Ghilotti Construction Co. v. City of Richmond

45 Cal. App. 4th 897, 53 Cal. Rptr. 2d 389, 96 Cal. Daily Op. Serv. 3639, 96 Daily Journal DAR 5863, 1996 Cal. App. LEXIS 497
CourtCalifornia Court of Appeal
DecidedMay 22, 1996
DocketA071235
StatusPublished
Cited by28 cases

This text of 45 Cal. App. 4th 897 (Ghilotti Construction Co. v. City of Richmond) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ghilotti Construction Co. v. City of Richmond, 45 Cal. App. 4th 897, 53 Cal. Rptr. 2d 389, 96 Cal. Daily Op. Serv. 3639, 96 Daily Journal DAR 5863, 1996 Cal. App. LEXIS 497 (Cal. Ct. App. 1996).

Opinion

Opinion

PARRILLI, J.

In this case we hold that a public entity may waive inconsequential deviations from contract specifications in a public contract bid. To be considered inconsequential, a deviation must neither give the bidder an unfair competitive advantage nor otherwise defeat the goals of insuring economy and preventing corruption in the public contracting process.

Appellant Ghilotti Construction Company (GCC), the second lowest bidder on a contract for a road construction project in respondent City of Richmond (the City), petitioned the trial court for a writ of mandate or prohibition to prevent the City from contracting with the low bidder on the project, real party in interest Ghilotti Brothers Construction, Inc. (GBCI). GCC contended GBCI’s bid deviated from contract specifications because it showed that GBCI would subcontract more than 50 percent of the work on the project. The trial court denied the petition. We affirm. The city council properly awarded the contract to GBCI, finding the irregularity in its bid insubstantial.

Background

The City issued an invitation for bids on a construction project on Cutting and Canal Boulevards (the Cutting/Canal Project) in May 1995. The invitation reserved “the right to reject any or all Bids or to waive any informalities in the bidding.” The city engineer’s estimate for the project was $2,577,383. On June 1, 1995, the City received bids from three contractors. GBCI bid $2,419,598; GCC bid $2,714,201; and RGW Construction, Inc., bid $2,774,765. On June 2, the City received a letter from GCC objecting to the award of the contract to GBCI on the ground that GBCI’s bid indicated it would subcontract more than 50 percent of the project.

The contract documents incorporated standard specifications issued by the California Department of Transportation (CalTrans). These specifications included the following requirement: “The Contractor shall perform with his own organization contract work amounting to not less than 50 percent of the *901 original total contract price, except that any designated ‘Specialty Items’ may be performed by subcontract and the amount of any such ‘Specialty Items’ so performed may be deducted from the original total contract price before computing the amount of work required to be performed by the Contractor with his own organization.” The City’s bid proposal did not designate any specialty items. CalTrans typically gives that designation to items such as landscaping, striping, and electrical and joint trench work. In a letter responding to GCC’s protest, GBCI argued that if such items were deducted from the original contract price, GBCI would have been performing 78.7 percent of the remaining work. However, GBCI’s bid showed it would be subcontracting 55.44 percent of the total contract price.

The City’s office of contract compliance issued a memorandum on June 13, 1995, analyzing the three bids for the Cutting/Canal Project. The memorandum noted both GBCI and GCC had exceeded the City’s goals for subcontracting to minority and local businesses, but GBCI’s bid appeared to violate the limit on subcontracting imposed by the CalTrans standard specifications. The memorandum also observed the City had waived or disregarded this requirement on previous projects, including a 1991 street project and another recent San Pablo Avenue project on which appellant GCC had performed less than 50 percent of the work itself. The memorandum concluded there was sufficient precedent to award the contract to GBCI, the lowest responsive bidder.

The city council met on June 26, 1995, to consider the contract for the Cutting/Canal Project. The office of contract compliance memorandum was presented, and oral presentations were made in the following order. Jim Ghilotti, vice-president of GCC, argued that GCC’s bid had been dramatically affected by the restriction on subcontracting. He claimed GCC could have made its bid $90,000 lower by using a subcontractor for storm drain work. He also contended GCC had not violated the subcontracting restriction on the San Pablo project identified in the office of contract compliance memorandum. Frank Ruona, vice-president of GBCI in charge of estimating and construction management, told the city council he had the bid documents from the San Pablo project; he asserted they showed that GCC had not complied with the 50 percent requirement at bid time but had reduced the dollar amounts allotted to various subcontractors by paying for materials itself instead of purchasing the materials through the subcontractors. Ruona noted GBCI had tried to use local and minority subcontractors to comply with the City’s priorities. Mario Ghilotti, vice-president and general manager of GBCI, mentioned previous projects on which GBCI had been low bidder but had not been awarded the contracts because it had failed to meet the *902 City’s requirements for using local and minority subcontractors. He claimed GCC was using “good sharp lawyers” to try to disqualify GBCI’s low bid on the Cutting/Canal Project when GBCI could have shown it would be performing 55 percent of the project by making minor alterations in its bid.

