Hamm Mine Act 250 Jurisdiction

CourtVermont Superior Court
DecidedMay 15, 2008
Docket271-11-06 Vtec
StatusPublished

This text of Hamm Mine Act 250 Jurisdiction (Hamm Mine Act 250 Jurisdiction) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hamm Mine Act 250 Jurisdiction, (Vt. Ct. App. 2008).

Opinion

STATE OF VERMONT ENVIRONMENTAL COURT

} In re: Hamm Mine Act 250 Jurisdiction } (Jurisdictional Opinion #2-241) } Docket No. 271-11-06 Vtec }

Decision on the Merits The Hamm Mine in Windham was first established in 1982, principally to mine the soft stone material known as talc. It was an open pit mine. After its owners ceased operation, the open pit began to fill with water. On October 26, 2006 the District #2 Environmental Commission Coordinator issued a jurisdictional opinion in which she concluded that the Hamm Mine property remained under Act 250 jurisdiction, even though its state land use permit had been allowed to expire and all reclamation work had been completed. The current property owner and last operators of the mine thereafter filed a timely appeal of the Coordinator’s jurisdictional opinion. The Court conducted a site visit and de novo merits hearing over five days. This Merits Decision addresses all issues preserved for review in this jurisdictional opinion appeal. Appellants Luzenac America, Inc. and U.S. Talc Co., Inc. (“Luzenac”) are represented throughout this proceeding by George McNaughton, Esq.; Appellant Sean T. Reese is represented by Richard D. Perra, Esq.; James McCandless, who as Trustee of the B.W. McCandless Trust, is the title holder to property that adjoins the Hamm Mine property, appears in this proceeding through his attorney, Robert E. Woolmington, Esq.; the Land Use Panel of the Vermont Natural Resources Board (“NRB”), appears in this proceeding through its staff attorney, Melanie Kehne, Esq. Based upon the evidence admitted at trial, some of which was put into context by the site visit conducted with the parties, the Court issues the following Findings of Fact and Conclusions of Law:

Factual Findings1

1 Some of the Factual Findings recited here are similar to several of the paragraphs in the “Factual Background” section of the Court’s Decision on Appellant Luzenac’s Motion for Summary Judgment, issued on September 27, 2007 (“September 27, 2007 Decision”). This is not a coincidence, as some facts once deemed uncontested remained material to our adjudication of the legal issues addressed in this Merits Decision, and some facts which may have once been disputed were proved accurate, based upon the credible evidence presented at trial. 1. In 1981, Vermont Talc, as a division of OMYA, Inc., acquired 84± acres from the Hamm family, upon which the company intended to establish a talc mine. The company owned several other nearby parcels, one of which was the site for a pre-existing mine, known as the Windham Mine. 2. Vermont Talc first received land use approval for the subject talc mine, known as the Hamm Mine, when the District #2 Environmental Commission (“Commission”) issued Act 250 Land Use Permit #2W0551 (“Permit #2W0551”) on October 20, 1982. 3. Permit #2W0551 directed that the Hamm Mine project “shall be completed . . . in accordance with the plans and exhibits stamped “Approved” and on file with the District Environmental Commission, and in accordance with the conditions of this permit.” Id. at ¶1. The development authority conferred by the Permit was conditioned upon the restriction that “[n]o changes shall be made in the project without the written approval of the . . . Commission.” Id. 4. As is the customary practice in its review of “major applications,” 2 the Commission also issued written Findings of Fact and Conclusions of Law with Permit #2W0551. 5. The Findings of Fact that accompanied Permit #2W0551 noted the applicant’s plan to pump water from the bottom of the mine to an adjacent holding pond. The site map stamped “Approved” in connection with this initial application, copies of which were admitted at trial as Exhibits L and L-1, shows that this pond was to be constructed next to the southeast corner of the mine, closest to property then owned by Karl and Olga Dietrich. 6. Water was to be pumped into this pond from the bottom of the mine, to “dewater” the area during mining operations. The approved pond was of a sufficient size to allow the pumped water to stand for two to three days, so that any suspended solids in the water could settle. The applicant’s plan called for the clearer water to then flow from this settlement pond, through an outlet pipe, onto a rip raped swale and then discharge onto lands further to the southeast, including the Dietrich lands. The Findings of Fact and Conclusions of Law specifically noted that the permittee “agreed to come back for an amendment if there is any work that will change the quantity or quality of the runoff in the direction of Mr. Dietrich’s property.” Id. at ¶4(E).

2 When an Act 250 application is deemed a “major” application, the Commission will conduct a site visit, one or more hearings to take evidence, and issue formal written Findings upon which its permit or denial of a permit is based, all pursuant to former Environmental Board Rule 2.

2 7. The Findings of Fact and Conclusions of Law also specifically noted the identified sedimentation pond, together with associated “culverts” and “rip rap” would constitute portions of the mine’s “[p]ermanent erosion controls.” Id at 4(C). 8. While the plan and practice during the mining operations had been to pump water from the bottom of the mine into this sedimentation pond, the approved site plan (Exhibits L and L-1) also called for a pipe and rip rapped swale to be installed from the southeast lip of the mine to this sedimentation pond, thereby allowing water to flow from the mine to the pond, if and when the mine filled with water. 9. This particular sedimentation pond and discharge structures may have been built in the early stages of the mine, but were abandoned as the mine operation continued.3 A permit amendment was never sought nor received to authorize their omission. 10. The evidence at trial was somewhat unclear as to why the permittee discarded the original sedimentation pond and discharge structures. What was undisputed at trial was that the permittee changed its plan for sediment treatment at the Hamm Mine by substituting an alternate set of settlement ponds to the northwest of the mine, in a portion of the area originally designated for overburden storage. This new plan called for water to be pumped out of the bottom of the mine to the first of the new retention ponds, where the mine sediment settled out and the clearer water flowed to a second pond or wetland area, where the water would gradually percolate into the ground. There was no evidence presented at trial that contradicted Luzenac’s representation that this alternate sedimentation plan worked in a satisfactory manner during the period in which the Hamm Mine was operational. 11. Luzenac asserted that Commission staff had notice of this alternate sedimentation pumping and treatment procedure during the operation of the mine, which fact was not disputed by the NRB.4 It was also undisputed at trial that no amendment to the original permit was applied for or issued that authorized this change to the permittee’s sedimentation plan and omission of the approved erosion control structures.

3 Exhibit 9 is a photo depicting the mine in 1991, in active operation. In the upper left corner of the photo is a grassed area that appears to include a depression that may have been this original sedimentation pond. The photo does not show any rip rapped swales or piping. The Court visited this area during its site visit with the parties and recalls viewing some area of depression, although not the full sedimentation pond and discharge structures as depicted in the originally approved site plan (Exhibits L and L-1). 4 The NRB has administrative authority of the various district environmental commissions and has the right to intervene in Act 250 appeal proceedings before this Court. 10 V.S.A., Chapter 151, subchapter 2.

3 12.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Greenmoss Builders, Inc. v. King
580 A.2d 971 (Supreme Court of Vermont, 1990)
In Re Huntley
2004 VT 115 (Supreme Court of Vermont, 2004)
Gravel & Shea v. White Current Corp.
752 A.2d 19 (Supreme Court of Vermont, 2000)
In re Merritt
2003 VT 84 (Supreme Court of Vermont, 2003)
In re Appeal of Tekram Partners
2005 VT 92 (Supreme Court of Vermont, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Hamm Mine Act 250 Jurisdiction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hamm-mine-act-250-jurisdiction-vtsuperct-2008.