Danzl v. City of Bismarck

451 N.W.2d 127, 1990 N.D. LEXIS 26, 1990 WL 4982
CourtNorth Dakota Supreme Court
DecidedJanuary 25, 1990
DocketCiv. 890146
StatusPublished
Cited by7 cases

This text of 451 N.W.2d 127 (Danzl v. City of Bismarck) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Danzl v. City of Bismarck, 451 N.W.2d 127, 1990 N.D. LEXIS 26, 1990 WL 4982 (N.D. 1990).

Opinion

LEVINE, Justice.

Sylvester Danzl appealed from a summary judgment in his action to enjoin the City of Bismarck (Bismarck) from proceeding with construction of an addition to the Bismarck Civic Center. We affirm.

Bismarck prepared plans and specifications for an expansion of its Civic Center and advertised for bids to be opened and read at 5:30 p.m. on March 9, 1989. After the bids were opened, Bismarck’s architect negotiated with the four low bidders for the four prime contracts (general, plumbing and heating, ventilation and air conditioning, and electrical) for lower prices based on revisions in the plans and specifications. The alterations and deductions negotiated by the architect and the low bidders reduced the cost of the project by $1,403,900. The contracts were executed on March 23, 1989.

Danzl, a Bismarck resident and taxpayer, commenced this action on April 3, 1989, on his own behalf and on behalf of all other residents and taxpayers similarly situated, to enjoin Bismarck from proceeding with the construction project. He alleged that Bismarck’s procedures in awarding the contracts for construction of the Civic Center addition violated North Dakota’s competitive bidding statutes. On April 12, 1989,' Danzl moved for judgment on the pleadings. Bismarck requested that Danzl’s mo *129 tion be treated as a motion for summary judgment and moved for summary judgment in its favor on April 21, 1989. After a May 2, 1989, hearing on the motions, the trial court granted summary judgment in favor of Bismarck. Judgment was entered on May 4, 1989.

On appeal, Danzl contends that Bismarck violated certain competitive bidding statutes. Bismarck denies that it violated any competitive bidding statutes, and contends that Danzl lacks standing to sue, that Danzl’s suit was not timely, and that the same result could have been achieved by simply accepting the original low bids and executing a series of change orders.

Bismarck contends that Danzl does not have standing to sue because he has not shown any damage to himself or other taxpayers. We disagree. Danzl, like the plaintiff in Lang v. City of Cavalier, 59 N.D. 75, 83, 228 N.W. 819, 822 (1930):

“complains that the city has entered into a contract ... without authority of law, and, as a result of that contract, is about to unlawfully expend and dissipate the funds of the city_ If this be so, plaintiff, as a taxpayer, has a right to bring the action in his own behalf and on behalf of all other taxpayers. He need not show any interest other than that which he has as a taxpayer, or any damage or injury to him other than that which he will suffer as a taxpayer in common with all other taxpayers. He has the right as a taxpayer to have his complaint heard.”

As a Bismarck taxpayer, Danzl has standing to sue for a determination of the legality of the contracts in issue.

Bismarck argues that Danzl’s action “should fail because he failed to act in a timely fashion.” The bids were opened and read on March 9, 1989. The contracts were awarded on March 23, 1989. Danzl commended this action on April 3, 1989. Bismarck argues that “[t]he unexplained lapse of ten days changed the entire complexion of the lawsuit,” and asserts: “All of the prime low bidders immediately started ordering materials for the project. By the time of the hearing on May 2, 1989, they were already on site. Danzl should have immediately applied to the court for a temporary injunction to stop any work on the project.” In an April 20, 1989, affidavit, Bismarck’s architect averred “that all of the contractors have ordered extensive construction materials and that on-site construction is to begin May 1, 1989.”

