Griswold v. County of Ramsey

65 N.W.2d 647, 242 Minn. 529, 1954 Minn. LEXIS 670
CourtSupreme Court of Minnesota
DecidedJuly 23, 1954
Docket36,337
StatusPublished
Cited by50 cases

This text of 65 N.W.2d 647 (Griswold v. County of Ramsey) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Griswold v. County of Ramsey, 65 N.W.2d 647, 242 Minn. 529, 1954 Minn. LEXIS 670 (Mich. 1954).

Opinion

Matson, Justice.

Several of the defendants appeal from a summary judgment for the plaintiffs permanently enjoining the defendants from proceeding with the construction of a new jail.

*531 The county board of Bamsey county in November 1952, as part of the 1953 budget, appropriated the sum of $600,000 for the building of a new county jail. Bids were advertised for on the basis of prepared plans and specifications. On August 3, 1953, when all bids were opened, it was discovered that even the lowest bid was considerably in excess of the $600,000 available for the construction of the jail. Consequently all bids were rejected.

A new request for bids was then submitted in which each bidder was asked to state his basic bid and also to indicate to what extent the basic bid would be reduced in the event the county board decided to eliminate certain construction work, such as the finishing of the fourth floor and construction of a tunnel to the courthouse, and further, if the board substituted certain cheaper building materials and equipment or made certain changes in structural design. In addition to these alternative bids directed to a decrease in cost, each bidder was also asked to indicate in what amount the basic bid would be increased if certain alternative items of a more expensive nature were substituted or added. These alternative proposals, by way of either deductions or additions to the basic bid, are for convenience referred to herein as the alternatives.

The request for bids contained the following significant provision:

“The Owner also reserves the right to accept or reject any of the alternate proposals witMn six (6) months as outlined in the specifications and as shown on the plans, from the date of the award of the contract, at prices quoted and shown on this proposal form.” (Italics supplied.)

The purpose of the foregoing provision was to enable the county board to bring the construction cost of the jail for the time being within the amount of the funds available. In other words the alternative bids would enable the county board to proceed with the construction of a part of the jail and to complete it later when funds became available.

When the new bids for the general construction, plumbing and heating, electrical, and other work were received on October 5,1953, several of the alternative deductions were subtracted from the basic *532 hid in order to arrive at contract figures which did not exceed the money available. The low bidders were determined by first deducting from the basic bids the alternative deductions whereby certain parts of the building were eliminated from the contract. On October 26, 1953, contracts were awarded to defendants Hagstrom Construction Company, Commonwealth Electric Company, and Healy Plumbing and Heating Company in the sum total of $573,370.

By the six-month-delayed-action provision above quoted, the board could within six months after the award require the successful bidders to complete the alternative items which had been deducted at the prices each successful bidder had quoted. It is undisputed that this delayed action provision or option for finishing and other work was formulated in anticipation of a future appropriation to the jail fund within six months which would permit the board to contract for such remaining work. On November 16, 1953, the budget for 1951 was approved and it contained an additional $210,000 appropriation for the building of the jail.

At this same meeting, apparently to forestall the effect of this suit commenced on November 1, 1953, by the plaintiff Kenneth P. Griswold, a taxpayer, to declare the contracts entered into void and to permanently enjoin the defendant county and contractors from proceeding with the work, the board took action to reject all the alternative bids which had been deducted from the successful basic bids. By this action the board abandoned any right or intention to require the successful bidders to complete the alternative items as provided for under the six months’ provision above quoted. In short the board sought to defeat the purpose of the Griswold action by asking for new bids on the alternative items.

Another action was then commenced by plaintiff Alois D. Kennedy, another taxpayer, who was permitted to intervene. The defendant county then moved for summary judgment and such procedure was agreed to by all the parties. On December 28, 1953, the trial court ordered judgment in plaintiffs’ favor permanently enjoining the defendants from proceeding with the construction of the jail as *533 provided for by the resolutions of the county board. This appeal is from the judgment entered thereon.

