Derian, Inc.

Armed Services Board of Contract Appeals·Decided August 25, 2023·No. 62957·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Derian, Inc. ) ASBCA No. 62957 ) Under Contract No. W912EF-19-C-0006 )

APPEARANCE FOR THE APPELLANT: Mr. Mark Jensen President

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Theresa L. Hampson, Esq. Engineer Trial Attorney U.S. Army Engineer District, Walla Walla

OPINION BY ADMINISTRATIVE JUDGE TAYLOR

In this appeal, the government deleted certain contract work pursuant to a partial termination for convenience from a contract for the construction of oil water separator systems and the installation of new turbine pit sump pumps inside the powerhouse at the Lower Monumental Dam in Washington state. The contractor, Derian, Inc. (Derian or appellant), seeks to recover partial termination for convenience, delay, and constructive changes costs, and the reversal of the government’s assessment of liquidated damages. The parties submitted the case under ASBCA Rule 11 and requested a ruling on entitlement and quantum. We sustain the appeal in part.

FINDINGS OF FACT

Contract Award and Requirements

1. On April 2, 2019, the United States Army Corps of Engineers (USACE or the government) awarded construction Contract No. W912EF-19-C-0006 (the contract) to Derian in the amount of $2,120,300 for the construction of oil water separator systems and the installation of new turbine pit sump pumps inside the powerhouse at Lower Monumental Dam in Washington state (R4, tab 3).

2. The contract included two Contract Line Items (CLINs) describing the work (R4, tab 3 at 28). CLIN 0001 required the supply and installation of new oil water separators at a price of $909,450, while CLIN 0002 required the supply and installation of new turbine pit sump pumps at a price of $1,210,850 (id.).

3. Contract clause 52.211-10(c) required the contractor to complete “all on-site installation ... of the headcover pumps for Main Units 1-6 between June 2019 and December 2019” (R4, tab 3 at 34). No two units could be out of service at any one time unless allowed by the contracting officer (id.). The clause further stated, “Each unit must be completely operational, commissioned, and ready to be back on line prior to taking another unit out of service” (id.). The clause also required that all on-site installation work for the main units headcover pumps be completed by December 20, 2019, with complete system commissioning to be completed by January 19, 2020 – 30 days after the final installation date (id.). The parties agreed the original contract completion date was January 19, 2020 (R4, tab 7a at 1342).

4. The contract incorporated by reference Federal Acquisition Regulation (FAR) 52.249-2, ALT I, “TERMINATION FOR THE CONVENIENCE OF THE GOVERNMENT (FIXED PRICE) (APR 2012) – ALTERNATIVE I (SEP 1996)” (R4, tab 3 at 32).

5. The contract also contained FAR 52.211-12, LIQUIDATED DAMAGES- CONSTRUCTION (SEP 2000). That clause, in part, states:

52.211-12 LIQUIDATED DAMAGES-- CONSTRUCTION (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,335.00/day for each calendar day of delay until the work is completed or accepted.

(R4, tab 3 at 35)

6. Contract Section 01 45 04.00 28, paragraph 3.10 states the contracting officer will notify the contractor of any detected noncompliance with the quality requirements (R4, tab 3 at 218). After receipt of such notice, this section required Derian to immediately take corrective action (id.). If Derian failed or refused to promptly comply, the contracting officer could issue “an order suspending or stopping all or part of the work” until Derian took satisfactory corrective action (id.).

7. The contract required Derian to submit a quality control plan (R4, tab 3 at 211). Derian’s “Quality Control Plan” listed eight “Definable Features of Work” (DFOWs) (R4, tab 6a at 1282-83). Derian’s list of DFOWs was derived from the contract’s

2 technical specifications and were intended to “help facilitate scheduling preparatory meetings” before beginning each activity (R4, tab 6a at 1282). The DFOW list included “Division 26 – Electrical” and “Division 35 – Waterway and Marine Construction,” which included the pump work (R4, tab 6a at 1283).

8. The contract also required Derian submit to the contracting officer for approval separate Activity Hazard Analysis (AHA) reports at least 15 working days prior to beginning “each activity, task or Definable Feature Of Work involving a type of work presenting hazards not experienced in previous project operations, or where a new work crew or subcontractor is to perform the work” (R4, tab 3 at 165).

9. Also, prior to beginning work on each DFOW, the contract required Derian to hold a preparatory meeting and conduct certain preparatory activities, including reviewing the minutes of the preparatory meeting (R4, tab 3 at 213-14). Likewise, Derian’s quality control plan indicated preparatory meetings would be held before beginning work on each DFOW, and the results of those meetings would be documented in separate minutes (R4, tab 6a at 1278).

10. The contract required the contractor to conform to the contract drawings (R4, tab 3 at 39). The contract drawings showed the contract required monolithic pump plates (R4, tab 3 at 394-95). The drawings also required the contractor to field verify the steel pump plate dimensions prior to cutting and fabrication of the steel plates (R4, tab 3 at 392, 394-95).

11. On April 9, 2019, the government issued Derian a notice to proceed with the contract (R4, tab 3e at 501). The notice informed Derian that only a warranted contracting officer had the authority to modify or change the contract’s terms and conditions (id).

Contract Performance

12. On May 15, 2019, Derian and the government held a pre-work meeting at Lower Monumental Dam (R4, tab 4a). During that meeting, the government again informed Derian that only the contracting officer could make changes to the contract (R4, tab 4a at 507). Similarly, the government informed Derian, at the pre-construction meeting on June 24, 2019, that the Administrative Contracting Officer (ACO) had the contract authority throughout the project, and Mr. Timothy Kuhlman, the government’s quality assurance representative, had no such authority (R4, tab 7b at 1344).

13. Following the pre-work meeting and site visit, Derian informed the government that the pump foundation plates may need to be modified due to various conflicts with existing electrical outlets, cabling, and piping (R4, tab 4x at 946). Mr. Kuhlman recalled telling Derian in response to their notification regarding the pump foundation

3 plates that “the potential solution of using split plates would be easier to install in the field than a single plate, a split plate appeared to be acceptable, and that an RFI would need to be submitted to confirm acceptability” (id. at 947). The government accepted the split plate modification (id at 948).

14. On July 11, 2019, Derian submitted an AHA for the activity/work task described as “Pump Install (Electrical)” to the government (app. supp. R4, tab 1 at 1-3). The AHA did not identify a DFOW (id.). On July 17, 2019, the government accepted the AHA for the electrical work inside the main unit number four (MU4) with comments (R4, tab 4u at 935). The comments included the direction to “[R]esubmit revised AHA when definable features of work are added” (id.). The record does not indicate Derian resubmitted the AHA for the electrical work.

15. Derian’s quality control report noted that as of July 22, 2019, the parties had not held a preparatory inspection meeting for the electrical work (R4, tab 6d at 1335).

Free access — add to your briefcase to read the full text and ask questions with AI

Derian, Inc., (asbca 2023).

Derian, Inc. (Derian, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related