Roger Rowe Act 250

CourtVermont Superior Court
DecidedJanuary 19, 2016
Docket96-7-12 Vtec
StatusPublished

This text of Roger Rowe Act 250 (Roger Rowe Act 250) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roger Rowe Act 250, (Vt. Ct. App. 2016).

Opinion

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION Vermont Unit Docket No. 96-7-12 Vtec

Roger Rowe et al A250 Gravel Pit DECISION ON THE MERITS

This matter relates to an existing gravel pit located off Furnace Road in Pittsford, Vermont. Roger and Erma Rowe obtained an Act 250 land use permit to operate the gravel pit in 1980 (Permit #1R0387). In 2001, Casella Construction, Inc. and the Rowes applied for and received an Act 250 permit amendment in order to enlarge the pit (Permit #1R0387-2). Permit #1R0387-2 was appealed to the former Environmental Board, now the Land Use Panel of the Natural Resources Board, by a group of interested parties and the applicants. The parties reached a settlement agreement dated April 1, 2003. The Environmental Board issued Permit #1R0387-2-EB (the EB Permit), expressly incorporating additional conditions expressed within the parties’ settlement agreement as well as the amended conditions from Permit #1R0387-2. Among other conditions, the EB Permit included conditions restricting the amendment of permit conditions regarding phasing, rates of extraction, and reclamation. In February 2012, Casella Construction, Inc., Roger and Erma Rowe, and the State of Vermont (Applicants) filed an application to amend the EB Permit and expand the existing pit onto a portion of adjacent lands owned by the State of Vermont and to extract up to 100,000 cubic yards of gravel per year in five phases over a 20-year period (-3 Application). Casella had a pre-application meeting with Act 250 Coordinator William Burke. Casella’s representative, Mr. Poirier, left that meeting with the understanding that Applicants were required to file a permit amendment application, not a new permit application. Neighboring property owners (the Neighbors), most of whom were parties to the EB Permit negotiations, oppose the amendment, arguing that it is barred by the terms of the EB Permit, the parties’ prior settlement agreement, and Act 250 Rule 34(E) (the Stowe Club Highlands doctrine). On June 21, 2012, the District 1 Commission (the Commission) dismissed the -3 Application, concluding that the permit amendment was barred by both the terms of the EB Permit and Rule 34(E). Casella Construction, Inc. timely appealed the Commission’s dismissal to this Court and raised four questions for the Court’s review. These questions include whether its application should be treated as a new and distinct application and not an amendment, and, if treated as an amendment, whether the amendment application violates the non-amendment provisions in Applicants’ EB Permit and Act 250 Rule 34(E). Our consideration of this matter was placed on inactive status while the parties litigated related issues in the Civil Division of the Vermont Superior Court. In a July 22, 2015 decision on cross-motions for summary judgment, we announced our intention to grant summary judgment under Rule 56(f) to the Neighbors, on grounds that the pit had been fully reclaimed and jurisdiction under the EB permit had ceased, meaning that there was no longer a valid permit to amend. See In re Roger Rowe A250 Gravel Pit, No. 96-7- 12 Vtec, slip op. at 7 (Vt. Super. Ct. Envtl. Div. July 22, 2015). The parties filed responses, and we determined that issues of material fact existed regarding whether the pit was actually reclaimed. See In re Roger Rowe A250 Gravel Pit, No. 96-7-12 Vtec, slip op. at 2 (Vt. Super Ct. Envtl. Div. Sept. 11, 2015). We therefore scheduled the matter for a merits hearing on the limited issue of whether the pit was in fact reclaimed. The Court conducted a site visit to the subject property on January 13, 2016, immediately followed by a single day merits hearing at the Vermont Superior Court, Rutland Criminal Division courthouse in Rutland, Vermont. Appearing at the site visit and trial were Casella Construction, Inc., represented in this appeal by Harry R. Ryan, Esq.; Mary Marzec- Gerrior, represented by Benjamin W. Putnam, Esq.; the Natural Resources Board represented by Gregory J. Boulbol, Esq.; and interested party Kelly Lyon appearing pro se. Based upon the evidence presented at trial, which was put into context by the site visit, the Court renders the following Findings of Fact and Conclusions of Law.

