Golden State Boring etc. v. Astaldi Construction

CourtCalifornia Court of Appeal
DecidedApril 16, 2025
DocketG062891
StatusPublished

This text of Golden State Boring etc. v. Astaldi Construction (Golden State Boring etc. v. Astaldi Construction) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Golden State Boring etc. v. Astaldi Construction, (Cal. Ct. App. 2025).

Opinion

Filed 4/16/25

CERTIFIED FOR PUBLICATION

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FOURTH APPELLATE DISTRICT

DIVISION THREE

GOLDEN STATE BORING & PIPE JACKING, INC., G062891 Plaintiff and Appellant, (Super. Ct. No. 30-2021-01198252) v. OPINION ASTALDI CONSTRUCTION CORPORATION et al.,

Defendants and Respondents.

Appeal from a judgment of the Superior Court of Orange County, Kimberly A. Knill, Judge. Affirmed. Law Offices of Timothy P. Creyaufmiller and Timothy P. Creyaufmiller for Plaintiff and Appellant. Pierce Kavcioglu Espinosa & Cesar, Timothy L. Pierce, Tyler J. Cesar, and Aren Kavcioglu for Defendants and Respondents. * * * The Orange County Transportation Authority (OCTA) awarded a contract to defendant OC 405 Partners Joint Venture (OC 405) to complete improvements to Interstate 405 in a design-build transportation project. OC 405 subsequently awarded certain subcontracting work to plaintiff Golden State Boring & Pipe Jacking, Inc. (GSB) under Public Contract Code section 1 6826. The parties ultimately disagreed over the scope of the subcontract work and never executed a written subcontract. After OC 405 contracted with a different subcontractor, GSB initiated the underlying action seeking benefit of the bargain damages. GSB claimed, inter alia, that OC 405 did not comply with section 4107’s substitution procedures before substituting GSB with another subcontractor. The trial court granted summary judgment in favor of defendants OC 405, Astaldi Construction Corporation (Astaldi), and OHL USA, Inc. (OHL) (collectively defendants). Among other things, the court held GSB was not entitled to the protections of section 4107 because it did not meet the requirements of section 4100 et seq. On appeal, GSB contends it is entitled to all the protections of a subcontractor under section 4100 et seq. To justify its argument, GSB relies on the relationship between sections 6826 and 4107, OC 405’s prime contract, and Southern California Acoustics Co. v. C. V. Holder, Inc. (1969) 71 Cal.2d 719 (Southern California Acoustics). We conclude the trial court did not err in finding section 4107’s substitution procedures did not apply to OC 405’s substitution of GSB. We accordingly affirm the judgment.

1 All further statutory references are to the Public Contract Code.

2 FACTS I. STATUTORY BACKGROUND A. Section 4100 et seq. “The Subletting and Subcontracting Fair Practices Act, sections 4100 et seq. (the [Subcontracting Practices] Act), establishes a detailed mandatory framework for competitive bids on public works contracts.” (Golden State Boring & Pipe Jacking, Inc. v. Orange County Water Dist. (2006) 143 Cal.App.4th 718, 721.) The Subcontracting Practices Act requires the general (or prime) contractor to list in its bid each subcontractor who performs work “in an amount in excess of one-half of 1 percent of the prime contractor’s total bid . . . .” (§ 4104, subd. (a)(1).) Section 4107, which is central to this appeal, prohibits the prime contractor from substituting “a person as subcontractor in place of the subcontractor listed in the original bid” unless the awarding authority consents and a statutory ground for substitution exists. (§ 4107, subd. (a).) The statute also describes a process through which substitutions may be made. (§ 4104, subd. (a)(1).) The requirements of the Subcontracting Practices Act stem from the Legislature’s finding that “the practices of bid shopping and bid peddling in connection with the construction, alteration, and repair of public improvements often result in poor quality of material and workmanship to the detriment of the public, deprive the public of the full benefits of fair competition among prime contractors and subcontractors, and lead to insolvencies, loss of wages to employees, and other evils.” (§ 4101.) “Bid shopping” involves “the use of the low bid already received by the general contractor to pressure other subcontractors into submitting even lower bids.” (Southern California Acoustics, supra, 71 Cal.2d at p. 726, fn. 7.) “Bid

