State ex rel. Associated Natural Gas Co. v. Public Service Commission

954 S.W.2d 520, 138 Oil & Gas Rep. 93, 1997 Mo. App. LEXIS 1632
CourtMissouri Court of Appeals
DecidedSeptember 23, 1997
DocketNo. WD 52973
StatusPublished
Cited by17 cases

This text of 954 S.W.2d 520 (State ex rel. Associated Natural Gas Co. v. Public Service Commission) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State ex rel. Associated Natural Gas Co. v. Public Service Commission, 954 S.W.2d 520, 138 Oil & Gas Rep. 93, 1997 Mo. App. LEXIS 1632 (Mo. Ct. App. 1997).

Opinion

HOWARD, Judge.

Associated Natural Gas Company (ANG) appeals from a decision of the Missouri Public Service Commission (PSC). The PSC’s decision disallowed the recovery of approximately $1.5 million in costs incurred by ANG under a gas purchase contract with SEECO, Inc., an affiliated company. ANG claims that the PSC erred by disallowing recovery of [523]*523part of the costs despite an absence of proof that ANG’s customers were harmed by the contract, that the PSC failed to properly utilize a prudence standard in evaluating the contract, and that the PSC acted arbitrarily in determining the amount to be disallowed. The PSC’s decision also disallowed recovery of approximately $700,000.00 in “take or pay” (TOP) charges which ANG had already paid to unaffiliated interstate pipelines pursuant to tariffs approved by the Federal Energy Regulatory Commission. ANG claims that it should have been allowed to recover the TOP costs pursuant to the federal preemption doctrine and the filed rate doctrine, that the refusal to allow recovery of the TOP costs was inconsistent with other PSC decisions, and that the PSC’s decision constituted an illegal taking in violation of ANG’s due process rights.

I. PSC Proceedings on the SEECO Gas Purchase Contract

ANG is a public utility operating a natural gas distribution system in a number of locations in Missouri. Pursuant to the statutory provisions in Chapter 393, RSMo 1994, the PSC has jurisdiction over the rates and charges which ANG imposes upon its retail customers in Missouri, and the PSC is responsible for ensuring that such rates and charges are “just and reasonable.” In part, this case involves the reasonableness of certain charges which ANG has sought to pass on to its Missouri customers, and the procedure for evaluating such charges can be briefly described as follows.

In addition to the basic rates which ANG charges its customers, ANG can also recover from its customers the costs which it incurs in obtaining gas from its own suppliers. These additional charges are recovered through a two-part mechanism known as a purchased gas adjustment/actual cost adjustment (PGA/ACA) process. In the first half of this process, which is known as the PGA, ANG files annual tariffs in which it estimates its cost of obtaining gas over the coming year. This part of the process is prospective or forward-looking, and the PGA amounts are then included in the customers’ bills over the ensuing twelve months. In the second half of the process, ANG submits ACA filings, which are meant to correct any discrepancies between the PGA amounts which were prospectively billed to ANG’s customers and the costs which, in retrospect, ANG actually incurred in obtaining gas from its suppliers.

The ACA filing procedure also provides the PSC with an opportunity to review the reasonableness of ANG’s cost-recouping charges by evaluating ANG’s gas acquisition practices during the relevant time period. If the costs have been appropriately incurred, the PSC allows ANG to pass them on to the customers. In order to determine if the costs can be passed through to customers as reasonable charges, the PSC employs a “prudence” standard, which will be more thoroughly described in our discussion of ANG’s initial points on appeal.

In the proceedings at issue here, the PSC staff (the Staff) reviewed four ACA filings, which covered the gas costs incurred during a 48-month period from 1988 to 1992. Due to the illness of a key Staff witness, the Staff contracted with an out-of-state consultant, Mr. Steve Rubaek, to conduct a prudence review for all four ACA periods. As part of his review of ANG’s gas purchases over this time, Mr. Rubaek evaluated an October 1, 1990, contract in which ANG agreed, for a ten-year period, to purchase approximately 70% of the gas supply for its Southeast Missouri District from SEECO, an affiliate of ANG (ANG is a division of Arkansas Western Gas Company (AWG) of Fayetteville, Arkansas, and both AWG and SEECO are wholly owned by the same entity, the Southwestern Energy Company).

In the contract, the purchase price of the gas was $1.90 per MCF (thousand cubic feet), and this price included a “premium” of approximately 54<t/MCF above the spot market price. Mr. Rubaek acknowledged that some kind of premium was appropriate for this kind of contract, as compensation for the benefits of a long-term commitment and swing service on the part of the supplier. Mr. Rubaek also acknowledged that, when ANG replaced its previous supplier with SEECO pursuant to the 1990 contract, the change resulted in lower overall gas costs.

