In Re Hamm Mine Act 250 Jurisdiction

2009 VT 88, 980 A.2d 286, 186 Vt. 590, 2009 Vt. LEXIS 101
CourtSupreme Court of Vermont
DecidedAugust 20, 2009
Docket08-249
StatusPublished
Cited by11 cases

This text of 2009 VT 88 (In Re Hamm Mine Act 250 Jurisdiction) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Hamm Mine Act 250 Jurisdiction, 2009 VT 88, 980 A.2d 286, 186 Vt. 590, 2009 Vt. LEXIS 101 (Vt. 2009).

Opinion

¶ 1. This case arises as the result of flooding allegedly caused by the failure of past operators of an open-pit talc mine to abide by the conditions of an Act 250 permit. Luzenac America, Inc. and U.S. Talc Co. (Luzenac) appeal the Environmental Court’s determination that the mine continues to be subject to Act 250 jurisdiction after mine operations ceased and the Act 250 permit expired. We affirm.

¶2. After purchasing land from the Hamm family in 1981, Vermont Tale obtained an Act 250 permit from the District 2 Environmental Commission the following year to operate a talc mine on the property. The 1982 permit stated that the permittee, as well as its assigns and successors, were obligated “to complete and maintain the project only as approved by the district commission in accordance with” the permit conditions, its findings and conclusions, and the permittee’s *591 plans and exhibits that were stamped as approved by the commission. The permit explicitly prohibited any changes in the project “without the written approval of the District Environmental Commission.”

¶ 3. The findings and conclusions that accompanied the 1982 permit endorsed, among other things, the permittee’s plan to pump water from the mine into a holding pond on the southeast corner of the property that would settle out solids and allow gradual drainage. To ensure compliance with criterion four of Act 250, 10 V.S.A. § 6086(a)(4), the permit stated that “[tjhere will be no unreasonable soil erosion or effects on the capacity of the land to hold water.” The permit further noted that the planned “[pjermanent erosion controls consist of culverts, rip rap, a sedimentation pond and seed and mulch.” Another finding pertaining to the extraction of earth resources stated that “[tjhe plan for opening the mine is the final grade for the closing of the mine,” and that “[tjhe project is planned to have shallow slopes to the water level of a pond in the open portion of the mine.” The finding further noted that the pond “can be used for recreation or for a fire pond.” The permit explicitly stated that it would expire on October 15, 2002, unless extended by the district commission.

¶ 4. For reasons that are not entirely clear, the permittee commenced construction of the pond in the southeast comer of the property as approved by the permit, but abandoned its use early on and instead constructed two sedimentation ponds northwest of the mine at a higher elevation. It is undisputed that the permittee never sought or obtained from the district commission a permit amendment allowing either relocation of the approved sedimentation pond or omission of erosion control structures associated with the pond.

¶ 5. Luzenac is the permittee's successor in interest. Between 1984 and 1995, the original permittee or Luzenac filed several applications for permit amendments, none of which referenced either the abandonment of the sedimentation pond and discharge structures originally approved in the 1982 permit or the replacement structures actually constructed and used in the operation of the mine. In November 1995, the district commission granted Luzenac’s permit application authorizing it to expand the mine’s existing overburden disposal area — the area where waste rock fill was placed. One of the permit conditions required Luzenac to reclaim the overburden disposal area by October 2002, as outlined in its plan. Luzenac stated in its application for the 1995 permit amendment that “[ojverall site reclamation is pending designation of mine closure date. Reclamation of overburden disposal area involves grading and revegetation.” Mine operations ceased in 1997.

¶ 6. Between 1997 and 2002, Luzenac monitored the gradual filling of the pit with water that resulted from the cessation of pumping operations. In October 2002, Luzenac informed the district commission of its full compliance with permit conditions and outlined its plans to allow the permit to expire, complete reclamation, and sell the property. That same month, Luzenac sold the property to a couple who participated in the later proceedings before the district commission and the Environmental Court but not the instant appeal. In 2003, the pit began overflowing onto the adjoining property of James McCandless, the successor trustee of appellee B.W. McCandless Trust. The Environmental Court found that flooding from the mine contributed to turning a portion of the McCandless property into a wetland that prevented productive use of the land.

¶7. In response to the new owners’ request for a jurisdictional opinion, the district coordinator ruled that the mine remained subject to Act 250 jurisdiction even though mine operations had ceased *592 and the Act 250 permit had expired. The new owners and Luzenae appealed that determination to the Environmental Court. The court reaffirmed the district coordinator’s determination, ruling that the failure of the mine operators to abide by the terms of the original permit by seeking a permit amendment before removing discharge structures and substituting unapproved sedimentation ponds for the one designated in the approved plan amounted to development activities that subjected the mine to continuing Act 250 jurisdiction, despite the cessation of mine operations and the expiration of the Act 250 permit. The court also rejected Luzenac’s argument that the district commission was estopped from asserting Act 250 jurisdiction because it was aware of the unpermitted changes when it approved later permit amendments.

¶ 8. On appeal, Luzenae argues that (1) any permit violations were causally unrelated to the alleged damage from the flooding and thus could not be the basis for continued Act 250 jurisdiction; (2) the company reclaimed the mine as required by the permit conditions, and thus there was no further development activity to trigger Act 250 jurisdiction; (3) under the circumstances of this case, the district commission should be estopped from asserting Act 250 jurisdiction; and (4) the Environmental Court erred in making certain findings that have the “propensity to cause legal mischief.” Both the adjoining landowner and the State have filed briefs asking this Court to affirm the Environmental Court’s decision.

¶ 9. We defer to the Environmental Court’s construction of land-use permit conditions. Agency of Natural Res. v. Weston, 2003 VT 58, ¶ 16, 175 Vt. 573, 830 A.2d 92 (mem.). We will not disturb the court’s factual findings unless, viewing the evidence most favorably to the prevailing party, the findings are clearly erroneous. Timb erlake Assocs. v. City of Winooksi, 170 Vt. 643, 645, 756 A.2d 774, 776 (2000) (mem.). Thus, as long as there is some credible evidence to support a finding, we will not disturb it, “even if it is contradicted by substantial evidence.” Id. at 645, 756 A.2d at 776-77. Further, we will uphold the court’s legal conclusions “if reasonably supported by the findings.” Clayton v. Clayton Invs., Inc., 2007 VT 38A, ¶ 9, 182 Vt. 541, 929 A.2d 713 (mem.).

¶ 10. With these standards in mind, we address Luzenac’s first claim of error, which goes to the heart of this case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCullough Crusing, Inc. Act 250
Vermont Superior Court, 2016
Roger Rowe Act 250
Vermont Superior Court, 2016
Leverenz Act 250 JO
Vermont Superior Court, 2015
Rowe Act 250 Gravel Pit
Vermont Superior Court, 2015
Evans Group, Inc. v. Robert Foti and Foti Fuels, Inc.
2012 VT 77 (Supreme Court of Vermont, 2012)
Fontaine Act 250 Application
Vermont Superior Court, 2011
In Re Village Associates Act 250 Land Use Permit
998 A.2d 712 (Supreme Court of Vermont, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
2009 VT 88, 980 A.2d 286, 186 Vt. 590, 2009 Vt. LEXIS 101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-hamm-mine-act-250-jurisdiction-vt-2009.