In Re Huntley

2004 VT 115, 865 A.2d 1123, 177 Vt. 596, 2004 Vt. LEXIS 326
CourtSupreme Court of Vermont
DecidedNovember 9, 2004
Docket03-369
StatusPublished
Cited by14 cases

This text of 2004 VT 115 (In Re Huntley) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Huntley, 2004 VT 115, 865 A.2d 1123, 177 Vt. 596, 2004 Vt. LEXIS 326 (Vt. 2004).

Opinion

¶ 1. Richard and Elinor Huntley, owners of a five-acre gravel mine, appeal a declaratory ruling by the Environmental Board. The Board determined that the Huntleys’ mine and associated property remained subject to Act 250 jurisdiction even though the site had been fully reclaimed, and its former permit had expired. We reverse and hold that, when á permit expires pursuant to 10 V.S.A. § 6090(b)(1), the land is no longer subject to Act 250 jurisdiction absent some activity to trigger the statute’s application.

¶ 2. In 1986, the Huntleys’ predecessors in interest applied for an Act 250 permit, under § 6090(b)(1) (extraction of rhineral resources), to extract gravel from a five-acre segment of their approximately 100-aere farm in Bethel. They proposed a three-phase mining operation with detailed reclamation requirements to be completed at each phase. The District 3 Environmental Commission approved the proposal contingent that it be “completed and maintained in conformance with all of the terms and conditions of that application, and of Land Use Permit #3W0473.” That permit obligated the applicant to “complete and maintain” the project only as approved by the district commission and peimit conditions. The commission found that, if the project was operated and reclaimed in accordance' with the permit’s conditions, it would “not result in undue harm to the environment and [would] result' in an area suitable for continued agricultural use.” The permit specified that the district environmental commission would “maintain[] continuing jurisdiction during the lifetime of the peimit” and that the peimit would expire on July 1, 1995, unless extended.

¶ 3. The Huntleys subsequently acquired the property. In 1995, they obtained a permit amendment authorizing minor changes in mining operations and extending the completion date for all mining and reclamation activities to October 1, 2002. 1 By the October deadline, the Huntleys had ceased mining operations, and fully reclaimed and rehabilitated the property in accordance with the permit requirements. A month later, as part of preparations to sell the property, the Huntleys requested an opinion from the district commission determining whether their property remained subject to Act 250 jurisdiction. In response, the District 3 coordinator concluded that, although all mining had ceased, the permit had expired and the land had been reclaimed in compliance with permit requirements, the project remained subject to continuing Act 250 jurisdiction, and that “[a]ny subsequent activity on the land may require a permit.”

¶ 4. The Huntleys appealed to the Environmental Board, which framed the issue as follows:

Does a sand and gravel extraction project remain subject to Act 250 jurisdiction when the project’s land use permit has *597 expired pursuant to 10 V.SA. § 6090(b)(1); and where the project tract has been reclaimed in accordance with the requirements of 10 V.SA. § 6086(a)(9)(E)(ii); and where, said reclamation results in there being no potential for future environmental impacts from the prior sand and gravel extraction project?

. ¶ 5. The Board found that it had continuing jurisdiction over the project. The Board reasoned that permit duration and jurisdiction are two different concepts: the permit duration determines the life of a project, while jurisdiction determines the Board’s oversight authority. In cases involving a sand and gravel extraction operation, the Board concluded that the need to ensure that future property owners maintain compliance with the permitted reclamation plan supported continuing jurisdiction beyond the permit’s expiration date. The Board acknowledged, however, that only a “material or substantial change” to the permitted project would require a permit amendment. See Environmental Board Rule (EBR) 2(A)(1)(e), 4 Code of Vermont Rules 12 003 001-6 (2004). This appeal followed.

¶ 6. In reviewing the Board’s decision, the Board’s interpretation of Act 250 and its rules control, unless a compelling indication of error exists. In re Rusin, 162 Vt. 185, 188, 643 A.2d 1209, 1210 (1994). If the Board operates outside the bounds authorized by its enabling legislation, we will intervene. In re Agency of Admin., 141 Vt. 68, 75, 444 A.2d 1349, 1352 (1982). When examining the legislative grant of authority to the Board, we look to the plain meaning of the statutory language and are guided by the Legislature’s intent, “as evidenced by the statutes themselves.” In re Audet, 2004 VT 30, ¶ 9, 176 Vt. 617, 850 A.2d 1000 (mem.) (internal citations and quotations omitted). We conclude that, under the circumstances in this case, Act 250 jurisdiction ended when the permit expired.

1Í 7. The Board’s decision in this case equates jurisdiction with continuing oversight of the land and the authority to “ensure” that the Huntleys followed certain aspects of the reclamation plan and other permit requirements. For example, the original permit required a vegetative buffer to screen the project. The Board was concerned that if jurisdiction was lifted the Huntleys could remove this buffer. The Board further believed it needed jurisdiction to ensure that the Huntleys did not ignore the reclamation plan. The Board’s decision, in effect, extended its enforcement powers beyond the permit’s expiration date.

¶ 8. In enacting Act 250, the Legislature conferred authority on the Board to bring enforcement actions. For example, the Board can impose penalties for violations of a permit or failure to obtain a permit. 10 V.S.A § 6003. The Board can revoke permits if a holder violates a permit’s terms or conditions and fails to correct the violation. Id. § 6090(c); EBR 38, 6 Code of Vermont Rules 12 003 001-33 to 001-34 (2004). Additionally, the Board can investigate to determine compliance with a permit, 10 V.S.A. § 8005, and the Board can request that the secretary issue a warning for violations. Id. §§ 8004,8006(b).

¶ 9. However, the Board’s enforcement authority is tied to development, as defined in Act 250, and the existence of a permit. Under Act 250, commencing development triggers jurisdiction and the obligation to obtain a permit. 10 V.S.A. § 6081. “Development” includes, among other things: (1) the construction of improvements for commercial or industrial purposes on more than one acre within a municipality that does not have zoning laws and bylaws, or on more than ten acres if the municipality does have permanent zoning and bylaws, or in munic *598 ipalities that choose to have one-acre jurisdiction apply; (2) construction of ten or more housing units; (3) construction above 2500 feet in elevation; and (4) extraction of oil, gas, or fissionable source materials. 10V.S.A. § 6001(3)(A). In the present case, the Huntleys ceased the sand and mining operation and reclaimed the land. At this time, they are not conducting any activity that constitutes development as defined by Act 250. Thus, the Board has no enforcement authority over the Huntleys’ land because no development is taking place.

¶ 10. Furthermore, the permit’s plain language states that the permit expired on October 1, 2002.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leverenz Act 250 JO
Vermont Superior Court, 2015
Roger Rowe Act 250 Gravel Pit
Vermont Superior Court, 2015
Fontaine Act 250 Application
Vermont Superior Court, 2011
In Re Hamm Mine Act 250 Jurisdiction
2009 VT 88 (Supreme Court of Vermont, 2009)
Hamm Mine Act 250 Jurisdiction
Vermont Superior Court, 2008
Hamm Mine Reclamation Act 250 JO 2-241
Vermont Superior Court, 2007
Eustance JO 2-231
Vermont Superior Court, 2007
State Ex Rel. Nixon v. Alternate Fuels, Inc.
181 S.W.3d 177 (Missouri Court of Appeals, 2005)
Judicial Watch, Inc. v. State
2005 VT 108 (Supreme Court of Vermont, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
2004 VT 115, 865 A.2d 1123, 177 Vt. 596, 2004 Vt. LEXIS 326, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-huntley-vt-2004.