Fontaine Act 250 Application

Vermont Superior Court·Decided December 20, 2011·No. 12-1-10 Vtec·Published

Opinion

STATE OF VERMONT

SUPERIOR COURT ENVIRONMENTAL DIVISION

}

In re Fontaine Act 250 Application } Docket No. 12-1-10 Vtec In re Fontaine Act 250 Reconsideration } Docket No. 143-9-10 Vtec (Appeals of Fontaine) } }

Decision and Order

Appellant-Applicants Daniel Fontaine and Michael Fontaine (Appellants)

appealed from a decision by the District 4 Environmental Commission (District Commission) ruling that Act 250 Rule 34(E) prevented its consideration of Appellants’ application for partial findings for a proposed residential development located within the sand extraction areas governed by an existing Act 250 permit. They also appealed from the District Commission’s subsequent decision declining to reconsider its decision, and the two appeals were consolidated. Appellants are represented by John W. O’Donnell, Esq.; the Land Use Panel of the Natural Resources Board (NRB) is represented by John H. Hasen, Esq.; and the Agency of Natural Resources (ANR) is represented by Elizabeth Lord, Esq.

Many of the facts necessary to decide the Rule 34(E) issue are undisputed; an evidentiary hearing was held before Merideth Wright, Environmental Judge, to take any remaining evidence relevant to the Rule 34(E) issue. The parties were given the opportunity to submit written memoranda and requests for findings. Upon consideration of the evidence, of the undisputed facts, and of the written memoranda and requests for findings filed by the parties, the Court finds and concludes as follows.

Procedural History and Factual Background Appellants’ project property consists of approximately 293.5 acres of land on both sides of Chapman Lane in the Town of Williston, located southerly of the Winooski River and easterly of North Williston Road. Parcel #1, consisting of 135 acres, is located northerly of Chapman Lane and is open land currently in agricultural use. Parcel #2, consisting of 158.5 acres, is located southerly of Chapman Lane and contains the two sand extraction pits and their associated roadway that are the subject of the Act 250 Permit at issue in the present appeal. Parcel #2 contains an open area near two ponds adjoining Chapman Lane, and is otherwise forested, except for the areas within the sand extraction pits. The forested areas of the project property, as well as those of adjoining property, function as a deer wintering area and have been so identified on maps produced by ANR.

In 1991, Appellants1 applied for and were issued Act 250 Land Use Permit # 4C0893 (the 1991 Permit) for the operation of a sand extraction pit on a portion of that parcel. The Permit authorized Appellants to disturb approximately 42 acres of the parcel, consisting of a 5.5-acre sand extraction area, a 33.9-acre sand extraction area, and a total of 2.5 acres of access roadways serving those areas.

The District Commission’s Findings of Fact related to the 1991 Permit state that the property contains “an important deer wintering area” and that Appellants had “agreed to conditions recommended by the Vermont Department of Fish and Wildlife to mitigate the impact” of the sand extraction project on the deer wintering area. As stated in Condition 10 of the 1991 Permit, the permit required that the remaining 98 forested acres of the project parcel be “retained in its natural condition as winter shelter for deer” and that it be managed under a forest management plan,

1 For ease of reference in discussing the permit history of the project property, the term Appellants includes the present Appellants’ predecessors and co-applicants.

to be updated every five years, “specifically outlining [the] protection and enhancement of the hemlock and white pine component” of that forested area. Condition 12 of the 1991 Permit required that sand extraction operations be suspended each winter from December 1 through March 31, except if special circumstances require sand extraction, and then only if the Department of Fish and Wildlife determines that such extraction will not result in any adverse effect on local deer populations. Condition 13 of the Permit required that, “following the extraction of sand resources,” the cleared areas are required to be replanted “to a hemlock/white pine cover type” and the road is required to be replanted to grass. The 1991 Permit allowed extraction to occur through October 1, 2016, unless the duration of the permit was extended by the District Commission. Restoration of the first extraction pit began in or about 2005, as discussed in the letter in evidence as Exhibit CC.

The Town Plan, Subdivision Regulations, and Zoning Regulations have each been amended over time since the original 1991 Permit was issued. Appellants did not provide any editions of any of those documents, but did provide evidence in their Exhibit 7 that the municipal regulations require that 75% of the parcel be preserved as open space. They also provided evidence that projects served by a loop road or cul-de-sac, that is, with only single access onto the adjoining street network, are limited to no more than 40 units, but that 50 units had been allowed under the regulations as they existed in 2004. Appellants did not provide evidence of any other specific changes in the municipal regulations over time since the 1991 permit conditions were imposed that would affect their ability to locate development outside the boundaries of the deer wintering area. Appellants also described the phased process for approval of residential development in the Town of Williston, which requires an applicant to obtain allocations of residential dwelling construction many years in advance of the proposed construction dates.

In March 2006, the District Commission issued Act 250 Land Use Permit # 4C0893-1 (the Dash-1 Amendment) as an amendment to the 1991 Permit, allowing Appellants to use 36.1 acres of the 152.5-acre neighboring Chapman Parcel2 for sand pit operations, and to use an existing logging road characterized in Condition 19 of the Dash-1 Amendment as “connect[ing] the existing Fontaine Pit with the proposed pit on the Chapman parcel.” Condition 18 of the Dash-1 Amendment required “the remaining 74.6 acres” (presumably of the forested portion of the Chapman parcel) to be “retained in perpetuity as protected deer wintering area.” Conditions 20, 21, and 22 are similar to conditions of the 1991 Permit and include requirements addressing winter operations, forest management, and reclamation by replanting the extraction areas “to a hemlock/white pine cover type” and replanting the roadway with grass. Paragraph 38 of the Dash-1 Amendment extended the expiration date of the permit to December 1, 2030, and the reclamation completion date to December 1, 2035, and specifically stated that the permit “shall not expire until the Commission has determined that such reclamation has been completed.” It is not clear from the materials provided by the parties whether the extended expiration date applies only to operations on the Chapman parcel or also extended the expiration dates regarding the original Fontaine pit sites; Appellants appear to treat the Fontaine pit sites as continuing to have a 2016 restoration date.

In December 2006 and in 2007, the District Commission issued two additional permit amendments applicable to operations on the Chapman Parcel. Permit # 4C0893-2 (the Dash-2 Amendment) approved a haul road between the two approved pits on the Chapman Parcel. The Dash-2 Amendment reiterated the conditions related to the deer wintering area contained in the Dash-1 Amendment,

2 Based on a notation on the project plans in evidence as Exhibit 9, the Chapman Parcel appears to be located easterly of the southerly project parcel.

Free access — add to your briefcase to read the full text and ask questions with AI

Fontaine Act 250 Application, (Vt. Ct. App. 2011).

Fontaine Act 250 Application (Fontaine Act 250 Application) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In Re Nehemiah Associates, Inc.
719 A.2d 34 (Supreme Court of Vermont, 1998)
In Re Huntley
2004 VT 115 (Supreme Court of Vermont, 2004)
In Re Stowe Club Highlands
687 A.2d 102 (Supreme Court of Vermont, 1996)
In Re Hamm Mine Act 250 Jurisdiction
2009 VT 88 (Supreme Court of Vermont, 2009)