FILED IN BUSINESS COURT OF TEXAS BEVERLY CRUMLEY, CLERK ENTERED 2/24/2026 2026 Tex. Bus. 8
The Business Court of Texas, First Division
BNSF RAILWAY COMPANY, § Plaintiff, § v. § Cause No. 25-BC01A-0025 LEVEL 3 COMMUNICATIONS, § LLC, § Defendant. § ═══════════════════════════════════════ Syllabus 1 ═══════════════════════════════════════ Granting a motion to confirm an arbitration award and denying a motion
to vacate the same award, the Court holds: the parties’ contract and applicable
law gave the arbitration panel authority to decide both substantive and
procedural arbitrability questions. Judgment is entered confirming the award.
1 This syllabus is provided for the convenience of the reader; it is not part of the Court’s opinion and should not be cited or relied upon as legal authority. 2026 Tex. Bus. 8
BNSF RAILWAY COMPANY, § Plaintiff, § v. § Cause No. 25-BC01A-0025 LEVEL 3 COMMUNICATIONS, § LLC, § Defendant. § ═══════════════════════════════════════ Opinion and Order Entering Final Judgment ═══════════════════════════════════════ I. Case Summary
¶1 On June 15, 1998, BNSF Railway Company (“BNSF”) and Level
3 Communications, LLC (“Level 3”) executed a Master Right-of-Way
Agreement (“the MROW” or “the Agreement”) by which BNSF would allow
Level 3 to infringe upon BNSF’s right-of-way in order to construct and install
fiber optic facilities along BNSF railroad segments in the United States in
exchange for cash and other consideration. See Arbitration Demand (“Arb.
Dem.”) ¶ 11, Tr. Ex. 1B at p. 4. The initial term of the Agreement was twenty- five years. See Arb. Dem. ¶ 17, Tr. Ex. 1B at p. 6. The Agreement was thus
anticipated to expire on June 14, 2023. See Arb. Dem. ¶ 19, Tr. Ex. 1B at p. 6.
¶2 BNSF gave Level 3 the right to extend the Agreement for two
renewal periods. See MROW § 17.a, Tr. Ex. 1B at pp. 547-48. If Level 3 elected
to extend the MROW, the MROW required the parties to negotiate a then-
current rate. See MROW § 17.a, Tr. Ex. 1B at p. 548. In the event the parties
failed to agree on a renewal rate during a 30-day negotiation period, Section
17 of the MROW purported to lay out a procedure (the appraisal process) by
which the parties were to arrive at a mutually agreeable renewal rate. See
MROW § 17, Tr. Ex. 1B at pp. 547-49.
¶3 On December 9, 2022, Level 3 notified BNSF of its intent to
renew the MROW, and the parties commenced the 30-day negotiation period.
See Pet. ¶ 21; Arb. Dem. ¶ 21, Tr. Ex. 1B at p. 7. The parties did not reach an
agreement on the then-current renewal rate, and the negotiation period was
extended several times. See Pet. ¶ 23; Arb. Dem. ¶¶ 26-27, 34, Tr. Ex. 1B at
pp. 8, 10. The extended negotiation period ended on October 31, 2023. See Pet.
¶ 39. Despite the extensions, the parties did not reach an agreement on the
then-current renewal rate. See id. ¶ 23.
Page 2 ¶4 The MROW contained several provisions concerning resolution of
disputes between the parties. See MROW §§ 17-18, Tr. Ex. 1B at pp. 547-50.
Section 17 set out an appraisal process to reach a renewal rate. See MROW §
17, Tr. Ex. 1B at pp. 547-49. Separately, the MROW contained a formal
dispute resolution procedure in Section 18.b, and an arbitration clause in 18.c.
See MROW § 18, Tr. Ex. 1B at pp. 549-50. Per its terms, the parties agreed “to
submit any disputes arising out of [the MROW] and not settled pursuant to
Section 18.b. to binding arbitration.” MROW § 18.c, Tr. Ex. 1B at p. 549. The
arbitration clause did not expressly reference renewal rate disputes or the
appraisal process, either inclusively or exclusively.
