Withrow v. Red Eagle Oil Co.

755 P.2d 622, 1988 WL 13738
CourtSupreme Court of Oklahoma
DecidedMarch 2, 1988
Docket62382, 63491 and 63632
StatusPublished
Cited by38 cases

This text of 755 P.2d 622 (Withrow v. Red Eagle Oil Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Withrow v. Red Eagle Oil Co., 755 P.2d 622, 1988 WL 13738 (Okla. 1988).

Opinion

HODGES, Justice.

Appellants Red Eagle Oil Company (Red Eagle) and Harry C. Johnson (Johnson) seek vacation of an unpublished opinion by the Court of Appeals, Division No. 1, affirming a judgment of the district court on a jury’s verdict awarding appellees Jon R. Withrow, Herbert H. Holmes, David A. Bash, Jr., Darnell Oil Corporation, Ann Caylor, James W. Caylor, Susan M. Holmes and Sundance Oil Company (co-owners) $360,940 in damages for permanent loss of production due to well damage from an oil and gas well operated by Red Eagle, $669,-575 in damages for loss of use of money, and $4,300.65 as reimbursement for appel-lees’ share of the costs of the commingling operation. Appellees were additionally awarded $2,008.34 in costs and $177,420 in attorney’s fees against Red Eagle only. Johnson, president of Red Eagle, was granted judgment against appellees and was awarded $1,770.88 in costs and $57,-895.75 in attorney's fees against appellees. Appellees co-owners also petition for certio-rari challenging the award of attorney’s fees in Johnson’s favor.

We grant appellants’ petition for certio-rari solely on the issue concerning the award of damages for loss of use of money. In all other respects review by certio-rari is denied. The dispositive issue is whether co-owners are entitled to recover for loss of use of money as an element of their actual damages measured by interest, at prime rate compounded every six months, on the amount of money they allege they would have received from sales of oil and gas from the W.O.R. No. 1 Well but for appellants’ alleged gross negligence. For the reasons that follow we vacate the opinion of the Court of Appeals and reverse the judgment of the trial court with respect to the damages awarded for loss of use of money.

Co-owners complained of certain actions of Red Eagle which amounted to a breach of duties as unit operator. Red Eagle mis-located the well drilled under a location exception order of the Oklahoma Corporation Commission which resulted in two penalties placed on production from October 1979 through October 1981. The first penalty on production was not followed by Red Eagle which resulted in the imposition of the second penalty. Appellees also alleged gross negligence and intentional misconduct in Red Eagle’s commingling operation of the Red Fork and Mississippi Solid formations which was performed in August 1980. Co-owners assert if Red Eagle had not breached the joint operating agreement, they would have had use of the income on their share of production valued at over $1,000,000 which they would have received between January 1980 through December 1982. They contend the $669,575 award for loss of use of money merely compensates them for the delay in receiving that income. The Court of Appeals stated:

“The damages awarded by the jury for loss of use of income is the measure of Appellees’ lost profits computed by discounting the present value of the production which would have been obtained but for Red Eagle’s conduct. Appellees did not seek nor have they recovered prejudgment interest but rather sought and recovered damages proximately caused by Red Eagle’s breach of the contract which were within the contemplation of the parties at the time the contract was entered into. Such damages can only be valued in relation to the time value of money, commonly referred to as ‘interest’.”

In affirming the trial court’s computation of loss of use of money, which was interest on the value of lost production at prime rate, compounded from the date of loss to the date of trial in September 1984, the Court of Appeals ruled:

“In the present case, the awarded damages arising from Appellants’ actions *624 must make the Appellees whole and therefore the rate of interest to be considered in computing present value must be compounded to achieve making the Appellees whole, i.e., Plaintiffs could have expected compounded interest on a safe investment in this locality.”

Appellants’ petition for certiorari challenges these conclusions. They assert the Court of Appeals mischaracterized the loss of use damages as “damages for the time value of the income they would have received but for Red Eagle’s breach of contract.” Appellants’ principal contention is that appellees’ award of loss of use damages constitutes an impermissible award of prejudgment interest in derogation of 23 O.S.1981 § 6. Section 6 provides:

“Any person who is entitled to recover damages certain, or capable of being made certain by calculation, and the right to recover which is vested in him upon a particular day, is entitled also to recover interest thereon from that day, except during such time as the debtor is prevented by law, or by the act of the creditor from paying the debt.”

