General Motors Corp. v. Illinois Commerce Commission

574 N.E.2d 650, 143 Ill. 2d 407, 158 Ill. Dec. 537, 1991 Ill. LEXIS 46
CourtIllinois Supreme Court
DecidedJune 4, 1991
Docket69853, 69856, 69857 and 69865
StatusPublished
Cited by12 cases

This text of 574 N.E.2d 650 (General Motors Corp. v. Illinois Commerce Commission) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Motors Corp. v. Illinois Commerce Commission, 574 N.E.2d 650, 143 Ill. 2d 407, 158 Ill. Dec. 537, 1991 Ill. LEXIS 46 (Ill. 1991).

Opinion

CHIEF JUSTICE MILLER

delivered the opinion of the court:

This case involves the efforts of Illinois natural gas distribution companies (distributors) to pass through to their customers the “take-or-pay” costs which the Federal Energy Regulatory Commission (FERC) requires distributors to pay to help relieve interstate gas pipeline companies (pipelines) of the pipelines’ take-or-pay obligations to gas producers. The pipelines’ liability arose from long-term contracts formed between pipelines and natural gas producers before FERC allowed distributors to purchase gas directly from producers. The issue before this court is whether the Illinois Commerce Commission (ICC) must allow distributors to recover these costs in full from ratepayers, pursuant to the “filed rate doctrine.” The filed rate doctrine is a rule of Federal preemption that requires States to give binding effect to rates filed with and approved by FERC.

Following an extensive investigation of the take-or-pay issue, the ICC determined that it was preempted from disallowing recovery of any portion of the FERC-approved costs. (Re Costs Associated With Take-or-Pay Charges (Ill. Com. Comm’n 1988), 95 Pub. Utilities Rep. 4th 5.) The Illinois Industrial Energy Consumers (Industrial Consumers) and the Office of Public Counsel (Public Counsel) appealed. With one justice dissenting, the appellate court reversed the ICC order. (191 Ill. App. 3d 450.) The distributors and the ICC appealed to this court. (See 134 Ill. 2d Rules 315(a), 317.) We aUowed their petitions for leave to appeal, and we now reverse the judgment of the appellate court and reinstate the order of the ICC.

Background

Until 1985, Illinois distributors purchased natural gas almost exclusively from interstate pipeline companies at FERC-approved rates. The pipelines in turn purchased gas supplies directly from gas producers pursuant to long-term contracts. During the natural gas shortage of the 1970s, virtually all contracts between pipelines and producers contained “take-or-pay” clauses, which required pipelines to purchase a certain amount of gas each year or pay for any gas not taken.

In 1985, FERC adopted an “open-access policy,” which meant that, for the first time, a distributor could purchase gas directly from a producer and transport the gas over an interstate pipeline, without using the pipeline as a wholesaler. (See FERC Order No. 436 (Oct. 18, 1985), 50 Fed. Reg. 42408, 33 FERC Statutes and Regulations par. 61,007.) The new policy coincided with a natural gas surplus, creating a strong “spot” market in which distributors could purchase gas directly from producers at unregulated prices that were often much lower than FERC-approved pipeline rates.

Distributors who took advantage of the spot market were required to pass on the cost savings directly and entirely to their customers. The savings were substantial; the average residential consumer’s rates were reduced 21% as a result of spot purchases. (FERC Order No. 500 — H (Dec. 21, 1989), 54 Fed. Reg. 52344, 49 FERC Statutes and Regulations par. 30,519, citing State Treatment of Take-or-Pay Settlement Costs, 17 Gas Energy Rev. 2, 3 (Sept. 1989).) The American Gas Association estimated that spot purchases resulted in consumer savings that were six times greater than the take-or-pay costs in question here. FERC Order No. 500 — H (Dec. 21, 1989), 54 Fed. Reg. 52344, 49 FERC Statutes and Regulations par. 30,867, citing 17 Gas Energy Rev. at 3.

