Ferrell Construction Co. v. Russell Creek Coal Co.

1982 OK 24, 645 P.2d 1005, 1982 Okla. LEXIS 207
CourtSupreme Court of Oklahoma
DecidedFebruary 16, 1982
Docket53774
StatusPublished
Cited by55 cases

This text of 1982 OK 24 (Ferrell Construction Co. v. Russell Creek Coal Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ferrell Construction Co. v. Russell Creek Coal Co., 1982 OK 24, 645 P.2d 1005, 1982 Okla. LEXIS 207 (Okla. 1982).

Opinion

LAVENDER, Justice:

Russell, owner of a forty acre coal mining lease in Craig County, Oklahoma, entered into a Strip Mining Agreement in writing as of September 3,1977, with Ferrell pursuant to which Ferrell was to remove the overburden, extract the coal, and load it for $.50 per bank yard for the overburden, $.30 per ton for the coal stockpiled for subsequent loading, and a sum equal to Ferrell’s documented cost of blasting.

In preparation for the excavation to remove the overburden and prior to September 15, 1977, Ferrell performed the following which were required of it under the contract: started the procurement of the mining permit; made contacts to obtain approval of reclamation and wage bonds; started trying to locate a mining office to place on the site; procured the required insurance coverage; and procured a scraper and bulldozer.

Mr. Ferrell testified that while waiting for the mining plan which was under the contract to be furnished by Russell, he had a telephone conversation on September 12, 1977, with a representative of Russell in which the representative discussed cancellation of the contract and demanded “good faith” demonstration of performance as an alternative. Thereafter, and over a span of a week or ten days, Ferrell cleared off the vegetation on the lease, built a mining road *1007 and installed a 30-inch culvert, hauled a building to the site, and hauled in machinery.

It was not until September 30,1977, that Russell furnished a mining plan.

It was at this stage that Russell wrote a letter to Ferrell dated October 14,1977, and delivered to Ferrell on October 17, 1977, in which Russell declared the Strip Mining Agreement cancelled, and declared null and void, “pursuant to the terms of said Strip Mining Agreement as contained in Section 1 thereof.”

Thereupon, Ferrell filed suit against Russell for damages for breach of the contract, in which Ferrell sought to recover the profits it claimed it would have made had it been permitted to perform the contract in its entirety. A jury verdict was returned in favor of Ferrell, and a judgment was entered in Ferrell’s favor in the sum of $135,-850 and costs. Both parties appealed.

The provisions of the Strip Mining Agreement which are critical to the determination of the issues presented on appeal are set forth, as follows:

(Recitation Clause) “WHEREAS, Russell Creek estimates that there are approximately 45,000 tons of merchantable coal in and under the real estate covered by the Niksch Lease and approximately one million cubic yards of overburden which must be removed in order to strip mine said coal, .... ”
******
“1. Mining Area and Commencement of Mining
“The Niksch Lease is presently in force and the real estate subject to the Niksch Lease is currently available for mining by Russell Creek. The Contractor shall commence mining work on the lands covered by the Niksch Lease (said land herein called the ‘Mining Area’) immediately. If mining is not commenced by September 15, 1977, this contract will be considered null and void.
******
“2. Work to be Done by Contractor “The Contractor shall furnish all labor, equipment and materials necessary to perform the following operations on the Mining Area (said operations herein called the ‘Work’):
“(a) Contractor shall excavate, mine and remove all merchantable, stripable coal to maximum depth from the natural surface of the ground to the bottom of the coal that, in the opinion of Russell Creek, can be practically, economically and profitably strip mined from the Mining Area. In doing the work Contractor shall proceed according to the mining plan of Russell Creek for the Mining Area and Contractor shall rely upon the geological information submitted by Russell Creek, and, unless otherwise directed by Russell Creek, the Contractor shall mine coextensive with the boundaries of the Mining Area as limited by the physical features of the terrain to be mined.”

We will first consider whether Ferrell’s preliminary preparations for excavation performed prior to September 15,1977, constituted the commencement of mining work within the meaning of § 1 of the agreement. This, in turn, requires the initial determination of whether the contract is ambiguous.

Whether a contract is ambiguous so as to require extrinsic evidence to clarify the ambiguity is purely one of law for the court, 1 and the construction of an unambiguous contract is a matter of law for the court. 2 As this court said in National Ins. Underwriters v. Walker, 3 (at p. 740):

“Our statutory law on interpretations of contracts are expressive of the wisdom of the common law and furnish us rules *1008 here applicable. Among such rules we find that ‘intent controls,’ ‘that language governs,’ ‘that intention is ascertained from the writing,’ ‘that effect should be given every part,’ ‘interpretation favors validity,’ ‘words to be taken in their ordinary sense,’ ‘technical words to (be) used as understood by the profession,’ ‘repug-nancy should be reconciled and that if there is uncertainty the language must be construed most strongly against the person causing the uncertainty’ * * *.”

While the word “mine” or “mining” is a broad term of imprecise meaning and unenlightening as to its import when considered apart from its contextual usage, 4 the words “commence mining work” and “if mining is not commenced” take on a more precise and illuminating meaning when used in a mining lease. In Cromwell v. Lewis, 5 it was held that locating an oil and gas well, the digging of the cellar, the hauling of 15 or 18 loads of derrick timber onto the site with more materials in transit prior to July 1, 1922, constituted compliance with a lease requirement that “The time for beginning a test well as provided in the contract hereto attached is hereby extended until July 1, 1922,” as against the contention that the drilling bit should be actually piercing the earth before July 1, 1922. And, in Stoltz, Wagner & Brown v. Duncan, 6 it was held that the location of the well, the filing of an intent to drill with the Oklahoma Corporation Commission, the starting of location or dirt work and the moving of a bulldozer to the site constituted the “commencement” of a well.

We see no distinction in law or logic between the mining of hard minerals and the mining of an oil or gas deposit which would vary the meaning of “commencement” under the law pertaining to minerals.

We therefore hold that § 1 of the Strip Mining Agreement was unambiguous, that Ferrell had “commenced” mining before September 15,1977, as a matter of law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morgan v. Sewell
S.D. Mississippi, 2024
QuikTrip Corp. v. Abatement Systems, Inc.
2012 OK CIV APP 54 (Court of Civil Appeals of Oklahoma, 2012)
Ferguson Advisors, LLC v. Malherbe
2012 OK CIV APP 33 (Court of Civil Appeals of Oklahoma, 2011)
Romine v. Pense
2011 OK 26 (Supreme Court of Oklahoma, 2011)
In Re Estate of Metz
2011 OK 26 (Supreme Court of Oklahoma, 2011)
McKissick v. Yuen
618 F.3d 1177 (Tenth Circuit, 2010)
Eagle Bluff, L.L.C. v. Taylor
2010 OK 47 (Supreme Court of Oklahoma, 2010)
Ahlschlager v. LAWTON SCHOOL DIST.
2010 OK 41 (Supreme Court of Oklahoma, 2010)
Capron & Edwards P.C. v. Holden & Carr, P.C.
331 F. App'x 563 (Tenth Circuit, 2009)
Bird Construction Co. v. Oklahoma City Housing Authority
2005 OK CIV APP 12 (Court of Civil Appeals of Oklahoma, 2004)
Ryan v. Ryan
2003 OK CIV APP 86 (Court of Civil Appeals of Oklahoma, 2003)
Oneok, Inc. v. Ming
1998 OK 79 (Supreme Court of Oklahoma, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
1982 OK 24, 645 P.2d 1005, 1982 Okla. LEXIS 207, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ferrell-construction-co-v-russell-creek-coal-co-okla-1982.