DeVita Subdivision Amendment - Decision on Motion

CourtVermont Superior Court
DecidedOctober 1, 2018
Docket164-12-17 Vtec
StatusPublished

This text of DeVita Subdivision Amendment - Decision on Motion (DeVita Subdivision Amendment - Decision on Motion) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DeVita Subdivision Amendment - Decision on Motion, (Vt. Ct. App. 2018).

Opinion

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION Docket No. 164-12-17 Vtec

DeVita Subdivision Amendment DECISION ON MOTION

The present appeal is of a Town of Williston (Town) Development Review Board (DRB) November 14, 2017 decision (the 2017 Decision) denying Frank and Christel DeVita’s application for a discretionary permit. The DeVitas appeal the 2017 Decision to this Court. Before the Court are the parties’ cross-motions for summary judgment on Questions 1 and 2, as well as the Town’s motion for summary judgment on Question 3. The DeVitas are represented by Christopher Roy, Esq. The Town is represented by Paul Gilles, Esq. Legal Standard Pursuant to V.R.C.P. 56(a), we grant summary judgment to a party “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” V.R.C.P. 56(a), applicable here through V.R.E.C.P. 5(a)(2). In determining whether there is any dispute over a material fact, “we accept as true allegations made in opposition to the motion for summary judgment, so long as they are supported by affidavits or other evidentiary material.” White v. Quechee Lakes Landowner’s Ass’n, Inc., 170 Vt. 25, 28 (1999) (citation omitted). When considering cross-motions for summary judgment, the Court considers each motion individually and gives the opposing party the benefit of all reasonable doubts and inferences. City of Burlington v. Fairpoint Commc’ns, Inc., 2009 VT 59, ¶ 5, 186 Vt. 332. Factual Findings We recite the following factual findings solely for the purpose of deciding the pending motions. 1. The DeVitas own property located on Fieldstone Drive (the Property) in Williston, Vermont. The Property is 35.44 acres. 2. The Property was originally created by subdivision on December 19, 1995 (the Original Permit). The Original Permit created four building lots (Lots 1 through 4), the Property (Lot 5), a wastewater disposal lot, and a proposed right-of-way for a public roadway. 3. Lots 1 through 4 range in size from 1.26 to 1.53 acres. The wastewater disposal lot is 1.2 acres. 4. The DeVitas built a home on Lot 1, which is located at 290 Fieldstone Drive. 5. The Town’s Unified Development Bylaw (the Bylaw) sets forth a multi-stage review process for development requiring a discretionary permit. Bylaw Chapter 6. 6. Pre-application review is the first step in this process. Bylaw § 6.2 sets forth the Town’s pre-application review process. 7. On March 18, 2016, the DeVitas submitted a pre-application to further subdivide the Property (the 2016 Pre-Application). Additionally, they sought to merge the wastewater disposal lot with Lot 1. The 2016 Pre-Application proposed to reconfigure Lot 5 to create three building lots and leave the remaining land as open space (the Project). 8. On April 26, 2016 and May 24, 2016, the DRB held hearings on the 2016 Pre-Application. The minutes of these hearings, as approved on June 17, 2016, authorized the DeVitas to file an application for a discretionary permit to amend the Original Permit as proposed (the 2016 Decision). 9. The 2016 Decision included various recommendations made by the DRB regarding the application. The list of recommendations included two crossed-out recommendations relating to the Public Works design standards, which would have recommended a cul-de-sac instead of a hammerhead road design at the pre-application stage. 10. A June 17, 2016 cover letter sent with the minutes states: “You are advised that decisions of the DRB may be appealed to the Vermont Environmental Court, within 30 days from the date of this letter, as provided by 24 V.S.A. § 4471.” 11. The 2016 Decision was not appealed. 12. On March 28, 2017, the DRB approved three units of growth management allocation for the three building lots proposed in the 2016 Pre-Application, beginning on July 1, 2017. 