Dunn v. Johnson

33 Ind. 54
CourtIndiana Supreme Court
DecidedJuly 1, 1870
StatusPublished
Cited by11 cases

This text of 33 Ind. 54 (Dunn v. Johnson) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dunn v. Johnson, 33 Ind. 54 (Ind. 1870).

Opinion

Ray, J.

This was a suit upon a written contract brought by the appellee against the appellants, for sawing lumber for them and for a failure to deliver logs to be sawed into lumber, as they had contracted by a written agreement whereby they agreed to furnish at the plaintiff’s mill one thousand saw-logs to be sawed by the plaintiff at seventy-five cents per hundred feet, payment for the sawing to be made every two weeks, the plaintiff to pile the defendants’ lumber separate from other lumber. This contract bore date on the 3d of January, 1865. The breaches alleged were a failure to pay for lumber sawed as agreed and a failure to deliver a portion of the logs. The suit as tried was compounded of two suits — one commenced on the 26th of January, 1866, and the other on the 25th of May, 1866, which were, on the 28th of June, consolidated by agreement.

[56]*56The answer was in seven paragraphs. The first was the general denial; second, payment; third, that the plaintiff’refused to perform his contract to saw, whereby the defendants were damaged one thousand dollars, which they demand, as and by way of counter-claim; foutk, as to failure to deliver logs, that plaintiff' had broken the contract by refusing to saw or let defendants take away their lumber sawed. Thf fifth paragraph need n.ot be noticed, inasmuch as. it has bearing upon any question here. The sixth paragraph was, that the defendants delivered five hundred logs, which the plaintiff’ sawed so badly and unworkmanlike that the lumber made was worthless, and the plaintiff' refusing to saw properly, the defendants, as they lawfully might, refused to deliver more logs. The seventh need not be noticed. The plaintiff' replied by general denial.

On the trial, after the defendants had offered evidence , tending to show the unworkmanlike character of the sawing done, by proving that the lumber sawed was bad, the plaintiff offered evidence tending to show that the logs of which the lumber was manufactured were of such a character that good lumber could not be made of them. This evidence was refused until the plaintiff, by leave, over the objection of the defendants, filed an additional paragraph of reply avering the fact, which was. unsuccessfully demurred to, and then the evidence was admitted, and the trial went on, the jury not having been resworn, and the defen-, dants objecting. This is urged as an. irregularity for which a new trial should have- been granted, as was demanded below, and it is also claimed that the demurer should have been sustained. We think not. The evidence ought to have been admitted when first offered. It merely tended to- disprove what the defendants were insisting upon — that the lumber was bad because of unskilful sawing'. It tended to show another and a different cause for the bad quality of the lumber’, and one for which the plaintiff was not responsible. It follows that the additional reply did not change the issue, and was therefore harmless, and that there. [57]*57was no necessity for reswearing the jury; and that though the demurer might properly have been sustained, or the paragraph stricken out on motion, or leave to file it should not have been given, yet no wrong resulted from the whole of these proceedings. They were steps by which the erroneous refusal of the evidence was corrected. Such seems to have been the final opinion of the presiding judge, when the motion for a new trial gave opportunity for fuller deliberation than w'as afforded when these various rulings were first made.

The verdict was for the plaintiff, assessing his damages at $836.40, and it appeared by answers of the jury to interrogatories submitted to them that they made up thS aggregate of damages thus assessed as follows: balance not paid on lumber sawed $393.50, and $442.90 damages for failure to deliver logs as per contract.

There was evidence showing that before all the logs which the defendants had delivered were sawed, the plaintiff' sold his saw-mill to one Pollard and delivered the possession thereof. The contract of sale was in writing and contained the following clause:

“ Said Pollard on his part agreeing to finish and wholly complete the contract heretofore entered into between said Johnson, of the one part, and "Wood and Eoudray, J. W. Browning and Jacob P. Dunn, of the other part, on the 3d day of January, 1865; said Johnson agreeing to pay Pollard for finishing the contract between him and Jacob P. Dunn, in said contract mentioned, and on the same terms and payments therein mentioned; Pollard to look to the remaining parties, Wood, Eoudray and Jones, the successor of Dunn and Love, for his payment for finishing and completing said contract.”

As the contract to furnish logs was several, we construe this agreement to look to the other parties to refer to the payment for sawing done for them individually under the contract.

This contract was signed on the 6th of February, 1866, [58]*58and it provided that Pollard should receive possession of the mill on the following day.

The court instructed the jury, that “the fact that the plaintiff sold his mill after he was notified by the defendants that they would pay for no more sawing and deliver no more logs, or that he made a sub-contract with some other person to saw the logs that might be delivered, cannot affect the right of recovery, or the measure of damages.”

It is insisted that this instruction was wrong; that as Johnson was to let Pollard receive the full amount of the contract price for the sawing, no possible profit could have resulted to Johnson, if the contract had been completed and the logs furnished; in other words, that the measure of damages between Johnson and the defendants is to be fixed by the profits he might have realized by a sub-contract with a third party to do the work. But if Pollard had contracted to do the work for half its actual value, it would not seem reasonable to charge the defendants with the consequences of Pollard’s folly — to impose upon them a liability for damages which resulted, not from the breach of their contract, but from the shrewdness and skill of the other contracting party in dealing with a third person. Plainly such consequences are not contemplated when parties enter into a contract, which by reason of some misfortune they may be unable to complete; but they consider rather the usual cost of the work for which they contract to pay and regard their liability as limited by the margin between such cost and the contract price. Johnson had no power by any sub-contract he might make with Pollard, either to increase or diminish the damages resulting from a violation by the defendants of their contract. Those damages must be determined alone from, and regulated by, the terms of the contract into which the plaintiff and defendants voluntarily entered.

Independent of authority, it would seem to be a reasonable and just rule, that on the breach of an executory contract like the present, the measure of damages should be [59]*59the difference between the contract price of tbe work to be done and tbe reasonable cost' of the work at the usual and ordinary prices. This rule would be just; for it fixes such damages on the breach of' the contract as the parties are presumed to have had in contemplation at the making of it. It would be fixed and certain, and not a sliding1 scale to be moved at the will of either party; for it is not affected by the subsequent contracts of one party with third persons.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Quaker Metal Co. v. Standard Tank Car Co.
123 A. 131 (Superior Court of Delaware, 1923)
Pillsbury Flour Mills Co. v. Walsh
110 N.E. 96 (Indiana Court of Appeals, 1915)
Singer Manufacturing Co. v. W. D. Reeves Lumber Co.
129 S.W. 805 (Supreme Court of Arkansas, 1910)
Cromer v. City of Logansport
78 N.E. 1045 (Indiana Court of Appeals, 1906)
Hamilton v. Love
53 N.E. 181 (Indiana Supreme Court, 1899)
Richter v. Meyers
31 N.E. 582 (Indiana Court of Appeals, 1892)
McAninch v. Hamilton
27 N.E. 719 (Indiana Court of Appeals, 1891)
Thompson v. Tilton
34 N.J. Eq. 306 (New Jersey Court of Chancery, 1881)
Fairfield v. Jeffreys
68 Ind. 578 (Indiana Supreme Court, 1879)
Hadley v. Prather
64 Ind. 137 (Indiana Supreme Court, 1878)

Cite This Page — Counsel Stack

Bluebook (online)
33 Ind. 54, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dunn-v-johnson-ind-1870.