DeSilva Gates Construction, LP v. Department of Transportation

242 Cal. App. 4th 1409, 195 Cal. Rptr. 3d 891, 2015 Cal. App. LEXIS 1114
CourtCalifornia Court of Appeal
DecidedDecember 14, 2015
DocketC074521
StatusPublished
Cited by10 cases

This text of 242 Cal. App. 4th 1409 (DeSilva Gates Construction, LP v. Department of Transportation) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DeSilva Gates Construction, LP v. Department of Transportation, 242 Cal. App. 4th 1409, 195 Cal. Rptr. 3d 891, 2015 Cal. App. LEXIS 1114 (Cal. Ct. App. 2015).

Opinion

Opinion

HOCH, J.

The Department of Transportation (CalTrans) and Papich Construction Company, Inc. (Papich), appeal from the trial court’s issuance *1412 of a writ of mandate to vacate the award of a public works contract to Papich. The trial court granted the writ on grounds CalTrans erroneously rejected a bid by DeSilva Gates Construction, LP (DeSilva), as nonresponsive, and erred by awarding the contract to Papich despite Papich’s failure to comply with a material requirement of the information for bids. On appeal, CalTrans and Papich argue DeSilva’s bid was nonresponsive because DeSilva impermissibly changed its list of subcontractors. Appellants also argue CalTrans had discretion to waive Papich’s mistake in failing to acknowledge the addendum to the information for bids.

On our own motion, we requested that the parties address whether this case has become moot. Based on the parties’ representations, we conclude this case remains justiciable.

DeSilva has elected not to file a respondent’s brief. Nonetheless, we “examine the record on the basis of appellant’s brief and . . . reverse only if prejudicial error is found. (Baldwin v. Baldwin (1944) 67 Cal.App.2d 175 [153 P.2d 567]; Jarvis v. O’Brien (1957) 147 Cal.App.2d 758 [305 P.2d 961].)” (Walker v. Porter (1974) 44 Cal.App.3d 174, 177 [118 Cal.Rptr. 468].) In this case, we conclude the trial court did not err. DeSilva’s disclosure of a subcontractor performing work amounting to only one-tenth of 1 percent of the total value of the contract was not required by the Public Contract Code 1 or CalTrans’s information for bids. The additional information was accurate, albeit unnecessary, and did not render DeSilva’s bid nonresponsive. By contrast, CalTrans initially declared Papich’s bid to be nonresponsive and then waived Papich’s mistake and determined the bid to be responsive. We conclude CalTrans abused its discretion by awarding Papich the contract. Accordingly, we affirm the trial court’s issuance of the writ of mandate.

FACTUAL AND PROCEDURAL HISTORY

CalTrans’s Information for Bids

In My 2012, CalTrans issued an information for bids on a construction project estimated to cost $34 million to widen a section of Highway 99 in Tulare County. The invitation for bids contained a section regarding disclosure of subcontractors that instructed bidders as follows: “2-1.12C Subcontractor List [¶] In the Subcontractor List, list each contractor to perform work in an amount in excess of 1/2 of 1 percent of the total bid or $10,000, whichever is greater (. . . § 4100 et seq.) [¶] The Subcontractor List must show the name, address, and work portions to be performed by each *1413 subcontractor listed. Show work portion by bid item number, description, and percentage of each bid item subcontracted. [¶] On the Subcontractor List you may either submit each subcontracted bid item number and corresponding percentage with your bid or fax these numbers and percentages to (916) 227-6282 within 24 hours after bid opening. Failure to do so results in a nonresponsive bid.” (Italics added.)

On September 7, 2012, CalTrans issued an addendum to the information for bids. Specifically, the addendum indicated that (1) bids would be opened on September 14, 2012, instead of September 11, 2012, (2) project plan sheets 142, 143, 145, and 146 were revised, and (3) items 59, 60, and 77 in the bid book’s “Bid Item List” were revised as well. The addendum concluded by advising potential bidders to: “Submit bids for this work with the understanding and full consideration of this addendum. The revisions declared in this addendum are an essential part of the contract.”

The Submitted Bids

CalTrans received and opened nine bids on September 14, 2012. Security Paving Company, Inc. (Security), submitted the lowest bid for $30,584,331. DeSilva submitted the second-lowest bid by offering to perform the work for $31,677,677. DeSilva’s bid included the names and description of work by all subcontractors slated to perform work exceeding one-half of 1 percent of the bid amount. The same day, DeSilva faxed to CalTrans additional information within 24 hours of bid opening (24-hour subcontractor list). DeSilva’s 24-hour subcontractor list included All Steel Fence, a subcontractor not listed in DeSilva’s bid. All Steel Fence was listed as performing “fences, gates, railing” work — work that constituted all of bid item numbers 139 and 140 as well as 1 percent of bid item number 143. Cumulatively, All Steel Fence was estimated to perform $15,023 worth of work. Papich submitted the third-lowest bid, proposing to perform the work for $32,611,185. Papich’s bid did not acknowledge or accept the addendum to the information for bids.

CalTrans’s Assessment of the Bids

CalTrans determined Security’s bid to be nonresponsive for revision of its subcontractor list after a protest by DeSilva on September 25, 2012. On September 25, 2012, DeSilva became the apparent low bidder.

On September 26, 2012, CalTrans sent a letter to Papich noting the company “failed to acknowledge Addendum #1 dated September 7, 2012, . . . on the signature page ... of its bid proposal. [CalTrans] considers the addendum to be a material amendment to the contract and is unable to identify in Papich’s bid submittal that it considered and agreed to be bound to *1414 the terms of said addendum. [¶] A bidder’s failure to acknowledge a material amendment to the contract renders its bid nonresponsive. Unless Papich is able to provide documentary evidence that it establishes it considered and agreed to be bound by the requirements of Addendum #1 its bid may be rejected.”

In the same letter, CalTrans noted Papich listed subcontractors Truesdell Corporation and Viking Construction as each performing 100 percent of several of the same tasks, including removal of unsound concrete, preparing concreted bridge surface, rapid setting concrete patch, and five more tasks. In the letter, CalTrans cured the problem by stating that “[i]f Papich is awarded contract 06-360214, it must perform” these tasks “with its own forces” to comply with section 4106.

On September 27, 2012, Papich sent a response letter stating: “It is the intent of [Papich] to provide, as requested, evidentiary proof of receipt (Attachment I) and acknowledgement included with the bid book (Attachment 2) of Addendum #1 for the above mentioned contract. [Papich] also contends that the information provided by [CalTrans] in Addendum #1 was reviewed, understood and utilized in the preparation of our bid proposal for this contract. [Papich] also agrees to be bound by the requirements of Addendum #1.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Golden State Boring etc. v. Astaldi Construction
California Court of Appeal, 2025
Lunday-Thagard Co. v. City of Los Angeles CA2/3
California Court of Appeal, 2024
Int'l Bhd. of Teamsters v. City of Monterey Park
242 Cal. Rptr. 3d 231 (California Court of Appeals, 5th District, 2019)
SJJC Aviation Services v. City of San Jose
California Court of Appeal, 2017
Roy Allan Slurry Seal, Inc. v. Am. Asphalt S., Inc.
388 P.3d 800 (California Supreme Court, 2017)
Kieu v. Quinal CA4/3
California Court of Appeal, 2016

Cite This Page — Counsel Stack

Bluebook (online)
242 Cal. App. 4th 1409, 195 Cal. Rptr. 3d 891, 2015 Cal. App. LEXIS 1114, Counsel Stack Legal Research, https://law.counselstack.com/opinion/desilva-gates-construction-lp-v-department-of-transportation-calctapp-2015.