Rochon Corp. v. City of Saint Paul

814 N.W.2d 365, 2012 WL 1570090, 2012 Minn. App. LEXIS 44
CourtCourt of Appeals of Minnesota
DecidedMay 7, 2012
DocketNo. A11-1271
StatusPublished
Cited by4 cases

This text of 814 N.W.2d 365 (Rochon Corp. v. City of Saint Paul) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rochon Corp. v. City of Saint Paul, 814 N.W.2d 365, 2012 WL 1570090, 2012 Minn. App. LEXIS 44 (Mich. Ct. App. 2012).

Opinion

OPINION

ROSS, Judge.

Rochon Corporation lost the municipal general-contract bidding contest to construct the Lofts at Farmer’s Market for the City of St. Paul to Shaw-Lundquist Associates. When the city opened the sealed bids, Shaw-Lundquist appeared to be the clear winner. But Shaw-Lundquist discovered that it had bid $619,200 lower than it had intended due to a clerical error, and the city allowed Shaw-Lundquist to change its bid, raising it to cover not only the $619,200 error but adding $89,211 more. Still, Shaw-Lundquist’s raised bid was lower than Rochon’s bid, and the city awarded Shaw-Lundquist the contract for $8,041,411. Rochon sued for the district court to void Shaw-Lundquist’s contract with the city. The district court granted Rochon’s summary judgment motion in part and denied it in part. It declared that the city had violated competitive bidding laws by permitting Shaw-Lundquist to change its bid after the bids were opened, but it held that the change was not material. It therefore declined to declare the contract void but awarded Rochon its $33,652 costs for its work preparing its bid. Rochon appeals, arguing that the district court erred by not declaring that the change was material and that the contract is void. Because Shaw-Lundquist’s bid change was material, we reverse.

FACTS

The city of St. Paul solicited bids in November 2010 for a construction project, the Lofts at Farmer’s Market. The city announced that the bid budget was $7.5 million. The bid instructions warned, “A bid may not be modified, withdrawn, or canceled by the Bidder for a period of sixty (60) days following the time and date designated for the receipt of bids, and each Bidder so agrees in submitting a bid.”

On November 22, 2010, the city received and opened six bids at a public bid opening. The results were as follows:

[[Image here]]
Shaw-Lundquist Associates, Inc. $7,338,000.00
Doran Construction $8,298,000.00
Sand Companies, Inc. $8,394,983.00
Rochon Corporation $8,725,000.00
Stahl Construction Co. $8,900,000.00
Moreon Construction Co., Inc. $9,652,568.00

Shaw-Lundquist was the lowest bidder. The city disqualified the two next closest bids — from Doran Construction and Sand Companies — as nonresponsive because they failed to include a required form stating that they would include the partic[367]*367ipation of women- and minority-owned subcontractor businesses. The double disqualification put Rochon’s bid in second place.

The day after the bid opening, Shaw-Lundquist informed the city by an electronically transmitted letter that it was withdrawing its bid because it had “discovered a mathematical error in [its] bid spreadsheet.” It stated that “[Shaw-Lundquist’s] correct bid total should be $8,041,411.” The error was a transcription mistake creating a disparity between a subcontractor’s bid and Shaw-Lundquist’s bid spreadsheet; instead of the correct amount of $688,000 for that subcontract cost, Shaw-Lundquist had mistakenly indicated only “$68,800.” The mistake rendered Shaw-Lundquist’s bid $619,200 lower than its bid would have been with the correct costs included.

The city considered how to treat the mistake. It first decided not to hold Shaw-Lundquist to its bid or to proceed against its bid bond. That much was not controversial. The dispute arose from the city’s next action. It asked Shaw-Lund-quist if it would maintain its bid if it were permitted to correct the transcription error. This seemed beneficial to the city since, even with the error corrected, the Shaw-Lundquist bid was still the lowest, with the next bid, Rochon’s, higher than the project’s budget. Shaw-Lundquist agreed that it would replace its bid with one for $8,041,411. The record does not indicate the city’s rationale for allowing not only the error correction but also the additional $89,211 in Shaw-Lundquist’s replacement bid, but it accepted the modified bid and awarded Shaw-Lundquist the contract.

Roehon, Morcon Construction Company, and Doran Construction protested the contract and demanded that the city either hold Shaw-Lundquist to its original bid or reject the bids altogether for a rebid. The city denied the request, recognizing that a delay would affect funding for the project and calculating that it could cost the city about $43,000 a month in interest.

Roehon commenced this lawsuit on its own behalf and under the private attorney general statute. It moved for a temporary restraining order or for a temporary injunction. It also asked the district court to declare the challenged contract illegal and void, and to order the city to reimburse its costs incurred in preparing its bid. The district court denied Rochon’s motion for temporary relief. Three days later, the city authorized Shaw-Lundquist to begin construction.

Roehon moved for summary judgment on its declaratory relief claim alleging that the city had violated public procurement law by permitting Shaw-Lundquist to make a material change to its bid after the public opening. The district court declared that by allowing Shaw-Lundquist to modify its bid the city had violated St. Paul Ordinances Chapter 82, section 82.02 (Code of Ordinances, Part III, Title IV, Chapter 82, section 82.02) (2010), Minnesota Statutes section 471.345, subdivision 3 (2010), and its own bidding instructions. But the district court held that the change was not material because Shaw-Lundquist did not enjoy a substantial advantage over the other bidders because it was still the lowest bidder after the changes. It declined to declare the contract void. The district court awarded Roehon its bid preparation costs of $33,652.

Roehon appeals.

ISSUE

Did the district court err by concluding that Shaw-Lundquist’s change to its bid was not material and that the contract [368]*368between Shaw-Lundquist and the city of St. Paul is not void?

ANALYSIS

Rochon appeals from the partial denial of its motion for summary judgment. Our review is de novo. On an appeal from summary judgment, we determine whether there are any genuine issues of material fact and whether the district court erroneously applied the law. Prior Lake Am. v. Mader, 642 N.W.2d 729, 735 (Minn.2002). The parties agree that no genuine issues of material facts exist, so our review is limited to whether the district court erred in its application of the law to the facts. See id. We first consider whether the change was “material” and then whether the change requires the contract to be voided.

Material Change ?

Rochon correctly argues that the district court erred by concluding that, although the city violated competitive bidding laws, the change it allowed in Shaw-Lundquist’s bid was not material because it remained the lowest nondisqualified bid. Both the Minnesota Statutes and St. Paul’s ordinances required competitive bidding for the Lofts project due to the contract amount. See Minn.Stat. § 471.345, subd. 3; St. Paul, Minn., Code of Ordinances, Part III, Title IV, Ch. 82, § 82.02. A central reason for competitive bidding is to eliminate an official’s discretion on matters open to fraud, favoritism, folly and extravagance. Griswold v. Ramsey Cnty., 242 Minn.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rochester City Lines Co. v. City of Rochester
897 N.W.2d 792 (Court of Appeals of Minnesota, 2017)
Rochon Corp. v. City of St. Paul
831 N.W.2d 651 (Court of Appeals of Minnesota, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
814 N.W.2d 365, 2012 WL 1570090, 2012 Minn. App. LEXIS 44, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rochon-corp-v-city-of-saint-paul-minnctapp-2012.