Although FERC’s open-access policy was beneficial to consumers, it created huge potential liabilities for pipelines, whose gas costs were often locked in at high prices by their long-term take-or-pay contracts. Unable to reduce their prices to meet competition from the spot market, pipelines could not sell all of the gas they were required to take or pay for under their contracts with producers. As a result, pipelines were subject to billions of dollars of take-or-pay liability to producers. In the two years following FERC’s adoption of the open-access policy, pipeline take-or-pay liability continued to accumulate, with no indication from FERC as to how the pipelines might handle the take-or-pay obligations.

In August 1987, FERC issued Order No. 500, which established a framework for pipelines to recover the take- or-pay costs from distributors. (FERC Order No. 500 (Aug. 14, 1987), 52 Fed. Reg. 30334, 40 FERC Statutes and Regulations par. 61,172.) In that Order, FERC expressed the view that pipelines ought to absorb some of the take-or-pay costs, rather than pass them on in full to the distributors, as part of an “equitable sharing” of the costs throughout the industry. FERC offered pipelines two alternative mechanisms for recovering portions of the take-or-pay costs from distributors.

Under the first alternative, pipelines could refuse to absorb any of the costs voluntarily and could seek full recovery of whatever portion of the take-or-pay costs FERC found to be prudently incurred. If a pipeline chose this option, however, it could recover its prudently incurred take-or-pay costs only by adding them to the cost of gas sold in the future, and distributors could avoid the charges by reducing their purchases.

FERC’s second alternative offered pipelines guaranteed recovery of up to 50% of the take-or-pay costs, which could be direct-billed to distributors at a fixed rate, if the pipeline agreed to absorb an equal amount of the cost it charged distributors. The two alternatives were not mutually exclusive. A pipeline could use the seqqnd option to recover a portion of the costs (up to 50%) and the first option to recover the remainder.

To prevent distributors from avoiding the take-or-pay charges under the second alternative, FERC imposed the charges on distributors that had purchased gas from the pipeline during a particular period regardless of whether those distributors currently continued to do business with the pipeline. The costs were allocated among distributors based on each distributor’s contribution to the pipeline’s decline in sales between two set periods, generally before and after the open-access policy took effect. As a result, those distributors who had taken advantage of the open-access spot market to achieve lower costs for ratepayers were assigned higher take-or-pay obligations than were distributors who had continued to purchase higher cost gas from pipelines when lower cost gas was available directly from producers. (See Associated Gas Distributors v. Federal Energy Regulatory Comm’n (D.C. Cir. 1989), 893 F.2d 349 (striking down this “purchase deficiency” method of allocating take-or-pay costs on grounds that it constituted retroactive ratemaking and violated the filed rate doctrine).) In the present case, this court is not called upon to determine the issue raised in Associated Gas Distributors but only to decide whether the ICC is preempted from disallowing distributors full recovery, from their customers, of the FERC-allocated take-or-pay costs.

Pipelines serving distributors in the present case uniformly elected the second alternative, which ensured them recovery of a portion of their take-or-pay costs from distributors. The pipelines submitted their take-or-pay costs to FERC for a determination that the costs were just and reasonable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth Edison Co. v. Illinois Commerce Comm'n
2014 IL App (1st) 130302 (Appellate Court of Illinois, 2014)
Commonwealth Edison Company v. Illinois Commerce Commission
2014 IL App (1st) 130302 (Appellate Court of Illinois, 2014)
State ex rel. Associated Natural Gas Co. v. Public Service Commission
954 S.W.2d 520 (Missouri Court of Appeals, 1997)
State Ex Rel. Ang v. Psc
954 S.W.2d 520 (Missouri Court of Appeals, 1997)
United Cities Gas Co. v. Illinois Commerce Commission
643 N.E.2d 719 (Illinois Supreme Court, 1994)
Gulf States Utilities Co. v. Public Utility Commission
841 S.W.2d 459 (Court of Appeals of Texas, 1992)
Appeal of Northern Utilities, Inc.
617 A.2d 1184 (Supreme Court of New Hampshire, 1992)
Abate v. Psc
480 N.W.2d 585 (Michigan Court of Appeals, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
574 N.E.2d 650, 143 Ill. 2d 407, 158 Ill. Dec. 537, 1991 Ill. LEXIS 46, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-motors-corp-v-illinois-commerce-commission-ill-1991.