3 peddling” involves a subcontractor’s attempt “to undercut known bids already submitted to the general contractor in order to procure the job.” (Ibid.) B. Section 6826 While the Subcontracting Practices Act generally applies to all public construction projects, section 6826 applies to subcontracts involving transportation design-build projects. The statute provides: “The transportation entity . . . may identify specific types of subcontractors that must be included in the design-build entity statement of qualifications and proposal. All construction subcontractors that are identified in the proposal shall be afforded all the protections of Chapter 4 (commencing with Section 4100) of Part 1 of Division 2.” (§ 6826, subd. (a).) Before a design-build entity awards subcontracts “not listed in the request for proposals,” it must comply with specific statutory requirements. (Id., subd. (b).) Section 6826, subdivision (c), another statute central to this appeal, states: “Subcontractors awarded subcontracts under this chapter shall be afforded all the protections of Chapter 4 (commencing with Section 4100) of Part 1 of Division 2.” II. THE PROJECT AND THE PRIME CONTRACT OC 405 is a joint venture comprised of Astaldi and OHLA USA, Inc.2 for the purpose of completing certain improvements to Interstate 405 (the Project). In 2016, OC 405 submitted its bid for the Project to the OCTA. GSB was not listed as a subcontractor in the original bid. The OCTA awarded the contract to OC 405, and they entered into a contract for the Project in 2017 for a total price of $1,217,065,000 (the Prime Contract).

2 In its separate statement of undisputed facts, defendants identified a joint venture with OHLA USA, Inc., but the party in the trial court and on appeal is OHL.

4 Section 7.2.2 of the Prime Contract addresses OC 405’s procurement of new subcontracts not identified in its initial proposal to the OCTA—i.e., a subcontractor that was not a “listed subcontractor.” To procure any new subcontracts, OC 405 had to “use a competitive process that complies with the provisions of Public Contract Code section 6826 . . . .” Section 7.2.3 of the Prime Contract also stated: “Design-Builder shall not have the right to make any substitution of any Listed Subcontractor or Subcontractor selected pursuant to Section 7.2.2 except in accordance with the provisions of the Subletting and Subcontracting Fair Practices Act, Public Contract Code section 4100 et seq.” III. GSB’S SUBCONTRACT BID In response to a request for proposals from OC 405, GSB submitted a bid to perform a portion of the Project for $1,723,620 in 2020. GSB later received an e-mail from OC 405 congratulating GSB on being awarded the subcontracting work. The parties thereafter negotiated the terms of the subcontract but disagreed over the scope of the work and never entered into a written subcontract. As a result, OC 405 contracted with a different subcontractor. IV. GSB’S COMPLAINT In June 2022, GSB filed the operative first amended complaint against defendants. The complaint alleged section 6826 and section 7.2.3 of the Prime Contract “contained . . . protections from substitution for the work awarded to” GSB. According to the complaint, OC 405 could not have substituted GSB with another subcontractor unless the substitution was in accordance with section 4100 et seq., which was referenced by section 6826

5 and section 7.2.3 of the Prime Contract. The complaint alleged defendants violated the latter provisions by making an unlawful substitution and sought damages for GSB’s benefit of the bargain. V. DEFENDANTS’ MOTION FOR SUMMARY JUDGMENT In December 2022, defendants moved for summary judgment seeking judgment in their favor on the complaint.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Golden State Boring & Pipe Jacking, Inc. v. Orange County Water District
49 Cal. Rptr. 3d 447 (California Court of Appeal, 2006)
Aguilar v. Atlantic Richfield Co.
24 P.3d 493 (California Supreme Court, 2001)
Hughes v. Pair
209 P.3d 963 (California Supreme Court, 2009)
DeSilva Gates Construction, LP v. Department of Transportation
242 Cal. App. 4th 1409 (California Court of Appeal, 2015)
Southern California Acoustics Co. v. C. V. Holder, Inc.
456 P.2d 975 (California Supreme Court, 1969)
Shin v. Ahn
165 P.3d 581 (California Supreme Court, 2007)
JMS Air Conditioning & Appliance Serv., Inc. v. Santa Monica Cmty. Coll. Dist.
242 Cal. Rptr. 3d 197 (California Court of Appeals, 5th District, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Golden State Boring etc. v. Astaldi Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/golden-state-boring-etc-v-astaldi-construction-calctapp-2025.