Bodell Construction Co. v. Trustees of the California State University

62 Cal. App. 4th 1508, 73 Cal. Rptr. 2d 450, 98 Daily Journal DAR 3731, 98 Cal. Daily Op. Serv. 2730, 1998 Cal. App. LEXIS 319
CourtCalifornia Court of Appeal
DecidedApril 13, 1998
DocketD028092
StatusPublished
Cited by33 cases

This text of 62 Cal. App. 4th 1508 (Bodell Construction Co. v. Trustees of the California State University) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bodell Construction Co. v. Trustees of the California State University, 62 Cal. App. 4th 1508, 73 Cal. Rptr. 2d 450, 98 Daily Journal DAR 3731, 98 Cal. Daily Op. Serv. 2730, 1998 Cal. App. LEXIS 319 (Cal. Ct. App. 1998).

Opinion

*1511 Opinion

NARES, J.

Defendant Trustees of the California State University (the State) appeals from the judgment on special jury verdict entered in favor of plaintiff Bodell Construction Company (Bodell). The State also appeals from a postjudgment order awarding to Bodell prejudgment interest under Civil Code section 3287, subdivision (a), and determining that Bodell is entitled to recover its costs of suit from the State under the “cost-shifting” penalty provisions of subdivision (c) of Code of Civil Procedure section 998 as amended in 1994, 1 on the ground it obtained a judgment more favorable than the State’s section 998 offer to compromise. 2

In a civil action, if a plaintiff rejects a defendant’s section 998 offer to compromise and later prevails after trial but fails to obtain a judgment more favorable than the defendant’s offer, he or she may recover preoffer costs but the mandatory penalty provisions of subdivision (c) of section 998 prohibit the plaintiff from recovering postoffer costs and require that he or she pay the defendant’s postoffer costs. (§ 998, subd. (c); Stiles v. Estate of Ryan (1985) 173 Cal.App.3d 1057, 1064-1065 [219 Cal.Rptr. 647].) Under the discretionary penalty provisions of section 998, subdivision (c), the trial court in such a case may in its discretion require the plaintiff to pay not only the defendant’s ordinary court costs from the date of filing of the complaint, but also the defendant’s expert witness costs.

To provide some guidance on what constitutes a “more favorable judgment” in a nontort action, such as the case before us here, the Legislature amended subdivision (c) of section 998 in 1994 by adding language stating “. . . a plaintiff in a cause of action not based on tort shall not be deemed to have obtained a more favorable judgment unless the judgment obtained by the plaintiff, exclusive of attorney’s fees and costs, exceeds the offer made *1512 by the defendant pursuant to this section. . . .” (§ 998, subd. (c), italics added.)

Here, the State made a section 998 offer to compromise in the amount of $525,000 to settle Bodell’s breach of construction contract action. This offer, which Bodell did not accept, exceeded by about $128,000 the amount of damages (exclusive of prejudgment interest) the jury later awarded to Bodell. In a posttrial order, the court awarded to Bodell preoffer and postoffer prejudgment interest in the amount of about $147,000 under subdivision (a) of Civil Code section 3287, which the court added to the jury award of about $397,000. The resulting damage award in favor of Bodell in the sum of about $544,000 exceeded the State’s offer to compromise by about $19,000. In the same posttrial order, the court determined that Bodell had obtained a judgment which was “more favorable” than the State’s $525,000 offer within the meaning of subdivision (c) of section 998, and ordered that Bodell was entitled to recover its costs of suit (about $41,000) from the State.

The State appeals, contending the court erred in adding prejudgment interest to the jury’s damage award in determining under section 998, subdivision (c), whether the judgment Bodell obtained was “more favorable” than the State’s statutory settlement offer. This contention is twofold. First, the State maintains that no prejudgment interest should be added to the jury’s damage award in favor of Bodell in determining whether the judgment is “more favorable” than the State’s section 998 offer. In the alternative, the State contends that if prejudgment interest is added to the jury award in making this determination, postoffer prejudgment interest should be excluded from the analysis.

Although we disagree with the State’s first contention that no amount of prejudgment interest should be included in the “more favorable judgment” analysis, we agree with the State’s alternative contention. In order to promote its legislative purpose of encouraging settlement of civil litigation prior to trial, we construe subdivision (c) of section 998 to require that in a nontort action in which the plaintiff has not accepted a defendant’s section 998 offer to compromise, postoffer prejudgment interest awarded to the plaintiff under Civil Code section 3287 be excluded in determining whether the plaintiff has obtained a judgment “more favorable” than the defendant’s offer. We also conclude that any preoffer prejudgment interest the plaintiff is entitled to recover under Civil Code section 3287 in a nontort action is to be included in determining whether the plaintiff has obtained a “more favorable judgment” within the meaning of subdivision (c) of section 998.