¶5 On October 31, 2023, Level 3 filed a demand for arbitration with
the American Arbitration Association (“AAA”). See Pet. ¶ 39; see generally
Arb. Dem., Tr. Ex. 1B at pp. 1-21. The arbitration demand centered on the
renewal rate dispute, specifically the methodology to be used to calculate the
rate. See Arb. Dem. ¶ 67, Tr. Ex. 1B at p. 18. Level 3 claimed that “by failing
to act in good faith and approve a rate consistent with the terms in the
[MROW], BNSF waived its rights under the [MROW] including the right to
enforce the appraisal process set forth in Section 17.a. . . ..” Arb. Dem. ¶ 73,
Tr. Ex. 1B at p. 19.
Page 3 ¶6 BNSF filed a Motion to Dismiss Claimant’s Demand for
Arbitration and Request for Relief, arguing that “under well-established Texas
Law, an agreement to negotiate in good faith in the future is unenforceable,
even if the agreement calls for a ‘good faith effort’ in the negotiations.” Mtn.
to Dismiss at p. 2, Tr. Ex. 1B at p. 135. BNSF thus asked the arbitration panel
(“the Panel”) to dismiss the arbitration demand and to allow the negotiations
to proceed to the appraisal process. See Mtn. to Dismiss at p. 5, Tr. Ex. 1B at
p. 138.
¶7 Before the motion was adjudicated, Level 3 filed a First Amended
Statement of Claims and Request for Relief. See generally 1st Am. St., Tr. Ex.
1B at pp. 200-27. In it, Level 3 argued, inter alia, that the parties’ agreement
to the appraisal process was premised on the parties’ mutual obligation to act
in good faith. See 1st Am. St. ¶ 62, Tr. Ex. 1B at p. 218. Because BNSF had
failed to act in good faith, Level 3 argued, BNSF had waived its right to enforce
the appraisal process. See 1st Am. St. ¶ 65(i), Tr. Ex. 1B at p. 220.
¶8 On March 12, 2024, BNSF filed a second motion to dismiss. See
generally Mtn. to Dismiss II, Tr. Ex. 1B at pp. 324-39. BNSF again asked the
Panel to dismiss the arbitration demand and to allow the parties to proceed to
appraisal. See Mtn. to Dismiss II at p. 12, Tr. Ex. 1B at p. 335. Level 3
Page 4 demurred, challenging every argument raised by BNSF in its motion. See
generally Mtn. to Dismiss II Resp. at pp. 5-29, Tr. Ex. 1B at pp. 380-404. On
April 5, 2024, the Panel denied BNSF’s motion to dismiss, concluding that
“the arbitration should proceed to a hearing on the merits of Level 3’s
complaint.” Order on Mtn. to Dismiss II at p. 2, Tr. Ex. 1B at p. 429.
¶9 On May 1, 2024, Level 3 filed an Expedited Motion to Stay
Appraisal Process and Request for Interim Award, noting BNSF’s “refus[al] to
agree to postpone the appraisal process” despite the Panel’s denial of BNSF’s
motion to dismiss. Mtn. to Stay at p. 2, Tr. Ex. 1B at p. 439. In its response,
BNSF argued that “the appraisal process must come before any other
adjudication related to the Agreement.” Mtn. to Stay Resp. at p. 2, Tr. Ex. 1B
at p. 467 (emphasis in original). On June 3, 2024, the Panel stayed the
appraisal process. See Order on Mtn. to Stay at pp. 1-2, Tr. Ex. 1B at pp. 497-
98.
¶10 BNSF then filed a counterclaim. See generally Countercl., Tr. Ex.
1B at pp. 514-26. BNSF asked the Panel to, among other things, “order[] Level
3 to participate in the agreed upon Appraisal Process.” Countercl. at p. 10, Tr.
