George Brackett v. Town of Rangeley

2003 ME 109, 831 A.2d 422, 2003 Me. LEXIS 121
CourtSupreme Judicial Court of Maine
DecidedAugust 25, 2003
StatusPublished
Cited by41 cases

This text of 2003 ME 109 (George Brackett v. Town of Rangeley) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George Brackett v. Town of Rangeley, 2003 ME 109, 831 A.2d 422, 2003 Me. LEXIS 121 (Me. 2003).

Opinions

DANA, J.

[¶ 1] George and Roselyn Brackett (the Bracketts) are, as we say in Maine, “from away.” When, on the Fourth of July weekend in 1999, they returned to their summer camp on Rangeley Lake for the first time that year, they discovered that [424]*424their next-door neighbor, William Sears, had, in multiple violation of the Town’s Zoning Ordinance and without the required hearing with notice to his neighbors but with the blessing of the Town’s Code Enforcement Officer, replaced his non-conforming cottage with a substantially larger but even more non-conforming dwelling. Although the Bracketts filed an appeal to the Zoning Board of Appeals within thirty days of their actual notice of Sears’s construction, the Board ultimately concluded that the Bracketts’ appeal was untimely and that under the circumstances, they were not entitled to relief from the Ordinance’s thirty day appeal period.1 We disagree, vacate the judgment of the Superior Court (Franklin County, Gorman, J.) affirming the Board’s finding, and direct that the court remand this matter to the Board to entertain the Bracketts’ appeal.

I. BACKGROUND

[¶ 2] The Bracketts and Sears own cottages on abutting land on Rangeley Lake in the Town of Rangeley. New Hampshire residents, the Bracketts use their cottage on Rangeley Lake only during the summer.

[¶ 3] In 1997, when Sears purchased his property, it included an old cottage (original cottage), a “nonconforming structure” within the Rangeley Shoreland District. See Rangeley, Me., Zoning Ordinance §§ 9(B)(51), 9(B)(70) (May 28, 1987, amended Jan. 5, 1998, and June 9, 1998). Being about forty feet back from the lake’s high water mark and six feet from the Bracketts’ property line, Sears’s original cottage violated two zoning requirements: it was situated less than 100 feet from the lake’s high water mark, see id. §§ 9(B)(53), 9(B)(69), and it did not meet the twenty-foot side setback requirement from the property line with the Bracketts. See id. § 4(G).

[¶ 4] During 1998, Peter Farnsworth, the Town’s Code Enforcement Officer (CEO), granted Sears three building permits for work on the original cottage:

• On May 28,1998, a permit to construct a deck;
• On September 29, 1998, a permit to demolish and reconstruct the part of the original cottage nearest the lake; and
• On November 3, 1998, a permit to demolish the original cottage and replace it with an entirely new cottage (new cottage).2

[425]*425The Bracketts received no notice of any of these permits. If Sears’s application for the November 3 permit had been processed properly, however, it would have gone before the Town’s Planning Board and the Bracketts would have been notified of Sears’s application for the permit. See id. §§ 7(C),(D).

[¶ 5] In October 1998, Sears began work pursuant to the September 29 permit. The Bracketts closed their cottage for the winter on October 18,1998. They testified that they were unaware of any construction at all on the Sears property that fall.

[¶ 6] After Sears began work pursuant to the second permit, he concluded that the extent of the floor timber rot in the original cottage precluded renovation and he decided to build a new cottage instead. Sears demolished the original cottage in April 1999 and began building the new cottage in mid-May. By July 2, the new cottage foundation was complete and by July 30, the walls were framed and sheathed. The Bracketts observed these changes for the first time when they returned to Rangeley on July 3, 1999. Until then, they had been unaware of the November 3 permit and Sears’s plan to replace the original cottage.

[¶ 7] As soon as they saw Sears’s construction, the Bracketts met with Robert Griseom, the Town’s new CEO, and complained about the new cottage, asking him to halt construction and to revoke the November 3 permit. He refused and did not tell them they needed to file an appeal on any particular form.

