Fontaine Act 250 Application

CourtVermont Superior Court
DecidedDecember 20, 2011
Docket12-1-10 Vtec
StatusPublished

This text of Fontaine Act 250 Application (Fontaine Act 250 Application) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fontaine Act 250 Application, (Vt. Ct. App. 2011).

Opinion

STATE OF VERMONT

SUPERIOR COURT ENVIRONMENTAL DIVISION

} In re Fontaine Act 250 Application } Docket No. 12-1-10 Vtec In re Fontaine Act 250 Reconsideration } Docket No. 143-9-10 Vtec (Appeals of Fontaine) } }

Decision and Order

Appellant-Applicants Daniel Fontaine and Michael Fontaine (Appellants)

appealed from a decision by the District 4 Environmental Commission (District

Commission) ruling that Act 250 Rule 34(E) prevented its consideration of

Appellants’ application for partial findings for a proposed residential development

located within the sand extraction areas governed by an existing Act 250 permit.

They also appealed from the District Commission’s subsequent decision declining to

reconsider its decision, and the two appeals were consolidated. Appellants are

represented by John W. O’Donnell, Esq.; the Land Use Panel of the Natural

Resources Board (NRB) is represented by John H. Hasen, Esq.; and the Agency of

Natural Resources (ANR) is represented by Elizabeth Lord, Esq.

Many of the facts necessary to decide the Rule 34(E) issue are undisputed; an

evidentiary hearing was held before Merideth Wright, Environmental Judge, to take

any remaining evidence relevant to the Rule 34(E) issue. The parties were given the

opportunity to submit written memoranda and requests for findings. Upon

consideration of the evidence, of the undisputed facts, and of the written

memoranda and requests for findings filed by the parties, the Court finds and

concludes as follows.

1 Procedural History and Factual Background

Appellants’ project property consists of approximately 293.5 acres of land on

both sides of Chapman Lane in the Town of Williston, located southerly of the

Winooski River and easterly of North Williston Road. Parcel #1, consisting of 135

acres, is located northerly of Chapman Lane and is open land currently in

agricultural use. Parcel #2, consisting of 158.5 acres, is located southerly of

Chapman Lane and contains the two sand extraction pits and their associated

roadway that are the subject of the Act 250 Permit at issue in the present appeal.

Parcel #2 contains an open area near two ponds adjoining Chapman Lane, and is

otherwise forested, except for the areas within the sand extraction pits. The forested

areas of the project property, as well as those of adjoining property, function as a

deer wintering area and have been so identified on maps produced by ANR.

In 1991, Appellants1 applied for and were issued Act 250 Land Use Permit

# 4C0893 (the 1991 Permit) for the operation of a sand extraction pit on a portion of

that parcel. The Permit authorized Appellants to disturb approximately 42 acres of

the parcel, consisting of a 5.5-acre sand extraction area, a 33.9-acre sand extraction

area, and a total of 2.5 acres of access roadways serving those areas.

The District Commission’s Findings of Fact related to the 1991 Permit state

that the property contains “an important deer wintering area” and that Appellants

had “agreed to conditions recommended by the Vermont Department of Fish and

Wildlife to mitigate the impact” of the sand extraction project on the deer wintering

area. As stated in Condition 10 of the 1991 Permit, the permit required that the

remaining 98 forested acres of the project parcel be “retained in its natural condition

as winter shelter for deer” and that it be managed under a forest management plan,

1 For ease of reference in discussing the permit history of the project property, the term Appellants includes the present Appellants’ predecessors and co-applicants.

2 to be updated every five years, “specifically outlining [the] protection and

enhancement of the hemlock and white pine component” of that forested area.

Condition 12 of the 1991 Permit required that sand extraction operations be

suspended each winter from December 1 through March 31, except if special

circumstances require sand extraction, and then only if the Department of Fish and

Wildlife determines that such extraction will not result in any adverse effect on local

deer populations. Condition 13 of the Permit required that, “following the

extraction of sand resources,” the cleared areas are required to be replanted “to a

hemlock/white pine cover type” and the road is required to be replanted to grass.

The 1991 Permit allowed extraction to occur through October 1, 2016, unless the

duration of the permit was extended by the District Commission. Restoration of the

first extraction pit began in or about 2005, as discussed in the letter in evidence as

Exhibit CC.

The Town Plan, Subdivision Regulations, and Zoning Regulations have each

been amended over time since the original 1991 Permit was issued. Appellants did

not provide any editions of any of those documents, but did provide evidence in

their Exhibit 7 that the municipal regulations require that 75% of the parcel be

preserved as open space. They also provided evidence that projects served by a

loop road or cul-de-sac, that is, with only single access onto the adjoining street

network, are limited to no more than 40 units, but that 50 units had been allowed

under the regulations as they existed in 2004. Appellants did not provide evidence

of any other specific changes in the municipal regulations over time since the 1991

permit conditions were imposed that would affect their ability to locate

development outside the boundaries of the deer wintering area. Appellants also

described the phased process for approval of residential development in the Town

of Williston, which requires an applicant to obtain allocations of residential dwelling

construction many years in advance of the proposed construction dates.

3 In March 2006, the District Commission issued Act 250 Land Use Permit

# 4C0893-1 (the Dash-1 Amendment) as an amendment to the 1991 Permit, allowing

Appellants to use 36.1 acres of the 152.5-acre neighboring Chapman Parcel2 for sand

pit operations, and to use an existing logging road characterized in Condition 19 of

the Dash-1 Amendment as “connect[ing] the existing Fontaine Pit with the proposed

pit on the Chapman parcel.” Condition 18 of the Dash-1 Amendment required “the

remaining 74.6 acres” (presumably of the forested portion of the Chapman parcel) to

be “retained in perpetuity as protected deer wintering area.” Conditions 20, 21, and

22 are similar to conditions of the 1991 Permit and include requirements addressing

winter operations, forest management, and reclamation by replanting the extraction

areas “to a hemlock/white pine cover type” and replanting the roadway with grass.

Paragraph 38 of the Dash-1 Amendment extended the expiration date of the permit

to December 1, 2030, and the reclamation completion date to December 1, 2035, and

specifically stated that the permit “shall not expire until the Commission has

determined that such reclamation has been completed.” It is not clear from the

materials provided by the parties whether the extended expiration date applies only

to operations on the Chapman parcel or also extended the expiration dates

regarding the original Fontaine pit sites; Appellants appear to treat the Fontaine pit

sites as continuing to have a 2016 restoration date.

In December 2006 and in 2007, the District Commission issued two additional

permit amendments applicable to operations on the Chapman Parcel. Permit

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Nehemiah Associates, Inc.
719 A.2d 34 (Supreme Court of Vermont, 1998)
In Re Huntley
2004 VT 115 (Supreme Court of Vermont, 2004)
In Re Stowe Club Highlands
687 A.2d 102 (Supreme Court of Vermont, 1996)
In Re Hamm Mine Act 250 Jurisdiction
2009 VT 88 (Supreme Court of Vermont, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
Fontaine Act 250 Application, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fontaine-act-250-application-vtsuperct-2011.