Ex. 1B at p. 523.
Page 5 ¶11 “Disputatious” discovery proceeded in due course. Final Award ¶
6, Tr. Ex. 1B at p. 3201. The final hearing on the merits began on March 10,
2025, in Dallas. See Final Award ¶ 8, Tr. Ex. 1B at p. 3201. At the conclusion
of Level 3’s case-in-chief, BNSF renewed its motion to dismiss as a motion for
directed verdict. See Final Award ¶ 9, Tr. Ex. 1B at p. 3202. The Panel carried
the motion to the conclusion of the hearing, and it was ultimately denied as
part of the Final Award. See Final Award ¶ 6, Tr. Ex. 1B at p. 3201.
Free access — add to your briefcase to read the full text and ask questions with AI
FILED IN BUSINESS COURT OF TEXAS BEVERLY CRUMLEY, CLERK ENTERED 2/24/2026 2026 Tex. Bus. 8
The Business Court of Texas, First Division
BNSF RAILWAY COMPANY, § Plaintiff, § v. § Cause No. 25-BC01A-0025 LEVEL 3 COMMUNICATIONS, § LLC, § Defendant. § ═══════════════════════════════════════ Syllabus 1 ═══════════════════════════════════════ Granting a motion to confirm an arbitration award and denying a motion
to vacate the same award, the Court holds: the parties’ contract and applicable
law gave the arbitration panel authority to decide both substantive and
procedural arbitrability questions. Judgment is entered confirming the award.
1 This syllabus is provided for the convenience of the reader; it is not part of the Court’s opinion and should not be cited or relied upon as legal authority. 2026 Tex. Bus. 8
BNSF RAILWAY COMPANY, § Plaintiff, § v. § Cause No. 25-BC01A-0025 LEVEL 3 COMMUNICATIONS, § LLC, § Defendant. § ═══════════════════════════════════════ Opinion and Order Entering Final Judgment ═══════════════════════════════════════ I. Case Summary
¶1 On June 15, 1998, BNSF Railway Company (“BNSF”) and Level
3 Communications, LLC (“Level 3”) executed a Master Right-of-Way
Agreement (“the MROW” or “the Agreement”) by which BNSF would allow
Level 3 to infringe upon BNSF’s right-of-way in order to construct and install
fiber optic facilities along BNSF railroad segments in the United States in
exchange for cash and other consideration. See Arbitration Demand (“Arb.
Dem.”) ¶ 11, Tr. Ex. 1B at p. 4. The initial term of the Agreement was twenty- five years. See Arb. Dem. ¶ 17, Tr. Ex. 1B at p. 6. The Agreement was thus
anticipated to expire on June 14, 2023. See Arb. Dem. ¶ 19, Tr. Ex. 1B at p. 6.
¶2 BNSF gave Level 3 the right to extend the Agreement for two
renewal periods. See MROW § 17.a, Tr. Ex. 1B at pp. 547-48. If Level 3 elected
to extend the MROW, the MROW required the parties to negotiate a then-
current rate. See MROW § 17.a, Tr. Ex. 1B at p. 548. In the event the parties
failed to agree on a renewal rate during a 30-day negotiation period, Section
17 of the MROW purported to lay out a procedure (the appraisal process) by
which the parties were to arrive at a mutually agreeable renewal rate. See
MROW § 17, Tr. Ex. 1B at pp. 547-49.
¶3 On December 9, 2022, Level 3 notified BNSF of its intent to
renew the MROW, and the parties commenced the 30-day negotiation period.
See Pet. ¶ 21; Arb. Dem. ¶ 21, Tr. Ex. 1B at p. 7. The parties did not reach an
agreement on the then-current renewal rate, and the negotiation period was
extended several times. See Pet. ¶ 23; Arb. Dem. ¶¶ 26-27, 34, Tr. Ex. 1B at
pp. 8, 10. The extended negotiation period ended on October 31, 2023. See Pet.