Co-owners in opposition argue that § 6 does not prohibit the computation of the actual damage sustained by reference to an interest rate as distinguished from prejudgment interest which applies interest to the damage award itself. They point to the distinction between interest allowed by statute or agreement as compensation for use or detention of money and interest as an element of damages necessary to compensate a plaintiff for all the detriment proximately caused by a defendant’s actions. Co-owners seek to uphold the trial court’s award upon the authority of 23 O.S.1981 § 21, 1 Groendyke Transport, Inc. v. Merchant, 380 P.2d 682 (Okla.1963); Gallaspy v. Warner, 324 P.2d 848 (Okla.1958) and Cavnar v. Quality Control Parking, Inc., 696 S.W.2d 549 (Tex.1985). They contend the award of loss of use of income damages was an award for the actual damage resulting from Red Eagle’s breach of the operating agreement, not an award of prejudgment interest upon damages. We are unpersuaded by co-owners’ arguments.

As the United States Supreme Court said in Library of Congress v. Shaw, 478 U.S. 310, 321, 106 S.Ct. 2957, 2965, 92 L.Ed.2d 250, 262 (1986):

“In the alternative, respondent argues that the no-interest rule does not prohibit the award of compensation for delay. But the force of the no-interest rule cannot be avoided simply by devising a new name for an old institution:
‘The character or nature of ‘interest’ cannot be changed by calling it ‘damages’, ‘loss’, ‘earned increment’, ‘just compensation’, ‘discount’, ‘offset’, or ‘penalty’, or any other term, because it is still interest and the no-interest rule applies to it.’

We see no distinction in awarding interest as damages and prejudgment interest as interest. “Prejudgment interest serves to compensate for the loss of use of money due as damages from the time the claim accrues until judgment is entered, thereby achieving full compensation for the injury those damages are intended to redress.” 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

KRUG v. HELMERICH & PAYNE, INC.
2015 OK 74 (Supreme Court of Oklahoma, 2015)
Yousuf v. Cohlmia
741 F.3d 31 (Tenth Circuit, 2014)
Estate of Bleeker v. Bleeker
2013 OK CIV APP 106 (Court of Civil Appeals of Oklahoma, 2013)
Pinnacle Rehabilitation Hospital v. Rivera-Villareal
2008 OK CIV APP 115 (Court of Civil Appeals of Oklahoma, 2008)
Bird Construction Co. v. Oklahoma City Housing Authority
2005 OK CIV APP 12 (Court of Civil Appeals of Oklahoma, 2004)
State Ex Rel. State Insurance Fund v. Accord Human Resources, Inc.
2003 OK 109 (Supreme Court of Oklahoma, 2003)
Johnson v. Ford Motor Co.
2002 OK 24 (Supreme Court of Oklahoma, 2002)
Cable v. State ex rel. Oklahoma Police Pension & Retirement Board
2001 OK CIV APP 99 (Court of Civil Appeals of Oklahoma, 2001)
Cable v. POLICE AND PENSION RETIREMENT BD.
2001 OK CIV APP 99 (Court of Civil Appeals of Oklahoma, 2001)
Morava v. Central Oklahoma Medical Group, Inc.
2001 OK CIV APP 84 (Court of Civil Appeals of Oklahoma, 2001)
Chesapeake Operating, Inc. v. Valence Operating Co.
193 F.3d 1153 (Tenth Circuit, 1999)
Taylor v. State Farm Fire & Casualty Co.
1999 OK 44 (Supreme Court of Oklahoma, 1999)
Pierce Couch Hendrickson Baysinger & Green v. Freede
936 P.2d 906 (Supreme Court of Oklahoma, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
755 P.2d 622, 1988 WL 13738, Counsel Stack Legal Research, https://law.counselstack.com/opinion/withrow-v-red-eagle-oil-co-okla-1988.