Derian, Inc.

Armed Services Board of Contract Appeals·Decided August 26, 2024·No. 62957-EAJA·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Application Under the Equal Access ) to Justice Act of ) ) Derian, Inc. ) ASBCA No. 62957-EAJA ) Under Contract No. W912EF-19-C-0006 )

APPEARANCE FOR THE APPELLANT: Mr. Mark Jensen President

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Michaela M. Murdock, Esq. Engineer Trial Attorney U.S. Army Engineer District, Walla Walla

OPINION BY ADMINISTRATIVE JUDGE TAYLOR ON APPELLANT’S EQUAL ACCESS TO JUSTICE APPLICATION

Appellant, Derian, Inc. (Derian), submitted an Application for Award of Attorney’s Fees and Other Fees & Expenses under the Equal Access to Justice Act (EAJA), 5 U.S.C. § 504, as amended. The underlying appeal arose from Derian’s claims for delay, constructive changes, a deductive credit determination, and the government’s assessment of liquidated damages, all arising from a contract for the construction of oil water separator systems and the installation of new turbine pit sump pumps inside the powerhouse at Lower Monumental Dam in Washington state. Derian, Inc., ASBCA No. 62957, 23-1 BCA ¶ 38,425, motion for reconsideration denied, 24-1 BCA ¶ 38,499. Familiarity with those decisions is presumed. We find Derian is an eligible prevailing party on its split pump plate modification claim, its deductive credit claim, and the government’s claim for liquidated damages. We further determine, however, that the government’s position on those claims was substantially justified. As such, we deny Derian’s EAJA application.

BACKGROUND

In 2019, the United States Army Corps of Engineers (USACE or the government) awarded Derian a contract to construct oil water separator systems and install new turbine pit sump pumps inside the powerhouse at Lower Monumental Dam in Washington state. Derian, Inc., 23-1 BCA ¶ 38,425 at 186,744. The government partially terminated the contract for convenience, including removing the requirement to install the remaining turbine pit sump pumps (id. at 186,748). Derian submitted a certified claim asserting a “Request for Equitable Adjustment” (REA) listing 11 USACE actions Derian alleged created contract changes and delays resulting in increased costs (id.). Derian also asserted a claim for “termination settlement costs” and disputed the government’s liquidated damage assessment (id. at 186,749). The government issued a contracting officer’s final decision (COFD) in response to Derian’s claims finding merit or partial merit to four of the 11 REA claims, determining a government credit for the terminated work, and asserting a government claim for liquidated damages (id. at 186,749-50). Derian appealed that COFD to the Board.

In its complaint, Derian sought increased costs resulting from four of its REA claims (id. at 186,750). Derian also challenged the government’s credit for the terminated work and appealed the government’s liquidated damages assessment (id.). The parties elected a written disposition under Board Rule 11.

In our decision on the merits, we denied three of Derian’s equitable adjustment claims but partially granted Derian’s claim for increased costs due to the changed requirement for split as opposed to monolithic pump plates (id. at 186,757-58). Our decision also determined the correct deductive credit amount for the terminated work (id. at 186,751-55). Finally, our decision found the government was not entitled to recover liquidated damages (id. at 186,759-60). We subsequently denied the government’s reconsideration motion on our denial of its liquidated damages assessment. Derian, Inc., 24-1 BCA ¶ 38,499 at 187,134.

In its EAJA application, Derian seeks fees and expenses for “Claim Preparation Expenses”, “Legal Fees”, and “Claim Award Interest” (app. EAJA application, at 2). In its reply, Derian withdrew its claim for interest acknowledging the Board had already ordered the payment of the Contract Disputes Act interest in its original decision (app. reply at 3).

DECISION

To recover under the EAJA, an applicant must timely file its application, establish it is an eligible party, and prove that it was a prevailing party in the underlying action. Rex Sys., Inc., ASBCA No. 52247, 02-1 BCA ¶ 31,760 at 156,854. The Board may also deny an award if the government’s position is determined to have been substantially justified, or when special circumstances make an award unjust. Equal Access to Justice Act, 5 U.S.C. § 504(a)(1); Alderman Bldg. Co., ASBCA No. 58082- EAJA, 22-1 BCA ¶ 38,126 at 185,211. As a partial waiver of sovereign immunity, the EAJA is to be strictly construed in favor of the United States. Ardestanti v. I.N.S., 502 U.S. 129, 137 (1991).

2 The government does not oppose Derian’s EAJA application based on Derian’s status as a prevailing party, that its application was timely filed, or Derian is an eligible party under the EAJA (gov’t resp. at 10). Rather, the government contends Derian is not eligible for EAJA fees because the government’s litigation position was substantially justified (gov’t resp. at 10-16). The government also challenges Derian’s EAJA application on the basis that it includes fees and other expenses that are not allowable, reasonable, or properly documented (gov’t resp. at 16-22).

“The Government’s position is substantially justified if it is ‘justified to a degree that could satisfy a reasonable person’ and has a ‘reasonable basis in both law and fact.’” Int’l Custom Prods., Inc. v. United States, 843 F.3d 1355, 1358 (Fed. Cir. 2016) (quoting Pierce v. Underwood, 487 U.S. 552, 565-66 (1988). “[T]he government is not required to prove that it had a substantial likelihood of victory in the litigation.” Buck Town Contractors & Co., ASBCA No. 60939-EAJA, 20-1 BCA ¶ 37,705 at 183,048. “Substantial justification applies to the entirety of the litigation position and not just the posture on individual issues.” K&K Indus., Inc., ASBCA No. 61189, 19-1 BCA ¶ 37,353 at 181,628. Finally, the government bears the burden of proof to show its position was substantially justified. Id. (citing Amaratek, ASBCA Nos. 59149, 59395, 15-1 BCA ¶ 35,866 at 175,348).

The government contends its litigation position was substantially justified on each of the three issues on which the Board found for appellant (gov’t resp. at 13-16). With regards to Derian’s REA claims, the government first points out that it prevailed on three of the four claims (gov’t resp. at 13). On the “split pump plates” claim, the government contends the final decision found partial merit to Derian’s claim and awarded Derian additional labor costs to adjust the pump plates due to the existing field conditions (id. at 13-14). The government, however, denied Derian’s remaining claimed costs on that claim since Derian chose to use split instead of monolithic plates and indicated that choice would not have a cost impact (id. at 13). In its Rule 11 brief, the government further argued it was Derian’s responsibility to verify the pump plate dimensions in the drawings, and Derian failed to supply supporting documentation for its alleged increased labor costs to install the split plates (Derian, Inc., 23-1 BCA ¶ 38,425 at 186,758).

In our decision, we partially granted Derian’s claim by awarding it an additional $2,883 for the increased material costs incurred by a subcontractor to provide split as opposed to monolithic plates (id.).

Free access — add to your briefcase to read the full text and ask questions with AI

Derian, Inc., (asbca 2024).

Derian, Inc. (Derian, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Pierce v. Underwood
487 U.S. 552 (Supreme Court, 1988)
Ardestani v. Immigration & Naturalization Service
502 U.S. 129 (Supreme Court, 1991)
International Custom Products, