Appeal of Rivers Development, LLC CU Appeal

CourtVermont Superior Court
DecidedNovember 21, 2008
Docket7-01-05 Vtec
StatusPublished

This text of Appeal of Rivers Development, LLC CU Appeal (Appeal of Rivers Development, LLC CU Appeal) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Appeal of Rivers Development, LLC CU Appeal, (Vt. Ct. App. 2008).

Opinion

STATE OF VERMONT ENVIRONMENTAL COURT

} In re Rivers Dev. Con. Use Appeal } Docket No. 7-1-05 Vtec } ******************************************************************** } In re Rivers Dev. Act 250 Appeal } Docket No. 68-3-07 Vtec } ******************************************************************** } In re Rivers Dev. ANR UIC JO } Docket No. 183-8-07 Vtec } ******************************************************************** } In re Rivers Dev. Indirect Discharge JO } Docket No. 248-11-07 Vtec } ******************************************************************** } In re Rivers Dev. Direct Discharge } Docket No. 157-7-08 Vtec Permit Appeal } }

Decision on Multiple Motions

These appeals arise out of decisions involving the efforts of Rivers Development, LLC (“Rivers”) to gain the necessary approvals to construct a rock extraction and processing quarry (“Quarry”) in the Town of Moretown. Docket Number 7-1-05 Vtec concerns the DRB’s denial of Rivers’ zoning and conditional use applications. Docket Number 68-3-07 Vtec concerns the denial by the District #5 Environmental Commission of Rivers’ Act 250 land use permit application. Docket Number 183-8-07 Vtec concerns the opinion issued by the Vermont Agency of Natural Resources (“the Agency”) that Rivers’ Quarry does not require an underground injection control (“UIC”) permit. Docket Number 248-11-07 Vtec concerns the jurisdictional opinion issued by the Agency that Rivers’ Quarry requires an indirect discharge permit. Docket Number 157-7-08 Vtec, which has not previously been consolidated with the remaining dockets, concerns the decision by the Agency, denying Rivers’ application for a direct discharge permit. The consolidated appeals have already been through one phase of trial and are scheduled for another phase of trial beginning on December 8, 2008.

1 Appellant-Applicant Rivers is represented by James Caffry, Esq., and Christopher J. Nordle, Esq.; Cross-Appellant “Neighbors”1 are represented by David L. Grayck, Esq., and Zachary K. Griefen, Esq.; Cross-Appellants Town of Moretown (through its Selectboard), the Moretown Planning Commission, and the Moretown School Board (collectively, “Moretown”) are represented by Ronald A. Shems, Esq., and Geoffrey H. Hand, Esq.; and the Vermont Agency of Natural Resources is represented by Aaron Adler, Esq. This Decision addresses three of the motions that are currently pending before this Court.2 First, Moretown has filed a motion to request that the Court reconsider its July 1, 2008 Entry Order on Moretown’s motion for an immediate judgment on the pleadings, and Rivers has responded in opposition. Second, Rivers has filed a motion to consolidate Docket Number 157- 7-08 with the other four cases that have already been consolidated, and the Agency and Moretown have responded in opposition. Third, the Agency has filed a motion to dismiss Docket Number 183-8-07 (the UIC permit appeal filed by Neighbors) and Docket Number 248- 11-07 (the indirect discharge permit appeal filed by Rivers). Neighbors and Moretown responded in support of dismissal of both cases, while Rivers responded in opposition to dismissing their indirect discharge permit appeal.

Factual Background Most of the factual background for this case has already been described in this Court’s two previous Decisions dated January 8, 2008, and January 11, 2008 (with corrected decisions for both filed on January 18, 2008), as well as the Entry Order of July 1, 2008, from which we incorporate undisputed material facts by this reference. To those descriptions, we need only add the following facts, all of which we understand to be undisputed, unless noted otherwise, and which we note for the sole purpose of putting the motion to consolidate and the motion to dismiss into context:

1 “Neighbors” includes the following individuals, all of whom have appeared as a party in one or more of the consolidated appeals pursuant to V.R.E.C.P. 5(d)(2): Thomas Allen, Robert Dansker, Jack Byrne, Virginia Farley, Doug Hall, Cindy Hall, June Holden Life Estate, Rick Hungerford, Rita Larocca, Robert McMullin, Beverly McMullin, John Porter, Scott Sainsbury, Patricia Sainsbury, Sandy Porter, Benjamin Sanders, Denis Sanders, Karen Sharpwolf, Ruth Van Heuven, Martin Van Heuven, and Constance Van Heuven. This Court’s July 3, 2007 Decision denied certain requests for additional party status, but did not disturb these Neighbors’ pre-existing party status. Although not all of the Neighbors have made appearances in each consolidated case, we use the term “Neighbors” here to represent whichever subset of Neighbors have appeared in each appeal. We also use the term Neighbors to include Arthur Hendrickson and Linda Hendrickson, who are allied with the Neighbors, even though they are representing themselves. 2 The Court addressed other pending motions in two separate Entry Orders dated November 18, 2008. Any motions that are still pending will be addressed at the upcoming in-person hearing at 1:00 p.m. on November 24, 2008.

