Greenmoss Builders, Inc. v. King

580 A.2d 971, 155 Vt. 1, 1990 Vt. LEXIS 129
CourtSupreme Court of Vermont
DecidedAugust 3, 1990
Docket88-108
StatusPublished
Cited by20 cases

This text of 580 A.2d 971 (Greenmoss Builders, Inc. v. King) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greenmoss Builders, Inc. v. King, 580 A.2d 971, 155 Vt. 1, 1990 Vt. LEXIS 129 (Vt. 1990).

Opinion

Dooley, J.

A builder and his lawyers parted ways. Appellee Premar Corporation/Greenmoss Builders (hereinafter plaintiff) sued appellants Richard King, Harriet King, and King & King (hereinafter defendants) to recover money allegedly owed on a construction contract. Defendants counterclaimed for an amount allegedly overpaid on an earlier construction contract. Plaintiff then added a claim for monies owed on that first contract.

The trial court entered judgment in favor of plaintiff 1 for the amount owed on the second contact, plus interest at lVz% per month from the date payment was . due. The court denied defendants recovery on the first contract, ruling that defendants’ *3 conduct subsequent to the alleged overpayment constituted a waiver of the right to pursue damages. The court also denied plaintiff’s claim for additional monies on the first contract, ruling that defendants had not waived their rights as to those payments. We affirm the trial court’s decision on the claim and the counterclaim, and we vacate the order to pay interest and remand the case for a recalculation of the interest to be awarded on the accrued damages.

The facts in this case, taken in the light most favorable to the prevailing party and excluding all modifying evidence, New England Road Machinery Co. v. Calkins, 121 Vt. 118, 120, 149 A.2d 734, 736 (1959), are as follows. Plaintiff is a construction company located in Waitsfield. Defendants are lawyers and their law firm. 2 Defendants represented plaintiff on a variety of corporate issues and represented plaintiff’s principal on some personal matters. The relationship between the builder and the lawyers was, at first, a benefit to both.

Defendants hired plaintiff to do an addition on their personal residence in the spring of 1981. The construction contract, based upon the standard American Institute of Architects form contract, contained a guaranteed maximum price of $38,063. It also provided for increases or decreases to be made in the maximum price through change orders. The terms of the contract, however, were not strictly followed nor were those terms always clear.

The trial court found that the contract was ambiguous, that many of the terms were unilaterally added by defendants, and that the parties very often did not follow the provisions of the contract. The written contract was never signed by plaintiff.

Payment for the construction was made in part by crediting plaintiff’s account with the law firm. Defendants actively participated in the design and oversight of the construction. Many changes were made as the construction moved forward, but formal change orders were not submitted to defendants. Each invoice contained an explanation of all charges. Payment for the *4 work was steady but did not follow the dictates of the written contract. Defendants paid each invoice as it came in up to a total of $45,134.35 — an amount obviously in excess of the $38,063 maximum price. Plaintiff’s final two invoices, totalling $6,923.68, were not paid. Although the final price, including that portion not paid by defendants, was almost $14,000 over the guaranteed maximum price, the trial court found that the price was fair and reasonable for the work performed. The court also found that defendants did not raise the issue of the overpayments until suit was filed against them for collection of funds owed on a second contract, as described below. Similarly, plaintiff never made an effort to collect the $6,923.68 billed out but not paid by defendants on the first contract until responding to defendants’ counterclaim.

Despite the failure of defendants to pay the final two installments on the house contract and plaintiff’s failure to perform the house contract within the maximum price, plaintiff and defendants maintained their professional relationship and entered into a second contract for renovation work in defendants’ new office in February, 1983. Plaintiff agreed to do the work on a cost plus 25% basis. In lieu of cash payments, defendants were to credit the plaintiff’s account, representing charges for legal services. Greenmoss did more work for defendants than initially agreed to, and the total bill for $4,474.15 was submitted by plaintiff on May 10, 1983. The trial court found the amount charged for the renovations to be fair and reasonable.

At about the same time plaintiff finished the office renovations, defendants negotiated a settlement to an unrelated lawsuit on behalf of plaintiff and presented plaintiff with a bill for $9,517.10. Defendants, however, would not honor the agreement to offset the fee with plaintiff’s charges for the office renovations and required plaintiff to pay the bill in full in order to receive the settlement proceeds. Plaintiff continuously billed defendants for the office work, but the billings and a collection letter from plaintiff’s present attorney were ignored. This litigation ensued.

The trial court found that defendants’ payment of part of the excess beyond the maximum price on the house contract, along *5 with their silence, was an “acquiescence that the house contract was over and done with.” It further found that defendants misrepresented their intentions regarding payment for the office job and plaintiff reasonably relied on defendants’ promise that it would be paid in agreeing to do the office renovation. On this basis, it concluded that plaintiff could collect for the price of the office renovation and defendants could not collect the amount that they paid for the house addition in excess of the guaranteed maximum price. The court also concluded that plaintiff could not collect for the amount of bills that were submitted for the house contract, but were not paid, because they were above the maximum price. The court added interest to plaintiff’s recovery at the rate of 1 Vz% per month from the date of plaintiff’s billing.

Defendants make three arguments on appeal: (1) the trial court erred in finding a waiver and estoppel to their claim for monies paid in excess of the maximum price on the house contract; (2) the court further erred by not awarding to them recovery where changes in the house contract terms resulted in cost decreases; and (3) the court erred in granting prejudgment interest at the rate of llA% per month absent any agreement between the parties. We take these issues in order, but we do not reach the second argument because we affirm on the first.

We begin by reiterating that the findings of the trial court will not be reversed unless we find them clearly erroneous. Fisher v. Poole, 142 Vt. 162, 166, 453 A.2d 408, 411 (1982); V.R.C.P. 52(a). The trial court in this case did its job of sifting the evidence and stating the facts. See, e.g., Lynda Lee Fashions, Inc. v. Sharp Offset Printing, Inc., 134 Vt. 167, 170, 352 A.2d 676, 677 (1976). Most of the evidence was contested.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jennifer Johnson v. Gregory Johnson
Supreme Court of Vermont, 2015
Nelson v. Town of St. Johnsbury
Vermont Superior Court, 2013
Dupuis v. Haven Health Center
Vermont Superior Court, 2011
Reed v. Zurn
2010 VT 14 (Supreme Court of Vermont, 2010)
Hamm Mine Act 250 Jurisdiction
Vermont Superior Court, 2008
Lamell Lumber Corp. v. Newstress International, Inc.
182 Vt. 282 (Supreme Court of Vermont, 2007)
Lamell Lumber Corp. v. NEWSTRESS INTERN.
2007 VT 83 (Supreme Court of Vermont, 2007)
New England Partnership, Inc. v. Rutland City School District
786 A.2d 408 (Supreme Court of Vermont, 2001)
Gravel & Shea v. White Current Corp.
752 A.2d 19 (Supreme Court of Vermont, 2000)
Beecher v. Stratton Corp.
743 A.2d 1093 (Supreme Court of Vermont, 1999)
Paradise Restaurant, Inc. v. Somerset Enterprises, Inc.
671 A.2d 1258 (Supreme Court of Vermont, 1995)
Roy v. Mugford
642 A.2d 688 (Supreme Court of Vermont, 1994)
McCormick v. McCormick
621 A.2d 238 (Supreme Court of Vermont, 1993)
Wright v. Doolin
607 A.2d 1137 (Supreme Court of Vermont, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
580 A.2d 971, 155 Vt. 1, 1990 Vt. LEXIS 129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greenmoss-builders-inc-v-king-vt-1990.