E&I Global Energy Services, Inc. v. United States

United States Court of Federal Claims·Decided April 15, 2021·No. 19-244·Published

Opinion

In the United States Court of Federal Claims No. 19-244C Filed: April 15, 2021

E&I GLOBAL ENERGY SERVICES, INC., et al.,

Plaintiffs,

v.

THE UNITED STATES,

Defendant.

Joseph Whitcomb, Whitcomb, Selinsky, P.C., Denver, CO, for Plaintiff.

Christopher L. Harlow, Trial Attorney, Patricia M. McCarthy, Assistant Director, Commercial Litigation Branch, Civil Division, U.S. Department of Justice, Washington, D.C., with whom were Thomas Cardova, and Trevor Upderaff, Western Area Power Association, Denver, CO, of counsel, for Defendant.

MEMORANDUM OPINION AND ORDER

TAPP, Judge.

This case concerns a contract dispute stemming from the construction of a high voltage substation in South Dakota. Plaintiffs, E&I Global Energy Services, Inc. and E&C Global, LLC (collectively “E&I”), seek damages for breach of contract and injunctive relief to convert a termination for default into a termination for convenience. (Compl. at ¶ 36, ECF No. 1).

Before the Court are several motions seeking overlapping relief. The United States moves for partial summary judgment on E&I’s wrongful termination and breach of contract claims for all but one category of invoices. (Def.’s MPSJ, ECF No. 42). E&I also moves for partial summary judgment on its wrongful termination claim, seeking a declaratory judgment that the United States’ termination for default was improper together with an order converting it to a termination for convenience. (Pl.’s MPSJ, ECF No. 50). In responding to E&I’s Motion, the United States cross-moves for judgment on the pleadings with respect to E&I’s wrongful termination claim. (Def.’s MJP, ECF No. 53). Each motion is ripe for decision.

For the following reasons, the United States’ Motion for Partial Summary Judgment is GRANTED-IN-PART and DENIED-IN-PART. E&I’s Motion for Partial Summary Judgment is DENIED. Finally, the United States’ Motion for Judgment on the Pleadings is GRANTED. I. Background

In September 2015, the United States, acting through the U.S. Department of Energy’s Western Area Power Association (“WAPA”), awarded Isolux Corsan, LLC (“Isolux”) a contract to “provide all labor, materials, equipment, transportation and other resources to complete the construction of a new high voltage VT Hanlon Substation in South Dakota.” (Compl. Ex. 4). WAPA estimated the cost of construction between $5,000,000 and $10,000,000 and all work was to be completed within 545 days of the Notice to Proceed. (Id.).

Liberty Mutual Insurance Company and The Insurance Company of the State of Pennsylvania (collectively “the Sureties”) issued performance and payment bonds on behalf of Isolux. (See Tender Agreement, Compl. Ex. 2 at 1). These bonds guaranteed completion of the construction project. (Id.) In December 2016, WAPA terminated Isolux for defaulting on its performance obligations. (Compl. ¶ 15). That same month, WAPA and E&I—a subcontractor on the project—discussed E&I becoming the prime contractor on the project. (Id. ¶ 16).

Several months later, in March 2017, the Sureties entered into a Completion Agreement with E&I to take over the project. (See Completion Agreement, Compl. Ex. 1). E&I would satisfy the performance obligations of the Sureties’ bonds and complete construction of the substation for a fixed price of $5,428,625.69. (Id. at 2–3). This “Completion Price” was described as:

“[A]ll-inclusive,” consisting of all subcontractor and vendor costs, the costs of repair, replacement and/or correction of any Defects, the costs of addressing any warranty claims, the costs of general conditions work and services by Completion Contract, including its site labor force, the costs for Completion Contractor’s project staff, and all other direct and indirect costs of performance under this Agreement, including any and all insurance and/or bond premiums.

(Id. at 2 (emphasis added)). “Defects” was defined to include:

All defects resulting from work previously performed by or on behalf of [Isolux] and any other claims arising out of work that [Isolux] performed or should have performed under the Bonded Contract, regardless of whether [E&I] was aware or unaware of said defect prior to execution of this Agreement. The term “Defect” included any defect in the work performed by [E&I] during the Completion of the Project.

(Id. (emphasis added)). Section 2 of the Completion Agreement made clear that:

[E&I] assumes all responsibility and liability for correction, repair, and/or replacement of any Defects and expressly acknowledges that the Completion Price includes consideration for correction of any Defects.

(Id. § 2 (emphasis added)). Significantly, E&I expressly warranted that it had inspected and examined the status of the project and the relevant contractual agreements and disclaimed any reliance on representations from the Sureties or WAPA:

2 [E&I] has: (i) examined the Bonded Contract together with all amendments or addenda; (ii) visually investigated the status of and the conditions affecting the Work (including, but not limited to, the locality and Project site); and (iii) fully informed itself with respect to those items required to complete the Work and perform all of the obligations required hereunder independent of any representations or warranties, either express or implied, of Sureties, [WAPA], or any of their respective employees, agents, consultants, or representatives.

(Completion Agreement § 14 (emphasis added)).

After E&I and the Sureties executed the Completion Agreement, the Sureties then tendered E&I to WAPA as the new prime contractor. (Tender Agreement at 1). Most of the Completion Agreement became part of the Tender Agreement by reference. (Id. at 1–2). However, the Tender Agreement provided that “Sections 3 and 16 of the Completion agreement shall survive this tender of [E&I], such that the benefits and obligations of Sections 3 and 16 of the Completion Agreement shall remain with and continue to run to Sureties and shall not pass to [E&I], regardless of anything provided for in this Agreement.” (Id. § 2). Section 3 of the Completion Agreement allowed for E&I to perform grading work that may or may not have been within the original scope of work delineated in the payment and performance bonds. (Completion Agreement § 3). Section 16 provided that E&I would “not be responsible for paying sums due [to] any of [Isolux’s] subcontractors or vendors with respect to materials ordered and/or work performed on behalf of [Isolux] prior to the date of this Agreement.” (Id. § 16).

The Tender Agreement contained a merger clause, clarifying that the Tender Agreement represented the entire agreement and incorporated all “oral discussions and prior agreements” among the parties. (Tender Agreement § 9). Of course, as mentioned above, Sections 3 and 16 of the Completion Agreement survived the tender. (Id. § 2).

In turn, in April 2017, E&I signed a Follow-On Contract with WAPA which incorporated the Tender Agreement (and thus most of the Completion Agreement) in its entirety. (Follow-On Contract, Compl. Ex. 3). 1 E&I agreed to complete the project within 330 days of the Notice to Proceed. (Id. at 1). The Follow-On Contract included standard government contract language. The Contracting Officer, Jonathan Dittmer, became the sole authorized representative of the United States who could assign additional work, issue changes, alter the terms or price, accept non-conforming work, or waive any requirement of the contract. (Id. at 8). The Follow-On Contract incorporated the standard changes clause, FAR § 52.243-4, which required E&I to notify WAPA in writing within 20 days of performing any work pursuant to a change order from the Contracting Officer. (Id. at 28).

1 Because the Follow-On Contract, Contract No.

Free access — add to your briefcase to read the full text and ask questions with AI

E&I Global Energy Services, Inc. v. United States, (uscfc 2021).

E&I Global Energy Services, Inc. v. United States (E&I Global Energy Services, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related