2 1. On April 15, 2004, Rivers submitted a proposed discharge plan for the proposed project (including plans dated April 12, 2004) and requested that the Agency determine that a direct discharge permit is not needed. At this point, Rivers apparently did not want to have to obtain a direct discharge permit for the Quarry. 2. On April 19, 2004, Randy Bean sent a letter on behalf of the Agency to Rivers noting that the Agency had determined that a direct discharge permit was not needed for the proposed project.3 3. On September 20, 2004, Rivers submitted revisions to its proposed discharge plan and asked the Agency to review these revisions. The Agency then conducted a site visit two days later, on September 22, 2004. 4. On September 27, 2004, Randy Bean sent a letter on behalf of the Agency to Rivers noting again that the Agency had determined that a direct discharge permit was not needed for the proposed project, even as revised.4 5. On December 13, 2004, the Agency Commissioner noted that he had “determined that Randy Bean’s letter, dated September 27, 2004, that indicated that no direct discharge permit is needed for the proposed quarry project in Moretown[,] is correct and therefore constitutes the final decision of the Agency.” 6. No one appealed the decision that was noted in the September 27, 2004 letter and in the December 13, 2004 letter. 7. Rivers apparently later used the determination noted in the September 27, 2004 and the December 13, 2004 letters when Rivers made representations to the District Commission to show that no direct discharge permit was needed for the Quarry. 8. During the roughly three years between December 13, 2004 (when the Agency Commissioner confirmed that no direct discharge permit was needed) and December 28, 2007 (when Rivers filed an application for a direct discharge permit), Rivers made additional modifications to the proposed discharge design for its proposed project. The parties disagree about the extent of those modifications and when those modifications were properly brought to the attention of the Agency. Rivers presented some of these modifications in its application for a UIC permit, which was received by the Agency on May 9, 2006, and which contained plans that

3 Although the April 19, 2004 letter, as well as the September 27, 2004 letter, refers only to a “discharge permit,” it is clear from the context that both of these letters were referring to direct discharge permits, as the Agency Commissioner noted in his December 13, 2004 letter. 4 See footnote 3 above.

3 were dated May 5, 2006. The Agency disputes whether all of these modifications were clearly brought to the Agency’s attention in the proper format.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re T.C.
2007 VT 115 (Supreme Court of Vermont, 2007)
Greenmoss Builders, Inc. v. King
580 A.2d 971 (Supreme Court of Vermont, 1990)
Rosenthal v. National Life Insurance
486 F. Supp. 1018 (S.D. New York, 1980)
Town of Bennington v. Hanson-Walbridge Funeral Home, Inc.
427 A.2d 365 (Supreme Court of Vermont, 1981)
Rubin v. Sterling Enterprises, Inc.
674 A.2d 782 (Supreme Court of Vermont, 1996)
Trepanier v. Getting Organized, Inc.
583 A.2d 583 (Supreme Court of Vermont, 1990)
Dutch Hill Inn, Inc. v. Patten
303 A.2d 811 (Supreme Court of Vermont, 1973)
Berisha v. Hardy
474 A.2d 90 (Supreme Court of Vermont, 1984)
Scott v. City of Newport
2004 VT 64 (Supreme Court of Vermont, 2004)
State v. Rooney
2008 VT 102 (Supreme Court of Vermont, 2008)
In Re Taft Corners Associates, Inc.
632 A.2d 649 (Supreme Court of Vermont, 1993)
In re Glen M.
575 A.2d 193 (Supreme Court of Vermont, 1990)
In re Grievance of Vermont State Employees' Ass'n
2005 VT 135 (Supreme Court of Vermont, 2005)
In re S.N.
2007 VT 47 (Supreme Court of Vermont, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
Appeal of Rivers Development, LLC CU Appeal, Counsel Stack Legal Research, https://law.counselstack.com/opinion/appeal-of-rivers-development-llc-cu-appeal-vtsuperct-2008.