Although an individual taxpayer-plaintiff may be barred by laches from questioning a municipal transaction, his inaction will not bar relief to all other taxpayers. Haugland v. City of Bismarck, 429 N.W.2d 449 (N.D.1988); Dahl v. City of Grafton, 286 N.W.2d 774 (N.D.1980). Because Danzl “is vindicating the rights of the public generally — that is, those of all other taxpayers as well as his own — the mere fact that he himself may have been dilatory, if in fact he was, cannot estop him from bringing the action.” Lang v. City of Cavalier, supra, 228 N.W. at 822. We conclude that Danzl is not precluded from bringing his action to question Bismarck’s procedures in awarding contracts for the construction of a public building.

Bismarck contends that it could have achieved the same result by awarding contracts to the low bidders based on the original plans and specifications and then reducing the cost of the project by executing a series of change orders effecting the same modifications and deductions as the revisions adopted after reading the bids. A municipality may reserve in a public works contract the right to make reasonable changes. 13 McQuillin Mun. Corp. § 37.125 (3rd Ed.1987). We are unable to assess Bismarck’s contention on this matter, however, as the record before us does not contain any of the contracts in issue. Therefore, we do not further address or resolve the question whether Bismarck could have achieved the same result by accepting the original low bids and executing change orders after letting the contracts.

Danzl contends that Bismarck violated competitive bidding statutes contained in Chapter 48-02, N.D.C.C., by opening bids earlier than the advertised time and by negotiating with the low bidders *130 without readvertising and rebidding the project upon revising the plans and specifications after the bids were opened. Section 48-02-02, N.D.C.C., provides that if the estimated cost of constructing a city building exceeds $50,000, the governing body of the city “shall procure plans, drawings, and specifications for the work.” Section 48-02-03 provides: “The governing board shall advertise for bids for the doing of the work for which plans, drawings, and specifications are required by section 48-02-02.” Section 48-02-04(2) requires that the- advertisement for bids state “[t]he place where, and the day and hour when, the bids will be opened.” Section 48-02-06 provides:

“At the time and place specified in the notice, the governing board shall open publicly and read aloud all bids received, and may reject all bids or award the contract ... to the lowest and best bidder. ... The board may reject any and all bids and may advertise anew ... until a satisfactory bid is received.”

Bismarck's advertisement for bids stated that the bids would be opened and read at 5:30 p.m. on March 9, 1989. Danzl contends that Bismarck “violated the law by opening the bids prior to the stated hour.” Bismarck alleged in its amended answer that the bids “were opened as late as practical to allow the 5:30 p.m. reading.” Danzl has not disputed Bismarck’s assertions that: “The bids were in fact opened during the meeting so that they could be read at 5:30. The process of opening and recording the twenty plus bids took almost one-half hour.” We believe that Bismarck substantially complied with the statute by opening the bids publicly a short time before 5:30 in order to accomplish their reading at the time stated in the notice.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baukol Builders, Inc. v. County of Grand Forks
2008 ND 116 (North Dakota Supreme Court, 2008)
Saefke v. Stenehjem
2003 ND 202 (North Dakota Supreme Court, 2003)
Bir Ram Construction Engineers Corp. v. Junta de Subastas del Gobierno Municipal de Hatillo
6 T.C.A. 881 (Tribunal De Apelaciones De Puerto Rico/Court of Appeals of Puerto Rico, 2000)
Billey v. North Dakota Stockmen's Ass'n
1998 ND 120 (North Dakota Supreme Court, 1998)
Prete Enterprises, Inc. v. Brainard, No. Cv 950374293 (Jul. 10, 1995)
1995 Conn. Super. Ct. 7580 (Connecticut Superior Court, 1995)
Becker Electric, Inc. v. City of Bismarck
469 N.W.2d 159 (North Dakota Supreme Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
451 N.W.2d 127, 1990 N.D. LEXIS 26, 1990 WL 4982, Counsel Stack Legal Research, https://law.counselstack.com/opinion/danzl-v-city-of-bismarck-nd-1990.