John Knox, counsel for GBCI, told the city council that if GBCI were allowed to adjust its figures by paying for subcontractors’ materials, as GCC had done on the San Pablo project, GBCI would meet the 50 percent requirement without raising its bid. Rick Norris, counsel for GCC, told the city council it was legally required to reject GBCI’s bid because it did not conform to specifications. Norris argued a deviation must be considered substantial unless it could not have affected the amount of the bid, and that GCC’s bid was higher by at least $90,000 because it had complied with the rules. A council member observed that the $90,000 difference was insufficient to make up the gap between the bids of GCC and GBCI. Norris responded that the $90,000 was the simplest example GCC was able to document, but that GCC believed its bid would have been lower than GBCI’s had it not been for the 50 percent requirement, and would be lower if the project were rebid without that requirement.

The city manager recommended the city council award the contract to GBCI. He cited the City’s past practice in dealing with the 50 percent requirement when awarding contracts, the insufficiency of GCC’s asserted $90,000 savings to displace GBCI as the lowest bidder, the necessity of awarding the contract by June 30 in order to receive state funding, and the fact that only GBCI’s bid had come in under the City’s estimate, so that if the contract were given to one of the other bidders more money would have to be budgeted for the project. The city manager suggested the city council waive the 50 percent requirement as “nonsubstantive and inconsequential.” The City Attorney stated “for further clarification” that the city council would be waiving any irregularity in GBCI’s bid on the ground it was not substantial. The city council unanimously voted to award the contract to GBCI.

On June 29, 1995, GCC filed its writ petition in the trial court, and at the same time sought a temporary restraining order to prevent the City from executing a contract with GBCI for the Cutting/Canal Project. On July 11, the trial court denied the application for a temporary restraining order, issued an alternative writ, and set a hearing on the issues raised by the writ petition. The parties submitted declarations and exhibits for the trial court’s review.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lunday-Thagard Co. v. City of Los Angeles CA2/3
California Court of Appeal, 2024
Int'l Bhd. of Teamsters v. City of Monterey Park
242 Cal. Rptr. 3d 231 (California Court of Appeals, 5th District, 2019)
Squire v. County of Los Angeles
California Court of Appeal, 2018
Squire v. Cnty. of L. A.
231 Cal. Rptr. 3d 217 (California Court of Appeals, 5th District, 2018)
DeSilva Gates Construction, LP v. Department of Transportation
242 Cal. App. 4th 1409 (California Court of Appeal, 2015)
Ramirez v. Marslek CA1/2
California Court of Appeal, 2014
Bay Cities Paving v. San Leandro
California Court of Appeal, 2014
Bay Cities Paving & Grading v. City of San Leandro CA1/2
223 Cal. App. 4th 1181 (California Court of Appeal, 2014)
EEL River Disposal & Resource Recovery Inc. v. County of Humboldt
221 Cal. App. 4th 209 (California Court of Appeal, 2013)
Marriage of Goldfarb and Yelton CA1/2
California Court of Appeal, 2013
People v. JTH Tax, Inc.
212 Cal. App. 4th 1219 (California Court of Appeal, 2013)
Michael Leslie Productions, Inc. v. City of Los Angeles
207 Cal. App. 4th 1011 (California Court of Appeal, 2012)
Great West Contractors, Inc. v. Irvine Unified School District
187 Cal. App. 4th 1425 (California Court of Appeal, 2010)
Schram Construction, Inc. v. Regents of University of California
187 Cal. App. 4th 1040 (California Court of Appeal, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
45 Cal. App. 4th 897, 53 Cal. Rptr. 2d 389, 96 Cal. Daily Op. Serv. 3639, 96 Daily Journal DAR 5863, 1996 Cal. App. LEXIS 497, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ghilotti-construction-co-v-city-of-richmond-calctapp-1996.