[524]*524However, Mr. Ruback also determined that there was inadequate evidence to demonstrate that ANG had maximized its gas cost savings by contracting with SEECO as opposed to contracting with some other reliable producer or marketer. Given the information available, Mr. Ruback felt he could not determine the appropriate amount for ANG to have paid as a premium for a supplier’s willingness to provide long-term supply and swing service. In his testimony before the PSC, Mr. Ruback explained that it is extremely difficult to compare contract prices because nearly all long-term contracts are individually tailored and treated as confidential. Mr. Ruback asserted that, in order to demonstrate that its savings were maximized, ANG should have undertaken a thorough and well-documented process of requesting proposals from numerous suppliers.

It is undisputed that ANG did not engage in a thorough Request for Proposal (RFP) process before entering into its contract with SEECO. Instead, proposals were received from a total of three other potential suppliers in 1988, two years before the date of the contract, and none of the proposals were for time periods of more than two years. None of the proposals offered terms that were as favorable to ANG as those in the contract with SEECO.

Rodney Pennington, an expert witness who testified on behalf of ANG, stated that he had talked to a lot of local gas distributors about their gas acquisition practices in 1990, and none of them had used an RFP process. He said that the RFP process was “basically a nonexisting creature” at that time. In addition, ANG argued that it did not engage in a competitive bidding process because, based upon its lengthy experience in the region, it already knew the few suppliers that could meet its needs, and therefore it would be a waste of resources to send numerous requests for proposals to suppliers that ANG knew would be unable or unwilling to offer sufficient service.

ANG also offered testimony from an expert witness, Mr. John Underwood, who stated that both the process which ANG used to develop the SEECO contract and the premium paid by ANG under the SEECO contract were consistent with industry practices at the time. Mr. Underwood also performed an analysis to determine a range of reasonable prices which he would have expected ANG to pay for gas during the period in question, and he concluded that the SEECO contract price was at the low end of the range of reasonableness, and below what he would have expected from an arm’s length negotiation.

In response to ANG’s explanation for its failure to employ a competitive bidding process, Mr. Ruback maintained that ANG was asking the PSC to simply defer to its judgment—an approach which he characterized as an evasion of regulatory oversight. He stated that he did not believe that the failure to use an RFP process, by itself, rendered ANG’s gas acquisition process unreasonable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Office of the Public Counsel v. Missouri Public Service Commission
409 S.W.3d 371 (Supreme Court of Missouri, 2013)
State ex rel. Union Electric Co. v. Public Service Commission
399 S.W.3d 467 (Missouri Court of Appeals, 2013)
Public Service Commission v. Office of Public Counsel
389 S.W.3d 224 (Missouri Court of Appeals, 2012)
Ag Processing, Inc. v. KCP & L Greater Missouri Operations Co.
385 S.W.3d 511 (Missouri Court of Appeals, 2012)
State Ex Rel. AG Processing, Inc. v. Public Service Commission
311 S.W.3d 361 (Missouri Court of Appeals, 2010)
State Ex Rel. Public Counsel v. Missouri Public Service Commission
289 S.W.3d 240 (Missouri Court of Appeals, 2009)
State ex rel. Public Counsel v. Public Service Commission
274 S.W.3d 569 (Missouri Court of Appeals, 2009)
State Ex Rel. Pub. Counsel v. PUB. SERVICE COMM'N
274 S.W.3d 569 (Missouri Court of Appeals, 2009)
State Ex Rel. Laclede Gas Co v. Public Service Commission
156 S.W.3d 513 (Missouri Court of Appeals, 2005)
State Ex Rel. GS Technologies Operating Co. v. Public Service Commission
116 S.W.3d 680 (Missouri Court of Appeals, 2003)
State ex rel. Associated Natural Gas Co. v. Public Service Commission
37 S.W.3d 287 (Missouri Court of Appeals, 2000)
Ang v. PUBLIC SERVICE COM'N
37 S.W.3d 287 (Missouri Court of Appeals, 2000)
State Ex Rel. Ang v. Psc
954 S.W.2d 520 (Missouri Court of Appeals, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
954 S.W.2d 520, 138 Oil & Gas Rep. 93, 1997 Mo. App. LEXIS 1632, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-associated-natural-gas-co-v-public-service-commission-moctapp-1997.