¶ 39. Despite the extensions, the parties did not reach an agreement on the
then-current renewal rate. See id. ¶ 23.
Page 2 ¶4 The MROW contained several provisions concerning resolution of
disputes between the parties. See MROW §§ 17-18, Tr. Ex. 1B at pp. 547-50.
Section 17 set out an appraisal process to reach a renewal rate. See MROW §
17, Tr. Ex. 1B at pp. 547-49. Separately, the MROW contained a formal
dispute resolution procedure in Section 18.b, and an arbitration clause in 18.c.
See MROW § 18, Tr. Ex. 1B at pp. 549-50. Per its terms, the parties agreed “to
submit any disputes arising out of [the MROW] and not settled pursuant to
Section 18.b. to binding arbitration.” MROW § 18.c, Tr. Ex. 1B at p. 549. The
arbitration clause did not expressly reference renewal rate disputes or the
appraisal process, either inclusively or exclusively.
¶5 On October 31, 2023, Level 3 filed a demand for arbitration with
the American Arbitration Association (“AAA”). See Pet. ¶ 39; see generally
Arb. Dem., Tr. Ex. 1B at pp. 1-21. The arbitration demand centered on the
renewal rate dispute, specifically the methodology to be used to calculate the
rate. See Arb. Dem. ¶ 67, Tr. Ex. 1B at p. 18. Level 3 claimed that “by failing
to act in good faith and approve a rate consistent with the terms in the
[MROW], BNSF waived its rights under the [MROW] including the right to
enforce the appraisal process set forth in Section 17.a. . . ..” Arb. Dem. ¶ 73,
Tr. Ex. 1B at p. 19.
Page 3 ¶6 BNSF filed a Motion to Dismiss Claimant’s Demand for
Arbitration and Request for Relief, arguing that “under well-established Texas
Law, an agreement to negotiate in good faith in the future is unenforceable,
even if the agreement calls for a ‘good faith effort’ in the negotiations.” Mtn.
to Dismiss at p. 2, Tr. Ex. 1B at p. 135. BNSF thus asked the arbitration panel
(“the Panel”) to dismiss the arbitration demand and to allow the negotiations
to proceed to the appraisal process. See Mtn. to Dismiss at p. 5, Tr. Ex. 1B at
p. 138.
¶7 Before the motion was adjudicated, Level 3 filed a First Amended
Statement of Claims and Request for Relief. See generally 1st Am. St., Tr. Ex.
1B at pp. 200-27. In it, Level 3 argued, inter alia, that the parties’ agreement
to the appraisal process was premised on the parties’ mutual obligation to act
in good faith. See 1st Am. St. ¶ 62, Tr. Ex. 1B at p. 218. Because BNSF had
failed to act in good faith, Level 3 argued, BNSF had waived its right to enforce
the appraisal process. See 1st Am. St. ¶ 65(i), Tr. Ex. 1B at p. 220.
¶8 On March 12, 2024, BNSF filed a second motion to dismiss. See
generally Mtn. to Dismiss II, Tr. Ex. 1B at pp. 324-39. BNSF again asked the
Panel to dismiss the arbitration demand and to allow the parties to proceed to
appraisal. See Mtn. to Dismiss II at p. 12, Tr. Ex. 1B at p. 335. Level 3
Page 4 demurred, challenging every argument raised by BNSF in its motion. See
generally Mtn. to Dismiss II Resp. at pp. 5-29, Tr. Ex. 1B at pp. 380-404. On
April 5, 2024, the Panel denied BNSF’s motion to dismiss, concluding that
“the arbitration should proceed to a hearing on the merits of Level 3’s
complaint.” Order on Mtn. to Dismiss II at p. 2, Tr. Ex. 1B at p. 429.
