McInnis Electric Company v. Brasfield & Gorrie, LLC and James Mapp

CourtMississippi Supreme Court
DecidedOctober 19, 2023
Docket2021-CA-01115-SCT
StatusPublished

This text of McInnis Electric Company v. Brasfield & Gorrie, LLC and James Mapp (McInnis Electric Company v. Brasfield & Gorrie, LLC and James Mapp) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McInnis Electric Company v. Brasfield & Gorrie, LLC and James Mapp, (Mich. 2023).

Opinion

IN THE SUPREME COURT OF MISSISSIPPI

NO. 2021-CA-01115-SCT

McINNIS ELECTRIC COMPANY

v.

BRASFIELD & GORRIE, LLC, AND JAMES MAPP

DATE OF JUDGMENT: 09/13/2021 TRIAL JUDGE: HON. WINSTON L. KIDD TRIAL COURT ATTORNEYS: SHIRLEY PAYNE CYNTHIA ANN STEWART DENNIS L. HORN R. LANE DOSSETT RALPH B. GERMANY, JR. SIMON TURNER BAILEY COURT FROM WHICH APPEALED: HINDS COUNTY CIRCUIT COURT ATTORNEYS FOR APPELLANT: DENNIS L. HORN R. LANE DOSSETT SHIRLEY PAYNE LEIGH KATHRYN PAYNE HORN ATTORNEYS FOR APPELLEES RALPH B. GERMANY, JR. SIMON TURNER BAILEY RANKIN SUMNER FORTENBERRY NATURE OF THE CASE: CIVIL - CONTRACT DISPOSITION: AFFIRMED - 10/19/2023 MOTION FOR REHEARING FILED:

CONSOLIDATED WITH

NO. 2021-CA-01300-SCT

BRASFIELD & GORRIE, LLC, AND JAMES MAPP DATE OF JUDGMENT: 09/13/2021 TRIAL JUDGE: HON. WINSTON L. KIDD COURT FROM WHICH APPEALED: HINDS COUNTY CIRCUIT COURT ATTORNEYS FOR APPELLANT: DENNIS L. HORN SHIRLEY PAYNE R. LANE DOSSETT LEIGH KATHRYN PAYNE HORN ATTORNEYS FOR APPELLEE: RALPH B. GERMANY, JR. SIMON TURNER BAILEY RANKIN SUMMER FORTENBERRY NATURE OF THE CASE: CIVIL - CONTRACT DISPOSITION: AFFIRMED - 10/19/2023 MOTION FOR REHEARING FILED:

EN BANC.

COLEMAN, JUSTICE, FOR THE COURT:

¶1. The instant matter stems from disagreements and a broken contract between a

contractor and subcontractor allegedly brought on by the COVID-19 pandemic. They contest

whether arbitration is appropriate to settle their disputes. The trial court compelled

arbitration, and we affirm.

FACTS

¶2. Construction firm Brasfield & Gorrie, LLC, received the prime contract to expand the

University of Mississippi Medical Center Children’s Hospital in 2017. Electrical contractor

McInnis Electric Company secured the winning bid to install the electrical and low voltage

systems package for the project and subsequently signed a subcontract with Brasfield &

Gorrie. Terms of the subcontract incorporated the prime contract, which were related to the

same project by reference.

2 ¶3. The subcontract signed by both parties states, “THIS CONTRACT IS SUBJECT TO

ARBITRATION.” It also provides a specific provision regarding “CLAIMS AND

DISPUTES; ARBITRATION.” There, the parties stipulated that they “intend[ed] that all

claims of Subcontractor (McInnis) shall be resolved in accordance with the provisions of the

Contract Documents and this Subcontract . . . .” Later in the same article, the process for all

claims handled and resolved under a dispute resolution process with the owner, i.e., the

children’s hospital, is outlined. It further provides as follows:

any disputes between Contractor and Subcontractor not resolved under Paragraph 29.2, including any disputes in which Subcontractor has a claim against another subcontractor, shall be finally determined by binding arbitration in accordance with the current Construction Industry Rules of the American Arbitration Association by one or more arbitrators selected in accordance with said Rules. The parties acknowledge that this Subcontract evidences a transaction involving interstate commerce and that this agreement to arbitrate is enforceable under 9 U.S.C. §§ 1, et seq.[1]

¶4. Additionally, the terms of the contract provided that work was set to begin on the

project on February 15, 2018. However, McInnis, was directed not to report on site until

June 4, 2018, and, due to delays, was unable to begin until July 23, 2018. McInnis’s work

began with underground construction of a complex web of conduits, which were successfully

installed, with the exception of damage caused by the concrete contractor. As work

progressed, the schedule allegedly became delayed as a result of Brasfield & Gorrie’s failure

to coordinate the work of the various subcontractors. By August 1, 2019, scheduled

construction was six months behind. By fall 2019, nearly a thousand Requests for

1 9 U.S.C. §§ 1-16 is commonly referred to as the Federal Arbitration Act.

