Petrofac, Inc. v. DynMcDermott Petroleum Operations Co.

687 F.3d 671, 2012 WL 2892401, 2012 U.S. App. LEXIS 14610
CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 17, 2012
Docket11-20141
StatusPublished
Cited by179 cases

This text of 687 F.3d 671 (Petrofac, Inc. v. DynMcDermott Petroleum Operations Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Petrofac, Inc. v. DynMcDermott Petroleum Operations Co., 687 F.3d 671, 2012 WL 2892401, 2012 U.S. App. LEXIS 14610 (5th Cir. 2012).

Opinion

JENNIFER WALKER ELROD, Circuit Judge:

DynMcDermott Petroleum Operations Company (DM) appeals the district court’s confirmation of an arbitration award in favor of Petrofac, Incorporated. Because DM fails to show any reversible error, we AFFIRM.

I.

DM operates the Strategic Petroleum Reserve for the Department of Energy. DM subcontracted with Petrofac to design and install a transportable degas plant to service the reserve. On July 30, 2003, DM and Petrofac agreed to resolve any claim under the subcontract through binding arbitration. The contract stated:

Petrofac and DM agree to enter into binding arbitration for any Request for Equitable Adjustment or claim submitted against the referenced subcontract, in lieu of litigation, in the event that a mutually agreeable resolution cannot be bilaterally achieved between DM and Petrofac through negotiations.

In May 2004, Petrofac sent DM a multivolume Request for Equitable Adjustment (REA). There, Petrofac asserted that DM disrupted Petrofac’s ability to perform its work and sought damages for differing site conditions, delays, disruption costs, lost productivity, and acceleration costs.

On December 6, 2005, Petrofac agreed to release DM from all but a few specifically preserved claims. Among these preserved claims, the release included Petrofac’s REA “as may be amended or supplemented.” 1

By July 2006, the parties had failed to resolve the REA dispute via negotiation. *674 Pursuant to the 2003 arbitration agreement, DM and Petrofac entered into an “Agreement for Arbitration and for Location and Methodology of Arbitration.” There, the parties agreed that “[t]hey shall submit to binding arbitration the [REA] and all claims and disputes between them arising out of or relating to the Subcontract.” In addition, the parties agreed that the arbitration would be conducted by the American Arbitration Association under its Construction Industry Arbitration Rules (AAA Rules).

Petrofac subsequently filed its demand for arbitration. In June 2008, Petrofac provided DM the report of its damages expert, Frank Adams. The Adams report calculated Petrofac’s damages using a different methodology and reached a different amount than the original REA. The arbitration began in March 2009. After five days of hearings, however, the arbitration panel recessed for seven months. When the arbitration reconvened, DM objected to the arbitration panel hearing any claims stemming from the different damages methodology used in the Adams report, claiming that it effectively created a new constructive change claim outside the parties’ agreement to arbitrate.

The arbitration panel dismissed DM’s objection because “the arbitration agreement is clear and encompasses all of the issues between the parties arising out of this contract. It is also clear that DM waived any objection it had to the arbitration of a constructive change claim.” The arbitration panel subsequently awarded Petrofac damages for the “contract balance, damages for a constructive change to the contract, an award for the benefit of Womack, and interest from August 24, 2006 to July 26, 2010” to be paid “within thirty days of the Award.”

The district court confirmed the award. The district court rejected DM’s argument that the REA and the Adams report represented different claims. Therefore, the district court ruled that the arbitration panel did not exceed its authority by awarding damages as presented in the Adams report. The court also determined that the award was not procured through fraud or undue means under 9 U.S.C. § 10(a)(1). Finally, the district court ordered prejudgment interest after August 26, 2010, ruling that prejudgment interest recommenced after DM failed to pay the award within the thirty-day period.

II.

This court reviews “a district court’s confirmation of an award de novo, but the review of the underlying award is exceedingly deferential.” Apache Bohai Corp. LDC v. Texaco China BV, 480 F.3d 397, 401 (5th Cir.2007) (internal quotation marks omitted).

A.

On appeal, DM argues that the arbitration panel exceeded its powers by issuing an award on a claim not covered by the parties’ arbitration agreement. 9 U.S.C. § 10(a)(4) (allowing a district court to vacate an award “where the arbitrators exceeded their powers”). Specifically, DM contends that the calculations in the expert report were extinguished by the 2005 release and therefore fall outside the parties’ agreement to arbitrate. Petrofac responds that the parties contracted for the arbitration panel (and not the courts) to decide this question of arbitrability, and even if the arbitration panel did not have the power to decide arbitrability, the district court properly determined that the claims at issue were within the arbitration agreement.

We first consider if the arbitration panel properly determined the initial *675 question of arbitrability, i.e. whether the claim is within the parties’ agreement to arbitrate. “Just as the arbitrability of the merits of a dispute depends upon whether the parties agreed to arbitrate that dispute, so the question ‘who has the primary power to decide arbitrability’ turns upon what the parties agreed about that matter.” First Options of Chi., Inc. v. Kaplan, 514 U.S. 938, 943, 115 S.Ct. 1920, 131 L.Ed.2d 985 (1995) (internal citations omitted). We will not assume that the parties agreed to arbitrate arbitrability “[ujnless the parties clearly and unmistakably provide otherwise.” AT & T Techs., Inc. v. Commc’ns Workers of Am., 475 U.S. 643, 649, 106 S.Ct. 1415, 89 L.Ed.2d 648 (1986). Accordingly, we must decide if DM and Petrofac “clearly and unmistakably” provided for the arbitration panel to decide arbitrability.

Here, the parties expressly incorporated into their arbitration agreement the AAA Rules. These rules state that “[t]he arbitrator shall have the power to rule on his or her own jurisdiction, including any objections with respect to the existence, scope or validity of the arbitration agreement.” We agree with most of our sister circuits that the express adoption of these rules presents clear and unmistakable evidence that the parties agreed to arbitrate arbitrability. See Fallo v. High-Tech Inst., 559 F.3d 874, 878 (8th Cir.2009) (“[WJe conclude that the arbitration provision’s incorporation of the AAA Rules ... constitutes a clear and unmistakable expression of the parties’ intent to leave the question of arbitrability to an arbitrator.”); Qualcomm Inc. v. Nokia Corp., 466 F.3d 1366, 1372-73 (Fed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McKoy v. ACN Opportunity, LLC
W.D. North Carolina, 2022
KETTLE BLACK OF MA, LLC v. COMMONWEALTH PAIN MANAGEMENT CONNECTION, LLC.
101 Mass. App. Ct. 109 (Massachusetts Appeals Court, 2022)
Fort, Trustee v. Daileader
D. South Carolina, 2022

Cite This Page — Counsel Stack

Bluebook (online)
687 F.3d 671, 2012 WL 2892401, 2012 U.S. App. LEXIS 14610, Counsel Stack Legal Research, https://law.counselstack.com/opinion/petrofac-inc-v-dynmcdermott-petroleum-operations-co-ca5-2012.