¶9 On May 1, 2024, Level 3 filed an Expedited Motion to Stay
Appraisal Process and Request for Interim Award, noting BNSF’s “refus[al] to
agree to postpone the appraisal process” despite the Panel’s denial of BNSF’s
motion to dismiss. Mtn. to Stay at p. 2, Tr. Ex. 1B at p. 439. In its response,
BNSF argued that “the appraisal process must come before any other
adjudication related to the Agreement.” Mtn. to Stay Resp. at p. 2, Tr. Ex. 1B
at p. 467 (emphasis in original). On June 3, 2024, the Panel stayed the
appraisal process. See Order on Mtn. to Stay at pp. 1-2, Tr. Ex. 1B at pp. 497-
98.
¶10 BNSF then filed a counterclaim. See generally Countercl., Tr. Ex.
1B at pp. 514-26. BNSF asked the Panel to, among other things, “order[] Level
3 to participate in the agreed upon Appraisal Process.” Countercl. at p. 10, Tr.
Ex. 1B at p. 523.
Page 5 ¶11 “Disputatious” discovery proceeded in due course. Final Award ¶
6, Tr. Ex. 1B at p. 3201. The final hearing on the merits began on March 10,
2025, in Dallas. See Final Award ¶ 8, Tr. Ex. 1B at p. 3201. At the conclusion
of Level 3’s case-in-chief, BNSF renewed its motion to dismiss as a motion for
directed verdict. See Final Award ¶ 9, Tr. Ex. 1B at p. 3202. The Panel carried
the motion to the conclusion of the hearing, and it was ultimately denied as
part of the Final Award. See Final Award ¶ 6, Tr. Ex. 1B at p. 3201.
¶12 In issuing an award in favor of Level 3, the Panel found that BNSF
had failed to negotiate in good faith, rendering further negotiations and the
appraisal process futile or impossible. See Final Award ¶ 42, Tr. Ex. 1B at p.
3215. Consequently, the Panel determined that BNSF had “waived any right
to pursue” either further negotiations or the appraisal process. Id. It thus
“order[ed] the parties to abide by” a rate negotiated between the parties’ lead
negotiators earlier in the dispute resolution process. Final Award at p. 1, Tr.
Ex. 1B at p. 3199.
¶13 On June 20, 2025, BNSF filed an application to vacate the
arbitration award in this Court because—in BNSF’s view—the Panel exceeded
its authority when it replaced a contractually-mandated appraisal process with
arbitration. See Pet. at pp. 1-2. Level 3 counterclaimed with an application to
Page 6 confirm the arbitration award. See Countercl. at p. 1. The Court entered an
agreed scheduling order on September 19, 2025, which outlined briefing
deadlines for both parties. See Scheduling Order at p. 4. A bench trial was held
in this Court on January 12, 2026.
II. Applicable Law
¶14 The arbitration clause in the MROW does not specify whether the
Federal Arbitration Act (“FAA”) or the arbitration law of the state (here, the
Texas Arbitration Act (“TAA”)) applies. However, the MROW does contain a
Texas choice of law provision. See Pet. ¶ 53. The parties agree that the MROW
is governed by both the FAA and TAA “[b]ecause the agreement does not
specifically exclude the application of federal law.” Moody Nat’l Grapevine
MT, LP v. TIC Grapevine 2, LP, 651 S.W.3d 450, 455 (Tex. App.—Houston
[14th Dist.] 2022, pet. denied); see Pet. ¶ 53 (citing Moody, 651 S.W.3d at
455); Countercl. ¶ 43 (quoting same).
¶15 Under both the TAA and the FAA, a court must—on application
of a party—confirm an arbitration award “[u]nless grounds are offered for
vacating, modifying, or correcting an award.” TEX. CIV. PRAC. & REM. CODE §
171.087; see also 9 U.S.C. § 9. Section 171.088 of the TAA and Section 10 of
the FAA enumerate the grounds under which a court may vacate an arbitration
Page 7 award. See TEX. CIV. PRAC. & REM. CODE § 171.088; 9 U.S.C. § 10. Of
relevance to this case, those grounds include a showing that the arbitrators
exceeded their authority. See TEX. CIV. PRAC. & REM. CODE §
171.088(a)(3)(A); 9 U.S.C. § 10(a)(4).
