Great American Insurance Company v. Johnson Controls, Inc.

CourtDistrict Court, S.D. Ohio
DecidedAugust 7, 2020
Docket1:20-cv-00096
StatusUnknown

This text of Great American Insurance Company v. Johnson Controls, Inc. (Great American Insurance Company v. Johnson Controls, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Great American Insurance Company v. Johnson Controls, Inc., (S.D. Ohio 2020).

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF OHIO WESTERN DIVISION

GREAT AMERICAN INSURANCE COMPANY, Case No. 1:20-cv-96 Plaintiff, JUDGE DOUGLAS R. COLE

v.

JOHNSON CONTROLS, INC.,

Defendant.

OPINION AND ORDER

This matter involving a bond dispute arising from an underlying construction project is before the Court on Defendant Johnson Controls, Inc.’s Motion to Compel Arbitration and to Dismiss Plaintiff’s Complaint. (Doc. 3). At the Plaintiff’s request, the Court held a telephone status conference on July 8, 2020, where the parties requested an expedited ruling. Also before the Court is Johnson Controls’ Motion for Stay, which Johnson Controls filed on July 30, 2020. (Doc. 9). For the reasons that follow, the Court determines that, based on the language of the bond and the subcontract at issue, the parties are required to submit the threshold issue of the arbitrability of their dispute to an arbitrator. Thus, the Court GRANTS Defendant’s Motion (Doc. 3), COMPELS the parties to arbitrate the issue of arbitrability (and the merits of the claim, should the arbitrator determine the dispute is arbitrable), DENIES Johnson Controls’ Motion for Stay (Doc. 9), and DISMISSES the action (Doc. 1) WITHOUT PREJUDICE. BACKGROUND Any construction project is complex, but building a hospital is especially so. For the hospital construction project underlying the instant dispute, the project

owner contracted with a general contractor, who enlisted subcontractors, who in turn relied on “sub-subcontractors” to complete specific, specialized work. In theory, by each contributing their part, the hospital would be built on time and on budget. But, as often happens with complex construction projects, delays and performance issues arose. This request for declaratory judgment relates to one such issue.

A. The Construction Subcontract And Great American’s Bond. In October 2017, Defendant Johnson Controls, Inc. (“Johnson Controls”) entered into a subcontract (the “Subcontract”) with Structured Cabling Solutions, Inc. d/b/a SCS Technologies (“SCS”). (Compl., Doc. 1, ¶ 7, #121). The Subcontract required SCS to perform “low voltage cabling work” related to construction of the MUSC Shawn Jenkins Children’s Hospital in Charleston, South Carolina (the “Project”). (Id.). Of particular relevance here, the Subcontract includes an arbitration provision

(the “Arbitration Provision”): 6.6 Disputes If any dispute shall arise between Subcontractor and Contractor in connection with this Subcontract, the parties shall promptly attempt in good faith to settle the same by negotiation. Subcontractor shall give Contractor written notice of its intent to exercise its rights under the Disputes Paragraph at least 30 days prior to initiating any legal action. At any time and at Contractor’s election, the parties shall participate in

1 Refers to PageID Number. mediation under the rules of the American Arbitration Association. The costs of the mediation shall be borne equally by the parties, and such costs shall not be recoverable by either party under the Attorney’s Fees paragraph of this Subcontract. All disputes not settled by negotiation or mediation shall be reserved until the final completion or termination of the Work and negotiation or mediation, at which time they shall be submitted to arbitration in accordance with the prevailing Construction Industry Rules of the American Arbitration Association, except as modified in this paragraph. ... ... Subcontractor further agrees to include a provision in all subcontracts, purchase orders or agreements to provide labor or material in connection with the Work that requires all disputes related to such subcontract, purchase order, or agreement to provide labor or material in connection with the Work to be resolved by arbitration in accordance with the rules of the AAA. Subcontractor authorizes Contractor to demand arbitration on its behalf against any subcontractor or supplier who claims that amounts are due for labor or material provided in connection with the Work. Subcontractor acknowledges that this is a material provision of this Subcontract. (Def.’s Mot. Ex. B, Doc. 3-1, #114–152 (emphasis added)).3

2 Whether the Court may consider the Subcontract in deciding the pending motion is discussed below.

3 The Subcontract also incorporated all higher level contracts, including those one level up, between Johnson Controls and the Project’s general contractor Robins & Morton (the “R&M Subcontract”), and two levels up, between Robins & Morton and the Project owner (the “Prime Contract”), both of which contain their own arbitration provision. The R&M Subcontract provides, in relevant part that:

30.4 Except as provided in Paragraph 30.5, any remaining claims of Subcontractor that cannot be resolved in accordance with the provisions of the Contract Documents or the Subcontract, shall be finally determined by binding arbitration in accordance with the Construction Industry Rules of the American Arbitration Association as those Rules existed on January 1, 1994 ... .

