Ejnes v. Carinthia Trailside Associates

571 A.2d 49, 153 Vt. 355, 1989 Vt. LEXIS 260
CourtSupreme Court of Vermont
DecidedDecember 1, 1989
DocketNo. 88-143
StatusPublished
Cited by5 cases

This text of 571 A.2d 49 (Ejnes v. Carinthia Trailside Associates) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ejnes v. Carinthia Trailside Associates, 571 A.2d 49, 153 Vt. 355, 1989 Vt. LEXIS 260 (Vt. 1989).

Opinion

Dooley, J.

This case involves the construction of a termination clause of a purchase-and-sale agreement. The defendants in the trial court were Carinthia Trailside Associates, a limited partnership, and Donald Swain, a general partner of Carinthia. [356]*356The plaintiffs were persons who signed agreements with defendant Carinthia (signed by defendant Swain) to purchase condominium units. Relying on a stipulation of facts, defendants moved for summary judgment, pursuant to V.R.C.P. 56, of . plaintiffs’ claims for return of their deposits because the condominium purchase did not go through. The trial court granted summary judgment in favor of plaintiffs and defendants appealed. We hold that material issues of fact exist between the parties and that the granting of summary judgment was error. We therefore reverse and remand for trial.

The following facts were stipulated. The parties in the case at bar entered into purchase-and-sale agreements for two condominiums built by defendants. Defendants offered a $3500-to-$5000 discount per unit if the plaintiffs would sign the agreement and deposit ten percent of the purchase price of their respective units before March 1, 1984. On February 28th, plaintiffs signed the purchase-and-sale agreements and made the deposits. Under the agreements, closing on the units was to take place within ten days of completion but no later than March 19, 1984. Each agreement contained an addendum dealing with mortgage financing. The addendum made the agreement contingent on the purchasers obtaining approval of a mortgage for a sum certain at a specified rate. This contingency was deemed waived, however, unless the purchasers notified the sellers by certified or registered mail, return receipt requested, no later than March 19,1984, of the purchasers’ inability to obtain mortgage approval. If notice of unavailability of financing was given under the addendum, the purchaser was entitled to return of the deposit.

With defendants’ assistance, plaintiffs sought financing from the Factory Point National Bank.1 As of March 19, 1984, however, the bank had not acted on plaintiffs’ mortgage applications. On March 20, 1984, defendant Swain had actual knowledge that the bank had not acted on the mortgage appli[357]*357cations. On March 22, 1984, he notified plaintiffs by letter that he had conferred with an officer of the Factory Point National Bank and that “[H]e is quite positive that the commitment will be forthcoming, but that some additional time will be required to process the loan.” The letter indicated that the units had been ready for occupancy since March 1st, but requested that the closing be delayed to a date no later than April 6th to allow plaintiffs’ financing source adequate time to provide the funds.

On April 10,1984, plaintiffs’ mortgage applications were denied.2 The notice from the bank stated: “We do not grant credit to any applicant on the terms and conditions you requested.” Plaintiffs immediately requested that their deposits be refunded. Defendants refused to refund the deposits, citing plaintiffs’ failure to provide notice of unavailability of financing by March 19, 1984.

The stipulation does not show when defendants were ready to convey title. Defendants alleged that they were ready and able to convey title on or before March 19,1984 and filed an affidavit to that effect. Plaintiffs denied this allegation. The stipulation indicates that plaintiffs were never given written notice of the date of the completion of the units but, at some point, were given oral notice that the units were ready on March 1, 1984. The purehase-and-sale agreement calls for the sellers’ architect to certify when a unit is ready for occupancy, with closing to take place within ten days thereafter but no later than March 19,1984. As indicated above, the March 22nd letter stated that the units had been ready since March 1st.

Defendants’ motion for summary judgment argued that the purchase-and-sale agreements were clear and unambiguous, that the agreements stated clearly that time was of the essence, and that plaintiffs failed to comply with the terms of the agreements. Plaintiffs responded that there were material issues of fact, because it was disputed whether defendants were ready to close on March 19, 1984 and that the March 22nd letter promised financing and obviated the need for notice under the adden[358]*358dum. Plaintiffs’ argument, then, is that defendants’ conduct constituted a waiver of strict compliance with the notice requirement.

The trial court’s opinion and order concluded that the failure to give notice of the unavailability of financing by the March 19th deadline was not effective to remove the financing contingency “because the financing application was still being processed.” It went on to conclude that defendants were entitled to notice only when the financing fell through and they received such notice, albeit in a form different from that specified in the addendum. Relying primarily upon Town of Newport v. State, 115 N.H. 506, 507, 345 A.2d 402, 403 (1975), the court found that the form of notice was not determinative and entered judgment for plaintiffs.

This case is unnecessarily difficult because of the wholly inadequate state of the record on which the trial court made its decision. As discussed more fully below, we find the stipulation of facts to be incomplete, a deficiency which is particularly critical when we are considering a motion for summary judgment. Here, the parties opposing summary judgment were entitled to the “benefit of all reasonable doubts and inferences in determining whether a genuine issue exists.” Cavanaugh v. Abbott Laboratories, 145 Vt. 516, 520, 496 A.2d 154, 157 (1985). However, only necéssary inferences can be drawn from stipulated facts. See Digregorio v. Champlain Valley Fruit Co., 127 Vt. 562, 564, 255 A.2d 183, 185 (1969). Since the resolution of this case must involve inferences to be drawn by the factfinder, the inability to do so leaves the record fatally incomplete. See Winooski Urban Renewal Agency v. Green Mountain Power Corp., 134 Vt. 497, 498, 365 A.2d 514, 515 (1976).

Defendants’ theory here and in the trial court focused exclusively on the March 19th date by which plaintiffs were to give notice of inability to obtain financing. Defendants ignore, however, that March 19th was also the last date for closing and that closing was to occur ten days after each unit was ready for occupancy as certified by defendants’ architect. Although it seems clear that the architect never certified when the units were ready for occupancy, we cannot tell from the stipulation what, if [359]*359anything, occurred on or before March 19th with respect to the closing. Although defendants assert that they were prepared to close, there is no indication that they tendered performance or showed a willingness to perform so as to put plaintiffs in default on that date. See Drew v. Bowen, 102 Vt. 124, 127, 146 A. 254, 255 (1929). Thus, we cannot tell whether defendants performed their “concurrent and dependent” undertakings that are a prerequisite to enforcing the contract against plaintiffs. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O'Brien v. Synnott
2013 VT 33 (Supreme Court of Vermont, 2013)
Hamelin v. Simpson Paper (Vermont) Co.
702 A.2d 86 (Supreme Court of Vermont, 1997)
Lopez v. Concord General Mutual Insurance Group
583 A.2d 602 (Supreme Court of Vermont, 1990)
Greenmoss Builders, Inc. v. King
580 A.2d 971 (Supreme Court of Vermont, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
571 A.2d 49, 153 Vt. 355, 1989 Vt. LEXIS 260, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ejnes-v-carinthia-trailside-associates-vt-1989.