Findings of Fact 1. In 1980, Roger and Erma Rowe obtained Land Use Permit #1R0387 to operate a gravel pit on their property off Furnace Road in Pittsford, Vermont (the Rowe Pit).

2 2. The Rowe Pit encompassed an area of 19.6 acres of the total 53.9 acres owned by the Rowes. 3. In 2001, Casella Construction, Inc. and the Rowes applied for and received an Act 250 permit amendment to enlarge the Rowe Pit (Permit #1R0387-2). A group of interested parties, including the Marzec-Gerriors, appealed Permit #1R0387-2. 4. On February 12, 2003, the Rowes and Casella Construction, Inc., entered into a settlement agreement with the interested parties, including the Marzec-Gerriors. 5. On April 17, 2003, the Environmental Board issued amended Act 250 Land Use Permit #1R0387-2-EB (the EB Permit) with three conditions. 6. Condition 1 of the EB Permit expressly incorporates all but conditions 3 and 14 of Permit #1R0387-2. It also incorporates additional conditions expressed within the parties’ settlement agreement.1 7. Permit #1R0387-2 authorized the extraction of 100,000 cubic yards of gravel annually from the Rowe Pit; the construction of a temporary scale, scale housing building, and washroom facilities adjacent to the existing gravel extraction operation; and progressive reclamation as the Rowe Pit expanded. 8. Condition 33 of Permit #1R0387-2, which was incorporated into the EB Permit, required that all gravel extraction and site reclamation be completed by September 15, 2010. 9. Condition 7 of Permit #1R0387-2, which was incorporated into the EB Permit, provided “The commercial extraction from the pit shall cease, and the entire site be certified by affidavit to the town and to the commission as fully reclaimed no later than October 15, 2010.” 10. The Rowe Pit was excavated in four phases, with reclamation occurring at the conclusion of each phase.

1 This settlement agreement has been the subject of litigation between these same parties before the Vermont Superior Court, Civil Division. This Court admitted a copy of the settlement agreement as Exhibit 4. The Court required all text in the settlement agreement except for the “Agreed Permit Conditions” to be redacted because Attorney Putnam conceded that only the additional conditions were relevant to the issues before the Court, and because the agreement was subject to a confidentiality clause. Casella asked the Court to rule definitively that the language in the EB Permit incorporating “the terms of the parties’ settlement agreement” incorporates only the conditions in the settlement agreement (and not the preamble language). Because we ultimately find that the permit is expired, see infra p. 11, we decline to authoritatively construe the EB Permit on mootness grounds and because there was no offer that other provisions are relevant to the issues before the Court.

3 11. Casella completed phases I through III, including reclamation, without complaints or violations. 12. In October 2010, Ms. Lyon contacted Robert Steadman, Chief Financial Officer (and de facto general manager) of Casella, and informed him that Casella was operating in violation of its permit, as the EB Permit required phase IV to be completed by October 15, 2010. 13. As Casella failed to timely complete and close the Rowe Pit, it self-reported to the Act 250 District Coordinator to resolve the violation. 14. Casella worked cooperatively with the Land Use Panel of the Natural Resources Board and accepted, without appeal, a November 17, 2010 Administrative Order (AO). 15. The AO set new reclamation deadlines. The AO required and authorized Casella to complete the grading portion of the reclamation procedures by December 23, 2010.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Hamm Mine Act 250 Jurisdiction
2009 VT 88 (Supreme Court of Vermont, 2009)
In Re Taft Corners Associates, Inc.
632 A.2d 649 (Supreme Court of Vermont, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Roger Rowe Act 250, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roger-rowe-act-250-vtsuperct-2016.