(Mot. to Compel Ex. A, Doc. 3-1, #63). The Prime Contract further requires arbitration in certain instances pursuant to South Carolina’s adoption of the Uniform Arbitration Act. (See In addition to requiring SCS to perform certain specified work, the Subcontract also required SCS to secure a payment and performance bond. (See Compl. at ¶ 8, #12). The plaintiff in this action, Great American Insurance Company (“Great

American”), issued the required bond (the “Bond”) securing SCS’s performance. The Bond named Johnson Controls as the “Obligee” and included a penal sum in the base Subcontract amount of $1,202,045. (See Compl. Ex. 1 (the “Bond”), Doc. 1-1, #18). The Bond further provided that it incorporated the Subcontract by reference: 1. SCOPE OF BOND. The Principal and the Surety, jointly and severally, bind themselves, ... to the Obligee for the performance of the Subcontract, which is incorporated in this bond by reference. In no event shall the Surety’s total obligation exceed the penal amount of this bond. (Id. at #19). After several setbacks related to SCS’s performance, on June 13, 2019, Johnson Controls sent Great American a letter indicating SCS had not upheld its end of the Subcontract and had “walked off the job.” (Compl. at ¶ 10, #12). At that point, Johnson Controls was left with several options under the Subcontract, one of which allowed it to retain a “supplementation contractor” to complete SCS’s unfinished work. (See id. at ¶ 12, #13). While SCS allegedly eventually agreed to return with a “partial crew,” Johnson Controls also went ahead and retained a replacement contractor. (Id.). Johnson Controls informed Great American that the preliminary cost to complete SCS’s

Def.’s Reply Ex. 1-A, Doc. 8-1, #234–35). As described below, these arbitration provisions are irrelevant to the issue currently before the Court. remaining work would be roughly $100,000. (Id. at ¶ 14). Subsequently, Great American and Johnson Controls negotiated a supplementation plan, and Johnson Controls indicated it was holding roughly $209,000 in contract funds that had not yet

been paid to SCS. (Id. at ¶¶ 15–16). Around the same time, Great American also paid $235,000 in claims under the Bond to one of SCS’s materials suppliers. (Id. at ¶ 17). Over the next several months, Johnson Controls and Great American exchanged multiple revised costs to complete, fixed-price costs to complete, and settlement offers in an attempt to negotiate a resolution. (See id. at ¶¶ 18–27, #13– 14). Simultaneously, Johnson Controls continued to submit project cost estimates to

Great American, and the estimated cost to complete SCS’s work continued to rise. (See id.). The last proposal that Johnson Controls tendered, which would be its final, set the fixed-price cost to complete SCS’s work at $1,146,000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Options of Chicago, Inc. v. Kaplan
514 U.S. 938 (Supreme Court, 1995)
Swierkiewicz v. Sorema N. A.
534 U.S. 506 (Supreme Court, 2002)
Tellabs, Inc. v. Makor Issues & Rights, Ltd.
551 U.S. 308 (Supreme Court, 2007)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
United States v. Ozuna-Cabrera
663 F.3d 496 (First Circuit, 2011)
Alan Weiner, D.P.M. v. Klais and Company, Inc.
108 F.3d 86 (Sixth Circuit, 1997)
Compuserve, Inc. v. Vigny International Finance Ltd.
760 F. Supp. 1273 (S.D. Ohio, 1990)
Whittiker v. Deutsche Bank National Trust Co.
605 F. Supp. 2d 914 (N.D. Ohio, 2009)
Bishop v. Gosiger, Inc.
692 F. Supp. 2d 762 (E.D. Michigan, 2010)
Morrison v. Circuit City Stores, Inc.
70 F. Supp. 2d 815 (S.D. Ohio, 1999)
Joseph Ozormoor v. T-Mobil USA, Inc.
354 F. App'x 972 (Sixth Circuit, 2009)
Eric Hilton v. Midland Funding
687 F. App'x 515 (Sixth Circuit, 2017)
Henry Schein, Inc. v. Archer & White Sales, Inc.
586 U.S. 63 (Supreme Court, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
Great American Insurance Company v. Johnson Controls, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/great-american-insurance-company-v-johnson-controls-inc-ohsd-2020.