¶16 “In determining whether an arbitrator has exceeded his authority,
the proper inquiry is not whether the arbitrator decided an issue correctly, but
rather, whether he had the authority to decide the issue at all.” Forest Oil Corp.
v. El Rucio Land & Cattle Co., Inc., 518 S.W.3d 422, 431 (Tex. 2017). Because
arbitration is the byproduct of the parties’ agreement, vacatur on the ground
that the arbitrators exceeded their authority requires a showing that the
arbitrators decided a matter that the agreement did not submit to their
judgment.
¶17 In examining the scope of the arbitrators’ authority in this case,
the key issue is arbitrability. The Texas Supreme Court (like the United States
Supreme Court) recognizes a distinction between questions of substantive
arbitrability and procedural arbitrability. See G.T. Leach Builders, LLC v.
Sapphire V.P., LP, 458 S.W.3d 502, 520 (Tex. 2015) (citing BG Grp., PLC v.
Republic of Arg., 572 U.S. 25, 33 (2014); Howsam v. Dean Witter Reynolds,
Inc., 537 U.S. 79, 81 (2002)). Whether a particular dispute is arbitrable—“a
Page 8 gateway dispute”—is a question of substantive arbitrability. Howsam, 537
U.S. at 84. Satisfaction (or not) of a condition precedent to arbitration, and
similar matters not at issue here, present questions of procedural arbitrability.
G.T. Leach Builders, 458 S.W.3d at 520. The outcome of the case at hand turns
not on what is arbitrable, but on who decides what is arbitrable.
III. Discussion
¶18 In its Original Petition and Application to Vacate Arbitration
Award, BNSF identified TAA Section 171.088(a)(3)(A) and 9 U.S.C. §
10(a)(4) as its bases for vacatur. See Pet. ¶ 54; see also TEX. CIV. PRAC. & REM.
CODE § 171.088(a)(3)(A); 9 U.S.C. § 10(a)(4). Specifically, BNSF argued that
the Panel exceeded its authority in two ways. See Pet. ¶¶ 72-74. First, BNSF
argues the Panel exceeded its authority “by ignoring [a] clear contractual
mandate and permitting Level 3 to replace the required appraisal process for
the renewal-rate determination with arbitration. 1 BNSF Supp. at p. 27
(emphases in original); see Pet. ¶ 68. Second, BNSF argues (in the alternative)
that the Panel exceeded its authority by allowing arbitration prior to the
1 In a variation of this argument, BNSF also argued that appraisal was “at a minimum” a condition precedent to arbitration, and as such, should be completed prior to arbitration. Pet. ¶ 62; see BNSF Supp. at p. 25. Page 9 parties’ completion of a condition precedent to arbitration, including the
formal settlement process described in Section 18.b of the MROW. See BNSF
Supp. at p. 28; Pet. ¶ 73.
¶19 The key issue in this case is arbitrability: did the Panel have the
authority to determine whether the renewal rate dispute was subject to
arbitration, and thereafter, to enter an award resolving that dispute? For the
reasons that follow, the Court finds that it did.
¶20 BNSF’s primary argument—that the Panel exceeded its authority
by adjudicating the renewal rate dispute despite contractual provisions
requiring resolution of that issue by other means—raises a question of
substantive arbitrability. In the absence of contractual provisions to the
contrary, questions of substantive arbitrability are typically decided by the
court. See G.T. Leach Builders, 458 S.W.3d at 520. Here, however, the parties
agreed—in the MROW’s arbitration clause—that “[a]ny arbitration under this
Agreement shall be conducted in accordance with the Commercial Rules of the
American Arbitration Association.” MROW § 18.c, Tr. Ex. 1B at p. 549.