[¶ 8] On July 8, George Brackett wrote a detailed letter to the Town’s Board of Selectmen (with a copy to Griseom but not Sears) asking the Board to revoke the November 3 permit and stop construction because the new cottage violated the requirements of the Town’s Zoning Ordinance for Shoreland District construction. Although it was not on the required form, Brackett’s letter contained all the information necessary for filing an appeal. There is no indication, however, that the Town informed Sears of Brackett’s request. The CEO still did not notify the Bracketts that they needed to file an appeal with the Zoning Board of Appeals or that the appeal needed to be on a particular form. Receiving no response to this letter, the Bracketts went to the Town Office on July 27 and learned that the selectmen had not considered George Brackett’s letter because they had not met since receiving it. The person with whom the Bracketts spoke suggested that they raise their concerns with the selectmen directly at their scheduled meeting that night. Upon doing so, the Bracketts were told for the first time to file an appeal on the Zoning Board of Appeals’s approved form. They did so on July 30, challenging Sears’s November 3,1998, permit.

[¶ 9] On August 27,1999, the Board held a public hearing on the Bracketts’ appeal [426]*426and, according to the minutes, voted to “send this back to the Planning Board for their approval, and [to have] the square footage be brought into the 30% expansion rule.” On September 9, however, the Board met again, reconsidered its August 27 decision,3 and voted instead to dismiss the Bracketts’ appeal.

[¶ 10] In its letter to the Bracketts, the Board stated that the building authorized by the November 3 permit exceeded the allowable 30% expansion by 100 square feet and that “[t]he lateral expansion of the building, a non-conforming structure, was not approved by the Planning Board as required by sect. 3(C)lb of the Zoning Ordinance.” Nevertheless, the letter stated that Board dismissed the Bracketts’ appeal because:

1.The appeal was not filed in a timely manner.4 The permit was issued to Mr. Sears on Nov. 3, 1998. Construction commenced in April, 1999 and Mr. Brackett filed his appeal on July 30, 1999.
2. Mr. Sears has a vested interest in the permit.
3. Mr. Sears acted in good faith in accordance with the permit.

[¶ 11] Pursuant to M.R. Civ. P. 80B, the Bracketts appealed from the Board’s decision, asking the Superior Court (Marden, J.) to decide whether the Board had acted legally at its September 9, 1999, meeting and whether Sears’s November 3 permit was consistent with the Town’s Ordinance. In March 2001, the court vacated the Board’s September 9 decision and remanded the matter to the Board “to find facts necessary to determine whether a good cause exception to the thirty day appeal period is applicable.... ”

[¶ 12] In May 2001, the Board concluded that the Bracketts did not satisfy the good [427]*427cause exception to the thirty day rule because “there were no facts which indicated that there were ‘special circumstances which would result in a miscarriage of justice’ unless the time limit was extended.” The Board explained,

1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Houseal v. City of Portland
Maine Superior, 2023
29 McKown LLC v. Town of Boothbay Harbor
2022 ME 38 (Supreme Judicial Court of Maine, 2022)
Lamarre v. Town of China
Maine Superior, 2020
Steven Wolfram v. Town of North Haven
2017 ME 114 (Supreme Judicial Court of Maine, 2017)
Allen v. Babcock
Maine Superior, 2016
Kastelein v. Town of Edgecomb
Maine Superior, 2015
Jonathan R. Day v. Town of Phippsburg
2015 ME 13 (Supreme Judicial Court of Maine, 2015)
White v. Town of Naples
Maine Superior, 2013
Cassat v. Town of Scarborough
Maine Superior, 2012
Rich v. Town of Harpswell
Maine Superior, 2011
Khalsa v. Town of Kennebunk
Maine Superior, 2011
Nergaard v. Town of Westport Island
2009 ME 56 (Supreme Judicial Court of Maine, 2009)
Nestle Waters North America, Inc. v. Town of Fryeburg
2009 ME 30 (Supreme Judicial Court of Maine, 2009)
Mills v. Town of Eliot
2008 ME 134 (Supreme Judicial Court of Maine, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2003 ME 109, 831 A.2d 422, 2003 Me. LEXIS 121, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-brackett-v-town-of-rangeley-me-2003.