BNSF Railway v. Level 3 Communications

2026 Tex. Bus. 8
Texas Business Court·Decided February 24, 2026·No. 25-BC01A-0025·Published

Opinion

FILED IN

BUSINESS COURT OF TEXAS

BEVERLY CRUMLEY, CLERK

ENTERED

2/24/2026

2026 Tex. Bus. 8

The Business Court of Texas, First Division

BNSF RAILWAY COMPANY, § Plaintiff, § v. § Cause No. 25-BC01A-0025 LEVEL 3 COMMUNICATIONS, § LLC, § Defendant. § ═══════════════════════════════════════ Syllabus 1

═══════════════════════════════════════ Granting a motion to confirm an arbitration award and denying a motion

to vacate the same award, the Court holds: the parties’ contract and applicable law gave the arbitration panel authority to decide both substantive and procedural arbitrability questions. Judgment is entered confirming the award.

1 This syllabus is provided for the convenience of the reader; it is not part of the Court’s opinion and should not be cited or relied upon as legal authority.

2026 Tex. Bus. 8

The Business Court of Texas, First Division

BNSF RAILWAY COMPANY, § Plaintiff, § v. § Cause No. 25-BC01A-0025 LEVEL 3 COMMUNICATIONS, § LLC, § Defendant. § ═══════════════════════════════════════ Opinion and Order Entering Final Judgment ═══════════════════════════════════════ I. Case Summary

¶1 On June 15, 1998, BNSF Railway Company (“BNSF”) and Level 3 Communications, LLC (“Level 3”) executed a Master Right-of-Way Agreement (“the MROW” or “the Agreement”) by which BNSF would allow Level 3 to infringe upon BNSF’s right-of-way in order to construct and install fiber optic facilities along BNSF railroad segments in the United States in exchange for cash and other consideration. See Arbitration Demand (“Arb. Dem.”) ¶ 11, Tr. Ex. 1B at p. 4. The initial term of the Agreement was twenty-

five years. See Arb. Dem. ¶ 17, Tr. Ex. 1B at p. 6. The Agreement was thus anticipated to expire on June 14, 2023. See Arb. Dem. ¶ 19, Tr. Ex. 1B at p. 6.

¶2 BNSF gave Level 3 the right to extend the Agreement for two renewal periods. See MROW § 17.a, Tr. Ex. 1B at pp. 547-48. If Level 3 elected to extend the MROW, the MROW required the parties to negotiate a then- current rate. See MROW § 17.a, Tr. Ex. 1B at p. 548. In the event the parties failed to agree on a renewal rate during a 30-day negotiation period, Section 17 of the MROW purported to lay out a procedure (the appraisal process) by which the parties were to arrive at a mutually agreeable renewal rate. See MROW § 17, Tr. Ex. 1B at pp. 547-49.

¶3 On December 9, 2022, Level 3 notified BNSF of its intent to renew the MROW, and the parties commenced the 30-day negotiation period. See Pet. ¶ 21; Arb. Dem. ¶ 21, Tr. Ex. 1B at p. 7. The parties did not reach an agreement on the then-current renewal rate, and the negotiation period was extended several times. See Pet. ¶ 23; Arb. Dem. ¶¶ 26-27, 34, Tr. Ex. 1B at pp. 8, 10. The extended negotiation period ended on October 31, 2023. See Pet.

¶ 39. Despite the extensions, the parties did not reach an agreement on the then-current renewal rate. See id. ¶ 23.

¶4 The MROW contained several provisions concerning resolution of disputes between the parties. See MROW §§ 17-18, Tr. Ex. 1B at pp. 547-50. Section 17 set out an appraisal process to reach a renewal rate. See MROW § 17, Tr. Ex. 1B at pp. 547-49. Separately, the MROW contained a formal dispute resolution procedure in Section 18.b, and an arbitration clause in 18.c. See MROW § 18, Tr. Ex. 1B at pp. 549-50. Per its terms, the parties agreed “to submit any disputes arising out of [the MROW] and not settled pursuant to Section 18.b. to binding arbitration.” MROW § 18.c, Tr. Ex. 1B at p. 549. The arbitration clause did not expressly reference renewal rate disputes or the appraisal process, either inclusively or exclusively.

¶5 On October 31, 2023, Level 3 filed a demand for arbitration with the American Arbitration Association (“AAA”). See Pet. ¶ 39; see generally Arb. Dem., Tr. Ex. 1B at pp. 1-21. The arbitration demand centered on the renewal rate dispute, specifically the methodology to be used to calculate the rate. See Arb. Dem. ¶ 67, Tr. Ex. 1B at p. 18. Level 3 claimed that “by failing to act in good faith and approve a rate consistent with the terms in the [MROW], BNSF waived its rights under the [MROW] including the right to enforce the appraisal process set forth in Section 17.a. . . ..” Arb. Dem. ¶ 73, Tr. Ex. 1B at p. 19.

