BNSF Railway v. Level 3 Communications

2026 Tex. Bus. 8
CourtTexas Business Court
DecidedFebruary 24, 2026
Docket25-BC01A-0025
StatusPublished

This text of 2026 Tex. Bus. 8 (BNSF Railway v. Level 3 Communications) is published on Counsel Stack Legal Research, covering Texas Business Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BNSF Railway v. Level 3 Communications, 2026 Tex. Bus. 8 (Tex. Super. Ct. 2026).

Opinion

FILED IN BUSINESS COURT OF TEXAS BEVERLY CRUMLEY, CLERK ENTERED 2/24/2026 2026 Tex. Bus. 8

The Business Court of Texas, First Division

BNSF RAILWAY COMPANY, § Plaintiff, § v. § Cause No. 25-BC01A-0025 LEVEL 3 COMMUNICATIONS, § LLC, § Defendant. § ═══════════════════════════════════════ Syllabus 1 ═══════════════════════════════════════ Granting a motion to confirm an arbitration award and denying a motion

to vacate the same award, the Court holds: the parties’ contract and applicable

law gave the arbitration panel authority to decide both substantive and

procedural arbitrability questions. Judgment is entered confirming the award.

1 This syllabus is provided for the convenience of the reader; it is not part of the Court’s opinion and should not be cited or relied upon as legal authority. 2026 Tex. Bus. 8

BNSF RAILWAY COMPANY, § Plaintiff, § v. § Cause No. 25-BC01A-0025 LEVEL 3 COMMUNICATIONS, § LLC, § Defendant. § ═══════════════════════════════════════ Opinion and Order Entering Final Judgment ═══════════════════════════════════════ I. Case Summary

¶1 On June 15, 1998, BNSF Railway Company (“BNSF”) and Level

3 Communications, LLC (“Level 3”) executed a Master Right-of-Way

Agreement (“the MROW” or “the Agreement”) by which BNSF would allow

Level 3 to infringe upon BNSF’s right-of-way in order to construct and install

fiber optic facilities along BNSF railroad segments in the United States in

exchange for cash and other consideration. See Arbitration Demand (“Arb.

Dem.”) ¶ 11, Tr. Ex. 1B at p. 4. The initial term of the Agreement was twenty- five years. See Arb. Dem. ¶ 17, Tr. Ex. 1B at p. 6. The Agreement was thus

anticipated to expire on June 14, 2023. See Arb. Dem. ¶ 19, Tr. Ex. 1B at p. 6.

¶2 BNSF gave Level 3 the right to extend the Agreement for two

renewal periods. See MROW § 17.a, Tr. Ex. 1B at pp. 547-48. If Level 3 elected

to extend the MROW, the MROW required the parties to negotiate a then-

current rate. See MROW § 17.a, Tr. Ex. 1B at p. 548. In the event the parties

failed to agree on a renewal rate during a 30-day negotiation period, Section

17 of the MROW purported to lay out a procedure (the appraisal process) by

which the parties were to arrive at a mutually agreeable renewal rate. See

MROW § 17, Tr. Ex. 1B at pp. 547-49.

¶3 On December 9, 2022, Level 3 notified BNSF of its intent to

renew the MROW, and the parties commenced the 30-day negotiation period.

See Pet. ¶ 21; Arb. Dem. ¶ 21, Tr. Ex. 1B at p. 7. The parties did not reach an

agreement on the then-current renewal rate, and the negotiation period was

extended several times. See Pet. ¶ 23; Arb. Dem. ¶¶ 26-27, 34, Tr. Ex. 1B at

pp. 8, 10. The extended negotiation period ended on October 31, 2023. See Pet.

¶ 39. Despite the extensions, the parties did not reach an agreement on the

then-current renewal rate. See id. ¶ 23.

Page 2 ¶4 The MROW contained several provisions concerning resolution of

disputes between the parties. See MROW §§ 17-18, Tr. Ex. 1B at pp. 547-50.

Section 17 set out an appraisal process to reach a renewal rate. See MROW §

17, Tr. Ex. 1B at pp. 547-49. Separately, the MROW contained a formal

dispute resolution procedure in Section 18.b, and an arbitration clause in 18.c.

See MROW § 18, Tr. Ex. 1B at pp. 549-50. Per its terms, the parties agreed “to

submit any disputes arising out of [the MROW] and not settled pursuant to

Section 18.b. to binding arbitration.” MROW § 18.c, Tr. Ex. 1B at p. 549. The

arbitration clause did not expressly reference renewal rate disputes or the

appraisal process, either inclusively or exclusively.