Although there is such a provision relating to contracts for the purchase of goods, materials, or supplies, no statutory provision applicable to Ramsey county requires the county board to advertise for bids and to let the contract to the lowest responsible bidder when contracting for the construction of a county jail or any other building. L. 1949, e. 180; M. S. A. 375.21, subd. 2. Without any apparent rational basis for making a distinction between the 85 smaller counties and the two larger ones, the legislature has expressly provided that no county with less than 75,000 population (§ 375.21, subd. 1) and no county with more than 75,000 and less than 225,000 population (§ 375.21, subd. 3) may make a contract for work or labor or for the construction of buildings without first advertising for bids and awarding the contract to the lowest responsible bidder. Section 375.21, subd. 2, however, which applies only to counties with a population of more than 225,000, expressly requires bids only for contracts for the purchase of goods, materials, or supplies and makes no mention whatever of contracts for the construction of buildings. This express omission is likewise true of L. 1949, c. 180, which applies to counties of more than 300,000 and less than 450,000 inhabitants and apparently was enacted to apply particularly to Ramsey county. L. 1951, c. 556, applicable to Hennepin county, similarly requires competitive bidding only for the purchase of goods, materials, supplies, and equipment and makes no mention of the construction of buildings. Ridiculous and unreasonable as it is today to permit any municipal body under ordinary conditions, and in the absence of any emergency, to construct large buildings without advertising for bids, the legislature has seen fit to exempt the two larger counties from such requirement. The language of both § 375.21, subd. 2, and L. 1949, c. 180, is plain in limiting the competitive-bid requirement to contracts for the purchase of goods, materials, or supplies, and such language does not by any reasonable standard of interpretation include contracts for constructing build *534 ings. 2 The statute is restrictive and should not be extended beyond the language used in it. In Otter Tail Power Co. v. Village of Elbow Lake, 234 Minn. 419, 428, 49 N. W. (2d) 197, 203, 27 A. L. R. (2d) 906, a similar distinction was drawn as to the bidding statutes applicable to villages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rochester City Lines, Co. v. City of Rochester, First Transit, Inc.
868 N.W.2d 655 (Supreme Court of Minnesota, 2015)
Rochester City Lines, Co. v. City of Rochester
846 N.W.2d 444 (Court of Appeals of Minnesota, 2014)
Rochon Corp. v. City of Saint Paul
814 N.W.2d 365 (Court of Appeals of Minnesota, 2012)
Sayer v. Minnesota Department of Transportation
790 N.W.2d 151 (Supreme Court of Minnesota, 2010)
Op. Atty. Gen. 1001k
Minnesota Attorney General Reports, 2002
Opinion No.
Texas Attorney General Reports, 1999
Untitled Texas Attorney General Opinion
Texas Attorney General Reports, 1999
San Jose Construction Group, Inc. v. Loudoun County School Board
47 Va. Cir. 487 (Loudoun County Circuit Court, 1998)
McGoff v. AMCO Insurance Co.
575 N.W.2d 118 (Court of Appeals of Minnesota, 1998)
W v. Nelson Construction Co. v. City of Lindstrom
565 N.W.2d 434 (Court of Appeals of Minnesota, 1997)
Lovering-Johnson, Inc. v. City of Prior Lake
558 N.W.2d 499 (Court of Appeals of Minnesota, 1997)
Op. Atty. Gen. 707a
Minnesota Attorney General Reports, 1993
Byrd v. Independent School District No. 194
495 N.W.2d 226 (Court of Appeals of Minnesota, 1993)
Ryan v. City of Coon Rapids
462 N.W.2d 420 (Court of Appeals of Minnesota, 1990)
Carl Bolander & Sons Co. v. City of Minneapolis
451 N.W.2d 204 (Supreme Court of Minnesota, 1990)
Danzl v. City of Bismarck
451 N.W.2d 127 (North Dakota Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
65 N.W.2d 647, 242 Minn. 529, 1954 Minn. LEXIS 670, Counsel Stack Legal Research, https://law.counselstack.com/opinion/griswold-v-county-of-ramsey-minn-1954.