3 Information and Construction Products Regulation had been issued, revealing significant

issues with contractual documents and drawings.

¶5. McInnis avers that Brasfield & Gorrie’s failure to coordinate and facilitate the work

of the various subcontractors worsened as the project progressed, and Brasfield & Gorrie

experienced turnover in management. For example, the sheetrock contractor and the

plumbing contractor were required to complete the patient rooms of the upper floors in

specific sequence coordinated with all trades, but allegedly no attempt was made for

sequencing. Additionally, there were instances in which patient room electrical conduit

installations were delayed because windows and headwalls had not yet been installed by

other subcontractors. The failure of these and other predecessor activities allegedly delayed

McInnis’s work, which was not on the path toward completion, supposedly through no fault

of its own.

¶6. Construction issues were amplified when on March 11, 2020, Mississippi experienced

its first reported case of COVID-19. Five days later, the National Electrical Contractors

Association announced a national disease emergency response agreement with the National

Electrical Union. McInnis received such notice and informed Brasfield & Gorrie. On March

24, 2020, McInnis notified Brasfield & Gorrie of workplace safety concerns related to

COVID-19, but these concerns were supposedly ignored. Brasfield & Gorrie, realizing that

the predecessor activities had resulted in substantial delays, sought to make up for lost time

by “squeezing” McInnis. As the threat of the pandemic increased, Brasfield & Gorrie

4 declined to implement additional health and safety measures2 and instead increased

contribution to McInnis’s workforce through workforce contractor workers from an outside

workforce management group. The intermingling of new employees from a job site that had

been shut down due to COVID-19 created fear among some workers. As the project and its

timeline deteriorated, one of Brasfield & Gorrie’s supervisors, Defendant James Mapp,

allegedly destroyed McInnis’s materials on the job site, evidencing the growing animosity

between the companies.

¶7. On April 1, 2020, Governor Tate Reeves instituted a shelter in place order in response

to the ongoing pandemic, requiring certain nonessential businesses to close and

recommending social distancing to reduce the spread of the coronavirus in Mississippi.

Executive Order Number 1463 provided that building and construction should be halted

during the ongoing pandemic except for maintaining essential preexisting infrastructure. The

children’s hospital was not classified as an existing infrastructure as it was a nonoperational

work in progress and thus was not subject to the executive order’s exception to the

governmental shutdowns.

¶8. By May 8, 2020, McInnis had suffered an approximately 40 percent loss in its

workforce due to employees testing positive for COVID-19. Despite the decrease in the

available workforce, Brasfield & Gorrie demanded McInnis perform under its contractual

obligation. McInnis took measures to continue the work, including making $94,000 in

Free access — add to your briefcase to read the full text and ask questions with AI

Related

At&T Technologies, Inc. v. Communications Workers
475 U.S. 643 (Supreme Court, 1986)
First Options of Chicago, Inc. v. Kaplan
514 U.S. 938 (Supreme Court, 1995)
Howsam v. Dean Witter Reynolds, Inc.
537 U.S. 79 (Supreme Court, 2002)
MS Credit Center, Inc. v. Horton
926 So. 2d 167 (Mississippi Supreme Court, 2006)
East Ford, Inc. v. Taylor
826 So. 2d 709 (Mississippi Supreme Court, 2002)
Sanderson Farms, Inc. v. Gatlin
848 So. 2d 828 (Mississippi Supreme Court, 2003)
Covenant Health Rehab of Picayune v. Brown
949 So. 2d 732 (Mississippi Supreme Court, 2007)
Hendrick v. Green
618 So. 2d 76 (Mississippi Supreme Court, 1993)
BC Rogers Poultry, Inc. v. Wedgeworth
911 So. 2d 483 (Mississippi Supreme Court, 2005)
Rogers-Dabbs Chevrolet-Hummer v. Blakeney
950 So. 2d 170 (Mississippi Supreme Court, 2007)
Greater Canton Ford Mercury, Inc. v. Ables
948 So. 2d 417 (Mississippi Supreme Court, 2007)
James & Jackson, LLC. v. Willie Gary, LLC.
906 A.2d 76 (Supreme Court of Delaware, 2006)
Lacie Cyless Smith v. Express Check Advance of Mississippi, LLC
153 So. 3d 601 (Mississippi Supreme Court, 2014)
Jane Doe v. Hallmark Partners, LP
227 So. 3d 1052 (Mississippi Supreme Court, 2017)
Brian Ray Pedigo v. Rent-A-Center Inc.
237 So. 3d 1263 (Mississippi Supreme Court, 2017)
Rebecca Keyes v. Dollar General Corporation
240 So. 3d 373 (Mississippi Supreme Court, 2018)
Green Tree Servicing, L.L.C. v. Henry House
890 F.3d 493 (Fifth Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
McInnis Electric Company v. Brasfield & Gorrie, LLC and James Mapp, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcinnis-electric-company-v-brasfield-gorrie-llc-and-james-mapp-miss-2023.