¶21 Rule 7 of the AAA Commercial Rules grants to the arbitrator the
“power to rule on his or her own jurisdiction, including any objections with
respect to the existence, scope, or validity of the arbitration agreement or to
Page 10 the arbitrability of any claim or counterclaim without any need to refer such
matters first to a court.” AAA Comm. R. 7. “[A]s a general rule, an agreement
to arbitrate in accordance with the AAA or similar rules constitutes a clear and
unmistakable agreement that the arbitrator must decide whether the parties’
disputes must be resolved through arbitration.” TotalEnergies E&P USA, Inc.
v. MP Gulf of Mex., LLC, 667 S.W.3d 694, 708 (Tex. 2023); see Petrofac, Inc.
v. DynMcDermott Petroleum Operations Co., 687 F.3d 671, 675 (5th Cir.
2012) (“[T]he express adoption of [the AAA rules] presents clear and
unmistakable evidence that the parties agreed to arbitrate arbitrability.”).
¶22 The parties’ agreement to arbitrate “in accordance with” the AAA
Commercial Rules (see MROW § 18.e, Tr. Ex. 1B at p. 549) bound the parties
to those rules, absent conflict between the arbitration agreement and the rules.
See TotalEnergies, 667 S.W.3d at 709. And once “the parties have
contractually agreed to delegate arbitrability issues to the arbitrator, courts
must enforce that agreement.” Id. at 702. Accordingly, the parties’ adoption
of the AAA Commercial Rules removed questions of substantive arbitrability
from the hands of the court and placed it squarely in the hands of the
arbitrators.
Page 11 ¶23 Because substantive arbitrability was contractually entrusted to
the arbitrators, the Court cannot hold, as BNSF urges, that the arbitrators
exceeded their authority in determining that the renewal rate dispute was
arbitrable or in rendering an award resolving that dispute. On this basis, the
Court rejects BNSF’s motion to vacate the award. In so holding, the Court
does not reach Level 3’s claims that “BNSF did not raise a timely objection to
arbitrability.” Level 3 Opening Br. at p. 25.
¶24 BNSF’s alternative argument—that the Panel exceeded its
authority by allowing arbitration prior to the completion of a condition
precedent—raises a question of procedural arbitrability. In this regard, Texas
law is clear: the arbitrators—not the court—have the authority to determine
procedural arbitrability. See G.T. Leach Builders, 458 S.W.3d at 520. To the
extent BNSF argues that Section 17’s appraisal process and Section 18.b’s
formal settlement process were conditions precedent to arbitration, the
enforceability or satisfaction of such conditions were matters for the Panel to
decide. Nothing in the parties’ agreement operates to shift such questions into
the court’s hands.
¶25 In sum, an arbitration panel only exceeds its power when it
“exceeds [its] contractual authority.” Clendening v. Blucora, Inc., No. 05-22-
Page 12 01190-CV, 2024 WL 980359, at *2 (Tex. App.—Dallas Mar. 7, 2024, no pet.)
(mem. op.). Here, the Panel had authority to decide both substantive and
procedural arbitrability issues by virtue of the contract language and
applicable law. Thus, the Panel—per the terms of the MROW—had the power
to decide whether the renewal rate dispute was subject to arbitration, whether
any condition precedent to arbitration was enforceable or satisfied, and
ultimately, how to resolve the renewal rate dispute.
¶26 “[J]udicial review of an arbitration award is extraordinarily
narrow” and “focuses on the integrity of the process, not the propriety of the
result.” Forest Oil Corp. v. El Rucio Land & Cattle Co., Inc., 446 S.W.3d 58,
75 (Tex. App.—Houston [1st Dist.] 2014), aff’d, 518 S.W.3d at 432. “Review
of an arbitration award is so limited that even a mistake of fact or law by the
arbitrator is not a proper ground for vacating an award.” Id.; see also Ancor
Holdings, LLC v. Peterson, Goldman & Villani, Inc., 294 S.W.3d 818, 826 (Tex.
