Gulf States Utilities Company v. Public Utility Commission of Texas

CourtCourt of Appeals of Texas
DecidedOctober 21, 1992
Docket03-90-00173-CV
StatusPublished

This text of Gulf States Utilities Company v. Public Utility Commission of Texas (Gulf States Utilities Company v. Public Utility Commission of Texas) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gulf States Utilities Company v. Public Utility Commission of Texas, (Tex. Ct. App. 1992).

Opinion

GULF STATES.G
IN THE COURT OF APPEALS, THIRD DISTRICT OF TEXAS,


AT AUSTIN




NO. 3-90-173-CV


GULF STATES UTILITIES COMPANY,


APPELLANT



vs.


PUBLIC UTILITY COMMISSION OF TEXAS, ET AL.,


APPELLEES





FROM THE DISTRICT COURT OF TRAVIS COUNTY, 261ST JUDICIAL DISTRICT


NO. 411,817, HONORABLE W. JEANNE MEURER, JUDGE PRESIDING


Gulf States Utilities Company ("Gulf States") appeals a district court judgment affirming a decision of the Public Utility Commission (the "Commission") disallowing Gulf States' recovery of energy capacity costs arising under a series of energy contracts with the Southern Company ("Southern"), a utility holding company. The Commission disallowed Gulf States' capacity costs after determining that they had been imprudently incurred. The district court affirmed the Commission's order; we will affirm the district court's judgment.



THE CONTROVERSY

A Summary of the Dispute.

This dispute arises from Gulf States' decision to contract with Southern for the long-term supply of energy and energy capacity. In exchange for this long-term supply, Gulf States agreed to multi-billion dollar payments over an eight-year period. After entering into these contracts, Gulf States petitioned the Commission for a retail-rate increase, hoping to pass through to its retail customers the contracts' energy and capacity costs. The Commission allowed Gulf States to recover its energy costs but denied the recovery of its capacity costs, ruling that Gulf States had not acted prudently in incurring them. The Commission based its ruling on findings that Gulf States knew or should have known at the time it entered the contracts that it did not need the Southern capacity in order to meet its future requirements and that the utility failed to explore alternative sources of energy. Gulf States sued in district court for judicial review of the Commission's order, which the court affirmed. In this appeal, Gulf States contends the Commission (1) lacked jurisdiction to pass upon the "prudence" of the company's decision to purchase the Southern power; (2) violated the Commerce Clause in arriving at its final order; (3) arbitrarily and capriciously ignored key evidence; (4) failed to apply res judicata to earlier Commission orders; (5) applied an incorrect legal standard of "prudence"; and (6) erroneously shifted the parties' burdens of proof when determining the prudence of the Southern purchases.



The Relevant Details.

Gulf States is an investor-owned utility engaged in generating, transmitting, distributing, and retailing electric energy throughout southeast Texas and south-central Louisiana. Before 1982, Gulf States primarily used natural gas to fuel its generators. However, in the late 1970s and early 1980s, the company began to construct coal-fired and nuclear-fired power plants in an effort to decrease its reliance on natural gas in generating electric power. Gulf States also determined that it would not be able to generate sufficient energy to meet its customers' demands during the 1980s and decided to purchase additional power on the open market.

In February 1982, Gulf States contracted with Southern (1) to purchase coal-fired energy and capacity, agreeing to pay both energy charges and capacity charges in exchange for access to large quantities of energy. Because this dispute centers on capacity charges, we pause to explain how these differ from the energy charges that the Commission allowed Gulf States to recover.



The price of any purchase of electric power is made up of an energy component, the variable costs associated with the production of electric energy (primarily the cost of fuel and some operating and maintenance expenses), and a capacity component, costs associated with providing the capability to deliver energy (primarily the capital costs of facilities).

Pennsylvania Power Co. v. Pennsylvania Pub. Serv. Comm'n, 561 A.2d 43, 46 n.4 (Pa. Commw. Ct. 1989), aff'd, 587 A.2d 312 (1991).

The capacity charges were calculated as a percentage of Southern's fixed investment for plant construction costs, corresponding to the portion of the facilities dedicated to producing Gulf States' purchase of the plant's generating potential. The energy charges reflected the cost of fuel and other variables associated with producing the energy. These contracts covered the period from 1984 to 1992 and required Gulf States to purchase 500 megawatts of capacity. In May 1982, Gulf States contracted with Southern for an additional 500 megawatts of capacity. Gulf States agreed to a 100% take-or-pay commitment for this capacity and a 50% take-or-pay commitment for purchased energy.

In August 1982, the Commission issued Gulf States a certificate of convenience and necessity to construct a transmission line to deliver the Southern energy to Gulf States' facilities. (2) In October 1985, Gulf States filed with the Commission a statement of intent to increase its retail rates in order to pass through to its consumers the costs of the Southern purchase. See Public Utility Regulatory Act., Tex. Rev. Civ. Stat. Ann. art. 1446c, § 43(a) (West Supp. 1992) ("PURA"). The Commission assigned this request Docket No. 6525 and scheduled a hearing for March 17, 1986.

The opponents (3) to the rate increase claimed that Gulf States failed to bargain for advantageous terms. They complained specifically of the contracts' take-or-pay clauses, which had no "market out" exceptions, and of the more expensive energy rates predicated upon Southern's use of newer, more costly generators. These opponents argued that the Southern contracts were so unfavorable that Gulf States never should have entered into the agreements. After seven weeks of hearings, the parties recessed for settlement negotiations and eventually entered into a stipulation that resolved most of the disputed issues.

In June 1986, the Commission reconvened to deal with the unresolved issues, specifically whether Gulf States could pass through the capacity charges to its retail customers. The hearing examiner ruled that Gulf States had failed to demonstrate prudent decision-making in entering into the contracts to purchase large quantities of energy capacity and therefore should not be allowed to recoup its capacity charges as part of the requested rate-increase. The Commission, with one dissent, accepted this recommendation, found that Gulf States had acted imprudently, and disallowed the capacity charges. The district court affirmed the Commission's order.



JURISDICTIONAL CHALLENGES

In three points of error, Gulf States has challenged the Commission's jurisdiction to disallow recovery of the Southern capacity charges in the utility's rate increase. In these points, Gulf States makes five distinct claims:



FERC (4) previously determined the prudence of Gulf States' decision to purchase the Southern capacity;



FERC exercises exclusive jurisdiction to review the prudence of purchases of wholesale electric power;


Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Public Utilities Commission
345 U.S. 295 (Supreme Court, 1953)
Pike v. Bruce Church, Inc.
397 U.S. 137 (Supreme Court, 1970)
Nantahala Power & Light Co. v. Thornburg
476 U.S. 953 (Supreme Court, 1986)
Northern States Power Co. v. Minnesota Public Utilities Commission
344 N.W.2d 374 (Supreme Court of Minnesota, 1984)
State Ex Rel. Pittman v. MISSISSIPPI PSC
506 So. 2d 978 (Mississippi Supreme Court, 1987)
Starr County v. Starr Industrial Services, Inc.
584 S.W.2d 352 (Court of Appeals of Texas, 1979)
Northern States Power Co. v. Hagen
314 N.W.2d 32 (North Dakota Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
Gulf States Utilities Company v. Public Utility Commission of Texas, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gulf-states-utilities-company-v-public-utility-com-texapp-1992.