¶6 BNSF filed a Motion to Dismiss Claimant’s Demand for Arbitration and Request for Relief, arguing that “under well-established Texas Law, an agreement to negotiate in good faith in the future is unenforceable, even if the agreement calls for a ‘good faith effort’ in the negotiations.” Mtn. to Dismiss at p. 2, Tr. Ex. 1B at p. 135. BNSF thus asked the arbitration panel (“the Panel”) to dismiss the arbitration demand and to allow the negotiations to proceed to the appraisal process. See Mtn. to Dismiss at p. 5, Tr. Ex. 1B at p. 138.

¶7 Before the motion was adjudicated, Level 3 filed a First Amended Statement of Claims and Request for Relief. See generally 1st Am. St., Tr. Ex. 1B at pp. 200-27. In it, Level 3 argued, inter alia, that the parties’ agreement to the appraisal process was premised on the parties’ mutual obligation to act in good faith. See 1st Am. St. ¶ 62, Tr. Ex. 1B at p. 218. Because BNSF had failed to act in good faith, Level 3 argued, BNSF had waived its right to enforce the appraisal process. See 1st Am. St. ¶ 65(i), Tr. Ex. 1B at p. 220.

¶8 On March 12, 2024, BNSF filed a second motion to dismiss. See generally Mtn. to Dismiss II, Tr. Ex. 1B at pp. 324-39. BNSF again asked the Panel to dismiss the arbitration demand and to allow the parties to proceed to appraisal. See Mtn. to Dismiss II at p. 12, Tr. Ex. 1B at p. 335. Level 3

demurred, challenging every argument raised by BNSF in its motion. See generally Mtn. to Dismiss II Resp. at pp. 5-29, Tr. Ex. 1B at pp. 380-404. On April 5, 2024, the Panel denied BNSF’s motion to dismiss, concluding that “the arbitration should proceed to a hearing on the merits of Level 3’s complaint.” Order on Mtn. to Dismiss II at p. 2, Tr. Ex. 1B at p. 429.

¶9 On May 1, 2024, Level 3 filed an Expedited Motion to Stay Appraisal Process and Request for Interim Award, noting BNSF’s “refus[al] to agree to postpone the appraisal process” despite the Panel’s denial of BNSF’s motion to dismiss. Mtn. to Stay at p. 2, Tr. Ex. 1B at p. 439. In its response, BNSF argued that “the appraisal process must come before any other adjudication related to the Agreement.” Mtn. to Stay Resp. at p. 2, Tr. Ex. 1B at p. 467 (emphasis in original). On June 3, 2024, the Panel stayed the appraisal process. See Order on Mtn. to Stay at pp. 1-2, Tr. Ex. 1B at pp. 497- 98.

¶10 BNSF then filed a counterclaim. See generally Countercl., Tr. Ex.

1B at pp. 514-26. BNSF asked the Panel to, among other things, “order[] Level 3 to participate in the agreed upon Appraisal Process.” Countercl. at p. 10, Tr. Ex. 1B at p. 523.

¶11 “Disputatious” discovery proceeded in due course. Final Award ¶ 6, Tr. Ex. 1B at p. 3201. The final hearing on the merits began on March 10, 2025, in Dallas. See Final Award ¶ 8, Tr. Ex. 1B at p. 3201. At the conclusion of Level 3’s case-in-chief, BNSF renewed its motion to dismiss as a motion for directed verdict. See Final Award ¶ 9, Tr. Ex. 1B at p. 3202. The Panel carried the motion to the conclusion of the hearing, and it was ultimately denied as part of the Final Award. See Final Award ¶ 6, Tr. Ex. 1B at p. 3201.

¶12 In issuing an award in favor of Level 3, the Panel found that BNSF had failed to negotiate in good faith, rendering further negotiations and the appraisal process futile or impossible. See Final Award ¶ 42, Tr. Ex. 1B at p. 3215. Consequently, the Panel determined that BNSF had “waived any right to pursue” either further negotiations or the appraisal process. Id. It thus “order[ed] the parties to abide by” a rate negotiated between the parties’ lead negotiators earlier in the dispute resolution process. Final Award at p. 1, Tr. Ex. 1B at p. 3199.

Free access — add to your briefcase to read the full text and ask questions with AI

BNSF Railway v. Level 3 Communications, 2026 Tex. Bus. 8 (Tex. Super. Ct. 2026).

2026 Tex. Bus. 8 (BNSF Railway v. Level 3 Communications) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related