App.—Dallas 2009, no pet.). BNSF urges the Court to hold that the renewal
rate dispute should not have been arbitrated. But under the parties’ contract
and applicable law, the Panel—and not this Court—was entrusted to make
that determination. Accordingly, BNSF’s arguments for vacatur must be
rejected and the Court must confirm the arbitration award.
Page 13 ¶27 Finally, insofar as Level 3 has pleaded for recovery of fees and
costs (see Level3 Opening Br. at p. 40), the Court notes that no evidence of
fees or costs was presented at trial. As the party bearing the burden of proof,
it was incumbent upon Level 3 to present such evidence at the time of trial.
See Yowell v. Granite Operating Co., 620 S.W.3d 335, 354 (Tex. 2020). In the
absence of the same, Level 3’s claim for fees and costs must be denied
regardless of the merits of the parties’ arguments concerning recoverability.
IV. Conclusion and Final Judgment
¶28 IT IS THEREFORE ORDERED that BNSF’s Application to
Vacate Arbitration Award is DENIED and Level 3’s Counter-Application for
Confirmation of Arbitration Award is GRANTED. Level 3’s request for
additional attorneys’ fees is DENIED. Judgment is RENDERED that the
Final Award entered by the Panel on June 2, 2025, is CONFIRMED. All relief
requested and not granted herein is DENIED.
_______________________ ANDREA K. BOURESSA Judge of the Texas Business Court, First Division
SIGNED ON: February 24, 2026. Page 14 Automated Certificate of eService This automated certificate of service was created by the efiling system. The filer served this document via email generated by the efiling system on the date and to the persons listed below. The rules governing certificates of service have not changed. Filers must still provide a certificate of service that complies with all applicable rules.
Envelope ID: 111640575 Filing Code Description: Proposed Order Filing Description: Opinion and Order Entering Final Judgment Status as of 2/24/2026 12:04 PM CST
Case Contacts
Name BarNumber Email TimestampSubmitted Status
Eric Nichols eric.nichols@butlersnow.com 2/24/2026 11:32:18 AM SENT
Amanda Taylor amanda.taylor@butlersnow.com 2/24/2026 11:32:18 AM SENT
TJP Service tillotsonjohnsonpatton@gmail.com 2/24/2026 11:32:18 AM SENT
Stephani Michel smichel@tillotsonlaw.com 2/24/2026 11:32:18 AM SENT
Tyler Reed Tyler.Reed@butlersnow.com 2/24/2026 11:32:18 AM SENT
David Keltner david.keltner@kellyhart.com 2/24/2026 11:32:18 AM SENT
Stacy Blanchette stacy.blanchette@kellyhart.com 2/24/2026 11:32:18 AM SENT
Caitlyn Hubbard caitlyn.hubbard@kellyhart.com 2/24/2026 11:32:18 AM SENT
Jody Sanders jody.sanders@kellyhart.com 2/24/2026 11:32:18 AM SENT
Anne Johnson ajohnson@tillotsonlaw.com 2/24/2026 11:32:18 AM SENT
J.R. Johnson jr.johnson@butlersnow.com 2/24/2026 11:32:18 AM SENT
Chelsea Beisel CMBeisel@hollandhart.com 2/24/2026 11:32:18 AM SENT
Alejandra Calderon alejandra.calderon@butlersnow.com 2/24/2026 11:32:18 AM SENT
Devlin Browne dbrowne@tillotsonlaw.com 2/24/2026 11:32:18 AM SENT
Alejandra Calderon alejandra.calderon@butlersnow.com 2/24/2026 11:32:18 AM SENT
Melissa Reagan MKReagan@hollandhart.com 2/24/2026 11:32:18 AM SENT
Katherine Varholak KDVarholak@hollandhart.com 2/24/2026 11:32:18 AM SENT
Rosa Cortez rosa.cortez@txcourts.gov 2/24/2026 11:32:18 AM SENT