DeSomma v. Town of Casco

2000 ME 113, 755 A.2d 485, 2000 Me. 113, 2000 Me. LEXIS 122
CourtSupreme Judicial Court of Maine
DecidedJune 19, 2000
StatusPublished
Cited by19 cases

This text of 2000 ME 113 (DeSomma v. Town of Casco) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DeSomma v. Town of Casco, 2000 ME 113, 755 A.2d 485, 2000 Me. 113, 2000 Me. LEXIS 122 (Me. 2000).

Opinion

DANA, J.

[¶ 1] Anthony and Rudolph DeSomma appeal from the judgment of the Superior Court (Cumberland County, Mills, J.) affirming the decision of the Town of Casco Zoning Board of Appeals. The Board denied the DeSommas’ appeal of the Town Code Enforcement Officer’s refusal to grant them a building permit and also denied the DeSommas’ request for a second variance. The DeSommas argue on appeal that the first variance granted to them by the Board had not expired and, therefore, the CEO erroneously denied their application for a building permit on that basis. Alternatively, they argue that if the variance was only for a fixed period of time, their failure to seek a building permit within that time frame should not constitute a self-created hardship that would preclude the grant of a second variance. We agree that the original variance granted by the Board had not expired and therefore vacate the decision of the Superi- or Court.

I. FACTUAL SUMMARY

[¶ 2] In May 1970, Anthony and Rudolph DeSomma purchased a parcel of property on Thomas Pond in the Town of Casco. Their deed contained a restrictive covenant that prevented them from building a residential structure on the property with a foundation area of less than 500 square feet. In the ensuing years, the Town amended its zoning ordinances, specifically its setback provisions, so that when the provisions were applied to the DeSommas’ property they left a building envelope measuring only 452 square feet.

[¶ 3] The DeSommas sought, and on September 15, 1997, were granted a variance that allowed for a foundation of greater than 452 square feet on the property. On the back of the “Notice of Decision” granting the variance were a series of statements providing the applicant with several legal facts described as “conditions” or “information.” One of the statements notified the DeSommas that they were required to record the variance at the Registry of Deeds. They did. Another statement notified them that “a variance is not a permit,” and did not obviate the need to obtain appropriate permits. Finally, a statement provided:

A permit secured by vote of the Zoning Board of Appeals under the provisions of this ordinance shall expire if the work or . change involved is not commenced within one year of the date on which the appeal is granted, and if the work or change is not substantially completed within eighteen months of the date on which such appeal is granted.

The DeSommas did not seek a building permit nor commence building within a year of the grant of the variance.

[¶ 4] In August 1998, they submitted a request for an extension of the time limit for beginning construction. The Board denied the request, determining that it did not have the power to grant an extension and that the DeSommas could instead return with a new application for another variance. Shortly thereafter, the DeSom-mas applied for a building permit from the Town’s Code Enforcement Officer. The CEO denied the application based on a determination that the original variance granted to the DeSommas had expired. The DeSommas filed an administrative appeal of the CEO’s decision, arguing that the initial variance never expired, while in *487 the alternative, filing an application for a second variance.

[¶ 5] The Board denied both the DeSom-mas’ administrative appeal and their request for a second variance. In its notice of decision, the Board found that the CEO properly denied the DeSommas’ request for a building permit because the time in which a permit could be granted had expired. The Board also determined that the DeSommas were not entitled to a second variance based on their failure to commence and complete construction within the time frame of the first variance.

[¶ 6] The DeSommas appealed the Board’s decision to the Superior Court pursuant to M.R. Civ. P. 80B and also sought a declaratory judgment establishing that the first variance had not expired. The court affirmed the decision of the Board, determining that the CEO properly refused to issue a building permit and that the Board did not err by declining to grant a second variance. The court also denied the DeSommas’ request for a declaratory judgment, finding that they were barred by res judicata from seeking collateral review of the Board’s earlier determination that an extension of the first variance was not available to the DeSommas and its necessary implication that the first variance was of a limited duration. The De-Sommas then apipealed to this Court.