*1513 We further conclude the court erred by including postoffer prejudgment interest in determining that Bodell had obtained a “more favorable judgment.” Because we determine on independent review that Bodell failed to obtain a judgment “more favorable” than the State’s reasonable offer to compromise, we reverse the portions of the judgment and order awarding costs to Bodell, and otherwise affirm the judgment.

Factual and Procedural Background

Bodell is a general contractor that entered into an agreement with the State for the construction of a campus building known as Craven Hall at the San Marcos campus of the California State University. As modified by a change order, the contract required Bodell to complete construction by September 28, 1992. Bodell did not complete construction by that date, but did substantially complete the project on December 14, 1992, at which time the State took beneficial use and occupancy.

The contract provided for the assessment of liquidated damages against Bodell in the amount of $4,000 for each day completion was delayed beyond the agreed completion date. Under this provision the State withheld liquidated damages in the sum of $304,100 from Bodell’s progress payments for the delay in completion from September 28, 1992, through December 14, 1992.

Following completion of the project, Bodell filed a claim with the State seeking return of the liquidated damages, and compensation for additional work performed and certain alleged damages related to the delayed completion of the project. A contractor’s claims review board convened by the State awarded Bodell $91,341 for additional work performed, offered a reduction in the amount of liquidated damages, and rejected virtually all of Bodell’s delay damages. Under this award the State would have paid nothing to Bodell, and would have retained about $44,000 of the contract balance. Bodell rejected the award and in March 1994 filed this action for breach of construction contract against the State. 3

On May 15, 1996, the State served on Bodell a section 998 offer to compromise in the amount of $525,000. This offer included statutory costs Bodell was entitled to recover, but provided each party would bear its own *1514 attorney fees. Bodell did not accept this offer and served the State with its own statutory settlement offer in the amount of $900,000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glassman v. Safeco Ins. Co. of America
California Court of Appeal, 2023
Glassman v. Safeco Ins. Co. of Am.
California Court of Appeal, 2023
Martinez v. Eatlite One, Inc.
California Court of Appeal, 2018
Martinez v. Eatlite One, Inc.
238 Cal. Rptr. 3d 747 (California Court of Appeals, 5th District, 2018)
A.M. v. Ventura Unified School Dist.
3 Cal. App. 5th 1252 (California Court of Appeal, 2016)
Vernoff Ex Rel. Vernoff v. Astrue
568 F.3d 1102 (Ninth Circuit, 2009)
Vernoff v. Astrue
Ninth Circuit, 2009
Quarry v. Doe 1
170 Cal. App. 4th 1574 (California Court of Appeal, 2009)
Lehman v. Superior Court
51 Cal. Rptr. 3d 411 (California Court of Appeal, 2006)
Paleski v. STATE DEPARTMENT OF HEALTH SERVICES
51 Cal. Rptr. 3d 28 (California Court of Appeal, 2006)
Golden State Boring & Pipe Jacking, Inc. v. Orange County Water District
49 Cal. Rptr. 3d 447 (California Court of Appeal, 2006)
Raghavan v. Boeing Co.
35 Cal. Rptr. 3d 397 (California Court of Appeal, 2005)
Gonzalez v. County of Los Angeles
19 Cal. Rptr. 3d 381 (California Court of Appeal, 2004)
Berg v. Darden
15 Cal. Rptr. 3d 829 (California Court of Appeal, 2004)
Donabedian v. Mercury Insurance
11 Cal. Rptr. 3d 45 (California Court of Appeal, 2004)
Elyaoudayan v. Hoffman
129 Cal. Rptr. 2d 41 (California Court of Appeal, 2003)
Smith v. Rae-Venter Law Group
58 P.3d 367 (California Supreme Court, 2002)
Lund v. San Joaquin Valley Railroad
108 Cal. Rptr. 2d 748 (California Court of Appeal, 2001)
Smith v. Rae-Venter Law Group
106 Cal. Rptr. 2d 873 (California Court of Appeal, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
62 Cal. App. 4th 1508, 73 Cal. Rptr. 2d 450, 98 Daily Journal DAR 3731, 98 Cal. Daily Op. Serv. 2730, 1998 Cal. App. LEXIS 319, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bodell-construction-co-v-trustees-of-the-california-state-university-calctapp-1998.