Sawyer Environmental Recovery Facilities, Inc. v. Town of Hampden

2000 ME 179, 760 A.2d 257, 2000 Me. LEXIS 187
Supreme Judicial Court of Maine·Decided October 24, 2000·Published·Cited by 38 cases

Opinion

ALEXANDER, J.

[¶ 1] The Town of Hampden appeals the order of the Superior Court (Penobscot County, Kravchuk, J.) granting Sawyer Environmental Recovery Facilities, Inc.’s Rule 80B appeal from (i) a decision of the Hampden Zoning Board of Appeals affirming the Hampden Code Enforcement Officer’s (CEO) decision that two proposed landfill expansion projects constituted prohibited expansions of a nonconforming use; and (ii) a subsequent decision of the Hampden Planning Board that these projects cannot receive site plan approval based on the Zoning Board’s approval of the CEO’s land use determination. Because state law preempts the Town’s capacity to absolutely prohibit expansion of the landfill, we vacate and remand.

I. FACTS AND PROCEDURE

[¶ 2] Sawyer Environmental Recovery Facilities (SERF) operates a private, commercial solid waste disposal facility (the landfill) on land located in Hampden. The district in which the landfill is located is zoned for industrial use. SERF’S predecessor-in-interest first sought a permit to operate the landfill in 1974. Sawyer’s 1974 application requested a permit “to operate a sanitary landfill facility on land owned by Lawrence Brown, Ruby Burke, [and] Fred Oxley (Lots 44-45^46)_” 1 The application did not suggest any limitations on the landfill boundaries within the listed lots.

[¶ 3] Under the then applicable 1964 ordinance, a landfill was not a permitted use within the industrial zone. Presumably on this basis, the building inspector denied Sawyer’s 1974 application. On appeal, the Hampden Zoning Board of Appeals (ZBA) granted a permit to operate the landfill on the condition that Sawyer follow all appli *259 cable Department of Environmental Protection (DEP) guidelines and monitoring requirements. The permit included no space or coverage limitations within the three lots subject to the permit. The parties have stipulated that the Board’s approval of the application constituted the grant of a variance as well as a permit because the landfill was not a permitted use within the industrial zone. 2

[¶ 4] In 1975, SERF separately sought and obtained DEP approval to operate the landfill. The footprint of the proposed landfill, indicated in the 1975 application, covered an area within but not coextensive with Lots 44, 45, and 46. The landfill as it existed within this footprint is described by the parties as the “conventional landfill.”

[¶ 5] In 1979, the Town enacted a comprehensive zoning ordinance that imposed stricter guidance on the process for granting conditional uses and variances, subjected such uses to site plan reviews, and prohibited expansion of nonconforming uses as the ordinance defined that term. 3 The ordinance also changed the general description of industrial uses, but maintained the status that a landfill was not a use allowed in the industrial zone.

[¶ 6] SERF operated the conventional landfill until its closure in the early 1980s. Since the closure of the conventional landfill, SERF’s operations proceeded with a series of “secure” 4 landfills situated on top of the conventional landfill. This litigation concerns Secure III, Phases VI, VII, and VIII.

[¶ 7] In September 1996, SERF filed a Preliminary Information Report with the DEP, seeking a determination of public benefit for a proposed expansion of Secure III. Pursuant to 38 M.R.S.A. § 1310-AA (Supp.1999), the DEP concluded that development of Secure III, Phases VI through VIII would “provide a substantial public benefit” and “meet [the] immediate, short-term and long-term capacity needs of the State.”

[¶ 8] In March 1998, pursuant to 38 M.R.S.A. §§ 1310-N(1) & 1310-S (Supp. 1999), SERF filed an application with the DEP for a license allowing them to commence operation of Phases VI through VIII. Prior to filing, SERF notified the Town of its intent to submit the application and held a public informational meeting in accordance with DEP regulations. Pursuant to 38 M.R.S.A. § 1310-S(3), the Town was granted automatic municipal interve-nor status in SERF’s application process.

[¶ 9] With the support of a $50,000 in-tervenor assistance grant, see §§ 1310-S(4) & 1310-T (Supp.1999), the Town hired an independent technical consultant and conducted an independent review of SERF’s application. This process included a series of “stakeholder meetings” occurring between July and October 1998, attended by the DEP, SERF, and the Town’s representatives. On October 2, 1998, the Town’s technical consultant and representative submitted a final summary of the Town’s technical comments, indicating those changes SERF had agreed to incorporate in the project as a result of the Town’s independent review. The summary concluded that “[w]ith these *260 commitments and application changes, the technical issues we have raised have been addressed and our intervenor review is complete.” 5

[¶ 10] On October 20, 1998, the DEP approved SERF’S application to construct and operate Secure III, Phases VI, VII, and VIII. Despite its participation in the intervenor review process, the Town appealed the DEP’s approval of the license application to the Board of Environmental Protection (BEP). The BEP denied the appeal and affirmed the order granting SERF the license, but modified some conditions and added other minor conditions to the license. No appeal was taken from this BEP action.

[¶11] On November 20, 1998, SERF applied to the CEO for site plan approval of Secure III, Phases VI, VII and a portion of VIII. The CEO concluded that (i) SERF’S landfill constitutes a nonconforming use that is subject to ordinance provisions prohibiting the expansion of nonconforming uses; and (ii) Phase VI and Phase VII are prohibited because they are to be built on land not situated within the conventional landfill’s footprint, which the CEO determined to be the extent of any grandfathered, preexisting use. The CEO approved construction of Phase VIII because it will be built atop the conventional landfill. On February 25, 1999, SERF appealed the CEO’s decision to the ZBA. Following an extended hearing, the ZBA affirmed the CEO’s decision on April 27, 1999.

Free access — add to your briefcase to read the full text and ask questions with AI

Sawyer Environmental Recovery Facilities, Inc. v. Town of Hampden, 2000 ME 179, 760 A.2d 257, 2000 Me. LEXIS 187 (Me. 2000).

2000 ME 179 (Sawyer Environmental Recovery Facilities, Inc. v. Town of Hampden) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Town of Sabattus v. L.P. Poirier & Son, Inc.
Supreme Judicial Court of Maine, 2026
Houseal v. City of Portland
Maine Superior, 2023
Kevin J. Hill v. Town of Wells
2021 ME 38 (Supreme Judicial Court of Maine, 2021)
Portland Pipe Line Corp. v. City of So. Portland
947 F.3d 11 (First Circuit, 2020)
Portland Pipe Line Corp. v. City of S. Portland
288 F. Supp. 3d 321 (D. Maine, 2017)
Mary E. Campbell v. City of South Portland
2015 ME 125 (Supreme Judicial Court of Maine, 2015)
Bell v. Town of Gray
Maine Superior, 2015
Petrin v. Town of Scarborough
Maine Superior, 2015
Bolton v. Town of Scarborough
Maine Superior, 2015
Dubois Livestock, Inc. v. Town of Arundel
2014 ME 122 (Supreme Judicial Court of Maine, 2014)
Beckford v. Town of Clifton
Maine Superior, 2013
Town of Minot v. Starbird
Maine Superior, 2011
Johansen v. City of Bath
Maine Superior, 2010
Driscoll v. City of Saco
Maine Superior, 2010
Aydelott v. City of Portland
2010 ME 25 (Supreme Judicial Court of Maine, 2010)