II. THE VARIANCE

[¶ 7] We review the decision of the Zoning Board of Appeals directly in the context of a Rule 80B appeal in which the Superior Court acts as an intermediate appellate court. 1 See Crispin v. Town of Scarborough, 1999 ME 112, ¶ 10, 736 A.2d 241, 244. The Board determined that the Town’s Zoning Ordinance 6.3.5.J imposes a time limitation on the duration of variances and therefore the CEO had properly denied the DeSommas a building permit because their variance had expired. The De-Sommas argue that this determination constituted error and contend that section 6.3.5. J does not apply to variances.

[¶ 8] “Interpretation of the provisions of a zoning ordinance is a question of law for the [C]ourt.” Town of Hartford v. Bryant, 645 A.2d 18, 19 (Me.1994). Therefore, we review such questions de novo. See Banks v. RSA # 1, 1998 ME 272, ¶ 4, 721 A.2d 655, 656. The contested provision of the Town’s Zoning Ordinance reads in full:

A permit secured by vote of the Zoning Board of Appeals under the provisions of this Ordinance shall expire if the work or change involved is not commenced within one year of the date on which the appeal is granted, and if the work or change is not substantially complete within eighteen (18) months of the date on which such appeal is granted.

Casco, Me., Zoning Ordinance 6.3.5.J (June 21, 1997) (hereinafter Zoning Ordinance at -). '

[¶ 9] The Town argues that the term “permit” in this provision encompasses variances and thereby establishes a time limit of one year on the duration of a variance if no work is commenced during that time. 2 The DeSommas argue that a *488 variance is not a permit within the meaning of the term as used in the Town’s Zoning Ordinance. We construe disputed language reasonably and “with regard to both the ordinance’s specific object and its general structure.” Lewis v. Town of Rockport, 1998 ME 144, ¶ 11, 712 A.2d 1047, 1049 (internal quotation marks and citation omitted). We give undefined terms their common and generally accepted meaning unless indicated otherwise by their context in the ordinance. See Town of Union v. Strong, 681 A.2d 14, 17 (Me.1996).

[¶ 10] “Variance” is defined in the Town’s Zoning Ordinance as:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Murray v. City of Portland
Maine Superior, 2022
Mary E. Campbell v. City of South Portland
2015 ME 125 (Supreme Judicial Court of Maine, 2015)
Jade Realty Corp. v. Town of Eliot
2008 ME 80 (Supreme Judicial Court of Maine, 2008)
Merrill v. Town of Durham
2007 ME 50 (Supreme Judicial Court of Maine, 2007)
Barrett v. Town of Bar Harbor
Maine Superior, 2004
Isis Development, LLC v. Town of Wells
2003 ME 149 (Supreme Judicial Court of Maine, 2003)
George Brackett v. Town of Rangeley
2003 ME 109 (Supreme Judicial Court of Maine, 2003)
Priestly v. Town of Hermon
2003 ME 9 (Supreme Judicial Court of Maine, 2003)
Griffin v. Town of Dedham
2002 ME 105 (Supreme Judicial Court of Maine, 2002)
Rockland Plaza Realty Corp. v. City of Rockland
2001 ME 81 (Supreme Judicial Court of Maine, 2001)
Lewis v. Maine Coast Artists
2001 ME 75 (Supreme Judicial Court of Maine, 2001)
Sawyer Environmental Recovery Facilities, Inc. v. Town of Hampden
2000 ME 179 (Supreme Judicial Court of Maine, 2000)
Sahl v. Town of York
2000 ME 180 (Supreme Judicial Court of Maine, 2000)
Marton v. Town of Ogunquit
2000 ME 166 (Supreme Judicial Court of Maine, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
2000 ME 113, 755 A.2d 485, 2000 Me. 113, 2000 Me. LEXIS 122, Counsel Stack Legal Research, https://law.counselstack.com/opinion/desomma-v-town-of-casco-me-2000.