13. The DeVitas then applied for a discretionary permit. On November 14, 2017, the DRB denied the permit (the 2017 Decision). Among the reasons for denial were conflicts with the conditions of the Original Permit and access which did not comply with Public Works design standards. Specifically, the DRB found fault with the proposed lot configuration and the road design, which was a hammerhead instead of a cul-de-sac. 14. The DeVitas appealed the 2017 Decision to this Court on December 13, 2017. Discussion The motions presently before the Court ask us to decide whether the DeVitas’ discretionary permit should be granted because the lot configuration and hammerhead road design issues were not raised by the Town DRB at the pre-application stage of the 2016 Decision. The DeVitas assert that the 2016 Decision is a final and binding decision, which approved the lot configuration and hammerhead road because it did not expressly disapprove of those aspects of the Project. The Town, they argue, should be bound by its tacit approval of those design elements at pre-application, so that it cannot later deny their discretionary permit on those same grounds. While we subscribe to the DeVitas’ view that certain decisions of the Town at the pre- application stage are final and binding, we do not agree that the Town’s representations regarding the lot and road design fall within that category of decision. The Town’s choice to leave the lot and road design questions for a subsequent stage of the application process falls outside the scope of what constitutes a final and binding decision at the pre-application stage. The Town was not bound to approve the lot configuration and hammerhead road design at the discretionary permit stage of the application. Next, the Town’s motion on Question 3 requires us to decide whether the Town was equitably estopped from denying the DeVitas’ discretionary permit because of its representations at the pre-application stage. Because the facts do not support a claim of equitable estoppel, we conclude that the Town was not precluded from denying the discretionary permit. I. The 2016 Decision is a final and binding decision but did not approve the contested design elements of the Project. The DeVitas assert that the 2016 Decision is a final and binding decision that effectively approved the lot configuration and hammerhead design aspects of the Project pursuant to 24 V.S.A. § 4472(d). They argue that the Town could not later deny them a permit on those grounds and was required to approve the discretionary permit. The Town disagrees. It argues that the 2016 Decision is only final and binding for the limited determination reached therein, namely, the determination that the application could progress to the growth management allocation phase. The Town offers that the 2016 Decision does not approve the number or location of lots, the access and road layout, or other substantive project details. Such issues are reviewed in greater detail later in the application process. A failure to appeal decisions like the 2016 Pre-Application determination results in all interested parties being bound by the decision. 24 V.S.A § 4472(d). The term “decision” is not statutorily defined, but “the word connotes finality . . . [;] if a ‘decision’ does not resolve an issue it is not really a decision, but mere commentary or analysis.” In re Saxon Partners LLC BJ’s Warehouse Sketch Plan, No. 5-1-16 Vtec, slip op. at 2 (Vt. Super. Ct. Envtl. Div. Jul. 15, 2016) (Walsh, J.). The 2016 Decision is a final and binding decision with regards to the determinations made therein. See In re Pintair Discretionary Permit, No. 54-5-15 Vtec, slip op. at 11 (Vt. Super. Ct. Envtl. Div. May 27, 2016) (Walsh, J.) (concluding that an unappealed pre-application decision is final and binding). Therefore, we must consider what legal issues the 2016 Decision determined to discover what aspects of that decision were final and binding on the DRB.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sobel v. City of Rutland
2012 VT 84 (Supreme Court of Vermont, 2012)
City of Burlington v. Fairpoint Communications, Inc.
2009 VT 59 (Supreme Court of Vermont, 2009)
In Re Appeal of Trahan Nov
2008 VT 90 (Supreme Court of Vermont, 2008)
Beecher v. Stratton Corp.
743 A.2d 1093 (Supreme Court of Vermont, 1999)
In Re Stowe Club Highlands
668 A.2d 1271 (Supreme Court of Vermont, 1995)
Greenmoss Builders, Inc. v. King
580 A.2d 971 (Supreme Court of Vermont, 1990)
L & H TRANSP., INC. v. Drew Agency, Inc.
403 N.W.2d 223 (Supreme Court of Minnesota, 1987)
Fisher v. Poole
453 A.2d 408 (Supreme Court of Vermont, 1982)
In Re Lyon
2005 VT 63 (Supreme Court of Vermont, 2005)
Ragosta v. Wilder
592 A.2d 367 (Supreme Court of Vermont, 1991)
In Re McDonald's Corp.
505 A.2d 1202 (Supreme Court of Vermont, 1985)
In Re Appeal of Lashins
807 A.2d 420 (Supreme Court of Vermont, 2002)
In re All Metals Recycling, Inc.
2014 VT 101 (Supreme Court of Vermont, 2014)
Welch v. H. P. Hood & Sons, Inc.
409 A.2d 603 (Supreme Court of Vermont, 1979)
Vermont Structural Steel v. State Department of Taxes
569 A.2d 1066 (Supreme Court of Vermont, 1989)
White v. Quechee Lakes Landowners' Ass'n
742 A.2d 734 (Supreme Court of Vermont, 1999)
Gravel & Shea v. White Current Corp.
752 A.2d 19 (Supreme Court of Vermont, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
DeVita Subdivision Amendment - Decision on Motion, Counsel Stack Legal Research, https://law.counselstack.com/opinion/devita-subdivision-amendment-decision-on-motion-vtsuperct-2018.