral and partly written. The parties here agree that such a contract is valid and will be enforced. We have said as much in Packard Oklahoma Motor Co. v. Funk, 117 Okl. 96, 245 P. 571:

“ * * * There can be no question about the right of parties to enter into> an oral contract, a written contract, or a contract partly in writing and partly parol.”

Defendant states that the trial court erred in allowing plaintiff to recover judgment when the evidence indicates that plaintiff breached the contract first by neglecting to perform the duties as terminal manager. Overlooked by defendant is the evidence which plaintiff presented to dispute this. Defendant’s letter to plaintiff terminating the contractual relationship made no specific reference to plaintiff’s performance of assigned tasks but simply said that the termination was “for economic reasons and for other reasons.” Plaintiff immediately contacted defendant’s executive vice-president and general manager who advised him that he (plaintiff) “was carrying on the work all right” and “was a good man,” but that defendant had decided to move its own trucks and manager into the location.

Whether plaintiff himself breached the contract was a question of fact for the trial judge in this jury-waived case. His general finding in favor of plaintiff indicates he found against defendant on this *684 issue. We find that there was competent evidence tending to support the judgment and that there was no prejudicial error. See cases cited in 2A Okl.Dig., Appeal and Error, ®=>1008(2).

Defendant next contends that the trial court failed to give effect to paragraph number three of the written lease agreement which provided as follows:

“3. That Lessee is engaged in the transportation of petroleum and petroleum products and other commodities in hulk, and operates other equipment similar to that hereby leased, and the business of Lessee fluctuates from time to time, so that it may not be possible, or practical, at times to keep all equipment in operation to the extent of its maximum utilization; but that so far as the equipment hereby leased is concerned, the Lessee will attempt to keep it in operation on a reasonably pro-rata basis, talcing into consideration the total number of units it has in operation, the sum total volume of business available, and the areas in which it operates.”

Defendant presented evidence that plaintiff’s equipment on a per unit basis created gross income of approximately twice the per unit average of the remainder of the units owned and operated by defendant. Attempt is then made to analyze plaintiff’s net income under the first year of the contract to show that if his equipment were used on a pro-rata basis during the remaining four years of the contract term, plaintiff would realize little, if any, net income.

This line of reasoning would be well and good if plaintiff and defendant had closely adhered to paragraph three of the written agreement during the first year. This they did not do. Nor did the contract require them to do so. It provided only that defendant should “attempt to keep it (equipment) in operation on a reasonably pro-rata basis.” The trial court could properly find that the method of pro-rating to be considered in awarding damages for the four years following the breach would, be the same as that actually used by the parties during the first year’s operations. Defendant cites many cases, but none are in point on the facts and we are not persuaded by defendant’s argument that the trial court erred in failing to use defendant’s theory on this phase of the case.

Defendant’s final contention relates to the amount of damages allowed by the trial court. The evidence of net profits to the plaintiff under this contract and a previous one with defendant might indicate that plaintiff’s profits were declining. For example during the calendar years of 1956 and 1957 plaintiff’s net profits were $26,005.65 and $20,786.83 respectively. Other evidence establishes that net profits in such an enterprise are subject to fluctuation, both up and down. Plaintiff argues with just as much validity that such figures merely indicate a criterion or yardstick by which to measure his loss of future profits. In that light, they indicate an average net profit of $23,396.24 per year during the last two calendar years before the breach. Defendant’s own evidence proved that plaintiff's net profit during the one year under the contract here in controversy from July 1, 1957, to June 30, 1958, was $23,347.33. Such a figure is strikingly close to the annual average figure proved by plaintiff.

Defendant believes the trial court relied on conjecture and speculation in reaching a decision as to the amount of damages and thereby erred. Defendant relies solely on Syllabus 3 of the Court in Bokoshe Smokeless Coal Co. v. Bray et al., 55 Okl. 446, 155 P. 226:

“As a general rule, anticipated profits of a commercial or other like business are too remote, speculative, and dependent upon uncertainties and changing circumstances to warrant a judgment for their loss. The exception to this rule is that the loss of profits from the destruction or interruption of an established business may be recovered where it is made reasonably certain by competent proof *685 what the amount of the loss actually is; and such damages must be established, not by guess work, conjectures, uncertain estimates, nor mere •conclusions, but by tangible facts from which actual damages may be logically and legally shown or inferred.”

We have analyzed the Bokoshe case, supra, in connection with a similar argument in Johnson Oil Refining Co. of Illinois v. Elledge, 175 Okl. 496, 53 P.2d 543:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PARSIA v. JOHN E. BARBRE TRUST
2021 OK CIV APP 36 (Court of Civil Appeals of Oklahoma, 2021)
Digital Design Group, Inc. v. Information Builders, Inc.
2001 OK 21 (Supreme Court of Oklahoma, 2001)
Florafax International Inc. v. GTE Market Resources, Inc.
1997 OK 7 (Supreme Court of Oklahoma, 1997)
Bane v. Anderson, Bryant & Co.
786 P.2d 1230 (Supreme Court of Oklahoma, 1989)
Withrow v. Red Eagle Oil Co.
755 P.2d 622 (Supreme Court of Oklahoma, 1988)
W.L. Scott, Inc. v. Madras Aerotech, Inc.
653 P.2d 791 (Idaho Supreme Court, 1982)
Ferrell Construction Co. v. Russell Creek Coal Co.
1982 OK 24 (Supreme Court of Oklahoma, 1982)
Indemnity Marine Assurance Co. v. Lipin Robinson Warehouse Corp.
297 N.W.2d 846 (Michigan Court of Appeals, 1980)
B & B Lines, Inc. v. Ryan Freight Lines, Inc.
601 P.2d 1207 (Court of Civil Appeals of Oklahoma, 1979)
Osborn v. Commanche Cattle Industries, Inc.
545 P.2d 827 (Court of Civil Appeals of Oklahoma, 1975)
Industrial Leasing Corporation v. Thomason
532 P.2d 916 (Idaho Supreme Court, 1974)
Renfroe v. Preferred Risk Mutual Insurance Company
296 F. Supp. 1137 (N.D. Oklahoma, 1969)
Antonio v. General Outdoor Advertising Co.
1966 OK 81 (Supreme Court of Oklahoma, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
1962 OK 32, 380 P.2d 682, 1962 Okla. LEXIS 549, Counsel Stack Legal Research, https://law.counselstack.com/opinion/groendyke-transport-inc-v-merchant-okla-1962.