Golden State Boring & Pipe Jacking, Inc. v. Orange County Water District

49 Cal. Rptr. 3d 447, 143 Cal. App. 4th 718, 2006 Cal. Daily Op. Serv. 9311, 2006 Daily Journal DAR 13261, 2006 Cal. App. LEXIS 1523
CourtCalifornia Court of Appeal
DecidedSeptember 28, 2006
DocketG035795
StatusPublished
Cited by3 cases

This text of 49 Cal. Rptr. 3d 447 (Golden State Boring & Pipe Jacking, Inc. v. Orange County Water District) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Golden State Boring & Pipe Jacking, Inc. v. Orange County Water District, 49 Cal. Rptr. 3d 447, 143 Cal. App. 4th 718, 2006 Cal. Daily Op. Serv. 9311, 2006 Daily Journal DAR 13261, 2006 Cal. App. LEXIS 1523 (Cal. Ct. App. 2006).

Opinion

*721 Opinion

IKOLA, J.

Colich Construction, LP (Colich), a general contractor, submitted a bid for a public works contract to construct Orange County Water District’s (OCWD) Groundwater Replenishment System Unit II Pipeline Project (the project). Colich’s bid listed Golden State Boring and Pipe Jacking, Inc. (GSB), as a subcontractor. After OCWD awarded the contract to Colich, GSB persistently refused to sign the subcontract requiring it to obtain a performance bond as GSB gratuitously had offered to do in its successful bid for the subcontract. The impasse led Colich to seek OCWD’s approval of its request to substitute GSB out of participation in the project. After an evidentiary hearing, OCWD authorized the substitution, finding under Public Contract Code section 4107, subdivision (a)(1), 1 that GSB’s unjustified intransigence constituted an “unwillingness to execute a written subcontract for the scope of work specified in its sub-bid.” GSB’s petition for writ in mandamus proceedings (Code Civ. Proc., § 1094.5) was denied by the superior court.

On appeal, GSB argues Colich had no right to insist on a performance bond because Colich failed to make a statutory request for bond under section 4108. We conclude the superior court did not err in rejecting GSB’s argument and finding the bond was a condition GSB imposed upon itself as part of the consideration for Colich’s acceptance of its bid for the subcontract.

FACTS

Statutory Background

The Subletting and Subcontracting Fair Practices Act, section 4100 et seq. (the Act), establishes a detailed mandatory framework for competitive bids on public works contracts. The Act requires general contractors to identify in their bids all subcontractors “who will perform work or labor or render service to the prime contractor” in excess of one-half of 1 percent of the total bid of the prime contract. (§ 4104, subd. (a)(1).) 2 The requirement emanates from the Legislature’s finding “that the practices of bid shopping and bid peddling in connection with the construction, alteration, and repair of public improvements often result in poor quality of material and workmanship to the detriment of the public, deprive the public of the full benefits of *722 fair competition among prime contractors and subcontractors, and lead to insolvencies, loss of wages to employees, and other evils.” 3 (§ 4101.)

“The Act thus binds a contractor to its listed subcontractors, even though the parties have not yet entered into a contractual relationship.” (E. F. Brady Co. v. M. H. Golden Co. (1997) 58 Cal.App.4th 182, 189 [67 Cal.Rptr.2d 886].) It confers a statutory right on the listed subcontractor to perform the specified work. (§ 4107; R.J. Land & Associates Construction Co. v. Kiewit-Shea (1999) 69 Cal.App.4th 416, 421 [81 Cal.Rptr.2d 615].) “Once a subcontractor has been designated, the prime contractor cannot substitute another subcontractor unless the awarding authority consents and one of certain situations exists.” (Valley Crest Landscape, Inc. v. City Council (1996) 41 Cal.App.4th 1432, 1438 [49 Cal.Rptr.2d 184].)

The circumstances justifying substitution are set forth in sections 4107 and 4107.5. As relevant here, grounds for substitution exist “[w]hen the subcontractor listed in the bid, after having had a reasonable opportunity to do so, fails or refuses to execute a written contract for the scope of work specified in the subcontractor’s bid . . . , when that written contract, based upon the general terms, conditions, plans, and specifications for the project involved or the terms of that subcontractor’s written bid, is presented to the subcontractor by the prime contractor.” (§ 4107, subd. (a)(1).)

When notified of the prime contractor’s request for substitution, the subcontractor may submit written objections to the awarding agency and obtain an administrative hearing. (§ 4107, subd. (a).) Thereafter, “a subcontractor that believes an awarding authority has violated the Act’s statutory mandate may be entitled to bring an administrative mandamus under Code of Civil Procedure section 1094.5.” (E. F. Brady Co. v. M. H. Golden Co., supra, 58 Cal.App.4th at p. 192, fin. 8.)

The Bid and the Parties’ Negotiations

In August 2003, OCWD issued a notice inviting bids for construction of a years-long, wide-ranging, multimillion dollar project designed to assist the district’s groundwater replenishment operations for recharging OCWD’s groundwater basin. Bids were due by 1:00 p.m. on October 21, 2003. Colich, the bidding prime contractor, neither advertised for subcontract bids (subbids) *723 nor issued any written invitations for bids. The parties agree Colich informally requested bids for subcontracts. On the final day for bidding on the prime contract, just a few minutes before the deadline, GSB faxed to Colich the low bid for subcontracting about $3 million of tunneling and grout work. The proposal stated, inter alia, “If bond is required, a fee of 2.5% of the contract price will be added.” Colich promptly submitted its $16 million prime bid, listing GSB as a subcontractor.

GSB’s unilateral offer to obtain bonding was to take center stage as the parties further negotiated the terms of the subcontract. For instance, when GSB twice faxed to Colich revised proposals inserting terms omitted from the initial subbid, it reiterated its offer to provide a bond if required, and with the second fax transmission, GSB further memorialized the proposal under a formal heading labeled “Bonds,” setting forth the matter in standardized format, as follows: “The cost of a bond premium is not included in the contract price. If desired by and paid by others, GSB will furnish a Payment and Performance bond at 2.5% of the contract value.” (Italics indicate filled-in blanks.) Thus, all of GSB’s subbid negotiations referred to the bonding offer.

OCWD awarded Colich the prime contract, and in January 2004, Colich sent GSB a letter of intent advising GSB it had been selected and a subcontract would soon follow. Thereafter, apparently concerned with GSB’s performance on another project, Colich asked the subcontractor to sign a written “statement of understanding” “agreeing] to bare [sz'c] responsibility for your contractual obligations and the potential delays and damages caused by [GSB].” The statement of understanding recited that GSB agreed to reimburse Colich for any delay costs or damages pertaining to the project, and warned that if GSB failed to do so, Colich would “diligently pursue contractor substitution on this basis.” GSB executed the statement of understanding.

In mid-March 2004, Colich sent GSB the subcontract agreement containing, inter alia, a verbatim provision for the bonding as proposed by GSB in its subbid, to wit, “If bond is required, a fee of 2.5% of the contract price will be added.” In early April 2004, Colich orally asked GSB to submit a bond on the project. In response, GSB’s president, Jeffrey Johnson, wrote: “[We] will make every effort to provide the requested bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
49 Cal. Rptr. 3d 447, 143 Cal. App. 4th 718, 2006 Cal. Daily Op. Serv. 9311, 2006 Daily Journal DAR 13261, 2006 Cal. App. LEXIS 1523, Counsel Stack Legal Research, https://law.counselstack.com/opinion/golden-state-boring-pipe-jacking-inc-v-orange-county-water-district-calctapp-2006.