¶5 On October 31, 2023, Level 3 filed a demand for arbitration with

the American Arbitration Association (“AAA”). See Pet. ¶ 39; see generally

Arb. Dem., Tr. Ex. 1B at pp. 1-21. The arbitration demand centered on the

renewal rate dispute, specifically the methodology to be used to calculate the

rate. See Arb. Dem. ¶ 67, Tr. Ex. 1B at p. 18. Level 3 claimed that “by failing

to act in good faith and approve a rate consistent with the terms in the

[MROW], BNSF waived its rights under the [MROW] including the right to

enforce the appraisal process set forth in Section 17.a. . . ..” Arb. Dem. ¶ 73,

Tr. Ex. 1B at p. 19.

Page 3 ¶6 BNSF filed a Motion to Dismiss Claimant’s Demand for

Arbitration and Request for Relief, arguing that “under well-established Texas

Law, an agreement to negotiate in good faith in the future is unenforceable,

even if the agreement calls for a ‘good faith effort’ in the negotiations.” Mtn.

to Dismiss at p. 2, Tr. Ex. 1B at p. 135. BNSF thus asked the arbitration panel

(“the Panel”) to dismiss the arbitration demand and to allow the negotiations

to proceed to the appraisal process. See Mtn. to Dismiss at p. 5, Tr. Ex. 1B at

p. 138.

¶7 Before the motion was adjudicated, Level 3 filed a First Amended

Statement of Claims and Request for Relief. See generally 1st Am. St., Tr. Ex.

1B at pp. 200-27. In it, Level 3 argued, inter alia, that the parties’ agreement

to the appraisal process was premised on the parties’ mutual obligation to act

in good faith. See 1st Am. St. ¶ 62, Tr. Ex. 1B at p. 218. Because BNSF had

failed to act in good faith, Level 3 argued, BNSF had waived its right to enforce

the appraisal process. See 1st Am. St. ¶ 65(i), Tr. Ex. 1B at p. 220.

¶8 On March 12, 2024, BNSF filed a second motion to dismiss. See

generally Mtn. to Dismiss II, Tr. Ex. 1B at pp. 324-39. BNSF again asked the

Panel to dismiss the arbitration demand and to allow the parties to proceed to

appraisal. See Mtn. to Dismiss II at p. 12, Tr. Ex. 1B at p. 335. Level 3

Page 4 demurred, challenging every argument raised by BNSF in its motion. See

generally Mtn. to Dismiss II Resp. at pp. 5-29, Tr. Ex. 1B at pp. 380-404. On

April 5, 2024, the Panel denied BNSF’s motion to dismiss, concluding that

“the arbitration should proceed to a hearing on the merits of Level 3’s

complaint.” Order on Mtn. to Dismiss II at p. 2, Tr. Ex. 1B at p. 429.

¶9 On May 1, 2024, Level 3 filed an Expedited Motion to Stay

Appraisal Process and Request for Interim Award, noting BNSF’s “refus[al] to

agree to postpone the appraisal process” despite the Panel’s denial of BNSF’s

motion to dismiss. Mtn. to Stay at p. 2, Tr. Ex. 1B at p. 439. In its response,

BNSF argued that “the appraisal process must come before any other

adjudication related to the Agreement.” Mtn. to Stay Resp. at p. 2, Tr. Ex. 1B

at p. 467 (emphasis in original). On June 3, 2024, the Panel stayed the

appraisal process. See Order on Mtn. to Stay at pp. 1-2, Tr. Ex. 1B at pp. 497-

98.

¶10 BNSF then filed a counterclaim. See generally Countercl., Tr. Ex.

1B at pp. 514-26. BNSF asked the Panel to, among other things, “order[] Level

3 to participate in the agreed upon Appraisal Process.” Countercl. at p. 10, Tr.

Ex. 1B at p. 523.

Page 5 ¶11 “Disputatious” discovery proceeded in due course. Final Award ¶

6, Tr. Ex. 1B at p. 3201. The final hearing on the merits began on March 10,

2025, in Dallas. See Final Award ¶ 8, Tr. Ex. 1B at p. 3201. At the conclusion

of Level 3’s case-in-chief, BNSF renewed its motion to dismiss as a motion for

directed verdict. See Final Award ¶ 9, Tr. Ex. 1B at p. 3202. The Panel carried

the motion to the conclusion of the hearing, and it was ultimately denied as

part of the Final Award. See Final Award ¶ 6, Tr. Ex. 1B at p. 3201.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2026 Tex. Bus. 8, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bnsf-railway-v-level-3-communications-texbizct-2026.