Geo Group, Inc. v. United States

100 Fed. Cl. 223, 2011 U.S. Claims LEXIS 1682, 2011 WL 3455823
CourtUnited States Court of Federal Claims
DecidedJuly 29, 2011
DocketNo. 11-490C
StatusPublished
Cited by15 cases

This text of 100 Fed. Cl. 223 (Geo Group, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Geo Group, Inc. v. United States, 100 Fed. Cl. 223, 2011 U.S. Claims LEXIS 1682, 2011 WL 3455823 (uscfc 2011).

Opinion

ORDER DENYING APPLICATION FOR TEMPORARY RESTRAINING ORDER

ALLEGRA, Judge:

This post-award bid protest case is before the court on plaintiffs application for a temporary restraining order. After careful consideration of the memoranda filed by the parties, and for the reasons discussed below, the court hereby DENIES plaintiffs application. 2

I. BACKGROUND3

Since 1989, GEO Group, Inc. (GEO) (or a predecessor corporation) has held a contract with the Bureau of Prisons (BOP) to run a residential reentry facility in Brooklyn, New York (the Brooklyn Facility). That contract is set to expire on July 31, 2011. On January 16, 2009, BOP issued RFP-200-1042-NE, soliciting proposals for the provision of residential reentry services in Brooklyn or Queens, New York.

Thereafter, GEO assembled a team to draft a bid submission. That team included Jack Brown, a GEO vice-president who had overall supervisory responsibility for GEO’s existing BOP contract. By virtue of his role in the bid submission process, Mr. Brown had access to sensitive competitive information. For example, he received copies of the following: (i) CSC’s Brooklyn Facility staffing plan from its last rebid; (ii) GEO’s Bronx facility staffing plan from its last RRC rebid; (iii) GEO’s Bronx facility weekly schedule; (iv) GEO’s Bronx facility personnel resource plan; and (v) various documents relating to GEO’s relationships with the communities in which its reentry facilities were located. More importantly, according to GEO officials, Mr. Brown also had access to all the information used by GEO in crafting its response to the RFP, including GEO’s staffing costs, expenses, per diem rates and other proposed costs. During the first week of March 2009, Mr. Brown met with other GEO officials to review GEO’s draft proposal line-by-line. He then abruptly resigned on March 13, 2009.

There are indications that the timing of this resignation was not coincidental. Responses to the RFP were due on March 18, 2009. GEO submitted its response on March 16, 2009; on March 18, 2009, BOP received a second response to its RFP from Community First Services (CFS). During his evaluation of the proposals, the contracting officer (CO) found a number of instances in which the wording of the two proposals was almost identical. At the contracting officer’s recommendation, the procurement was placed on hold while this matter was investigated. At or around the same time, GEO learned that Mr. Brown had left its employ to work at CFS, a company that he had apparently founded in 2005 and kept active throughout his employment with GEO. Based upon this information, GEO notified BOP of what it believes was a potential violation of the Procurement Integrity Act, 41 U.S.C. § 423. The Justice Department’s Office of the Inspector General (OIG) investigated this matter. On January 18, 2010, OIG issued a report concluding that no theft of GEO property or proprietary information, bid-rigging or other procurement integrity violations had occurred.

At this point, the procurement moved forward. BOP conducted three rounds of discussions with the offerors, during which time, [226]*226GEO and CFS both amended their pricing proposals. Following the completion of evaluations, the CO made a “best value” determination. On February 16, 2011, BOP announced that it had awarded the contract to CFS.

On February 28, 2011, plaintiff filed an agency protest of the award to CFS. On April 8, 2011, BOP denied plaintiffs protest. On April 18, 2011, plaintiff filed a bid protest at the General Accountability Office (GAO). This protest was denied on July 26, 2011. On July 27, 2011, plaintiff filed suit in this court seeking an injunction setting aside the award to CFS, filing with its complaint the subject application for a temporary restraining order, as well as a motion for preliminary injunction. On July 28, 2011, the court conducted a status conference in this matter, at which it granted CFS’s motion to intervene. Pursuant to an order entered after the conference, earlier today, defendant and CFS filed oppositions to plaintiffs application for a temporary restraining order.

II. DISCUSSION

Plaintiff seeks a temporary restraining order enjoining defendant from beginning performance of the new contract.

We begin with common ground. In order to obtain a temporary restraining order, a party must show: (i) it will suffer irreparable injury unless the order issues; (ii) the threatened injury to it outweighs any damage to the opposing party; (iii) the temporary restraining order, if issued, will not be adverse to the public interest; and (iv) a substantial likelihood exists that it will prevail on the merits. See Software Testing Solutions, Inc. v. United States, 58 Fed.Cl. 533, 536 (2003); EDP Enters., Inc. v. United States, 56 Fed.Cl. 498, 499 (2003); OAO Corp. v. United States, 49 Fed.Cl. 478, 480 (2001). A temporary restraining order is an “extraordinary and drastic remedy, one that should not be granted unless the movant, by a clear showing, carries the burden of persuasion.” Mazurek v. Armstrong, 520 U.S. 968, 972, 117 S.Ct. 1865, 138 L.Ed.2d 162 (1997) (citing 11A C. Wright, A Miller & M. Kane, Federal Practice and Procedure § 2948, at 129-30 (2d ed. 1995)); see also Software Testing Solutions, 58 Fed.Cl. at 536; Minor Metals, Inc. v. United States, 38 Fed.Cl. 379, 381 (1997) (citing Golden Eagle Refining Co. v. United States, 4 Cl.Ct. 622, 624 (1984)). In the instant ease, the absence of any indicated likelihood of success on the merits, as well as the balancing of harms and the public’s interest, leave little doubt in the court’s mind that the pending application should be denied. Of course, a few words of elaboration are in order.

A. Likelihood of Success

For reasons that will become apparent, the court will consider the last of the four injunctive factors — likelihood of success — first. In a bid protest case, this court will enjoin the government only where an agency’s actions were arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law. 5 U.S.C. § 706(2)(A); see also 28 U.S.C. § 1491(b)(4). By its very definition, this standard recognizes the possibility that there exists a zone of acceptable results in a particular case and requires only that the final decision reached by an agency be the result of a process which “consider[s] the relevant factors” and is “within the bounds of reasoned decisionmaking.” Baltimore Gas & Elec. Co. v. Natural Res. Def. Council, Inc., 462 U.S. 87, 104-05, 103 S.Ct. 2246, 76 L.Ed.2d 437 (1983). Accordingly, this court will interfere with the government procurement process “only in extremely limited circumstances.” CACI, Inc.-Federal v. United States, 719 F.2d 1567, 1581 (Fed.Cir. 1983) (quoting United States v. John C. Grimberg Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
100 Fed. Cl. 223, 2011 U.S. Claims LEXIS 1682, 2011 WL 3455823, Counsel Stack Legal Research, https://law.counselstack.com/opinion/geo-group-inc-v-united-states-uscfc-2011.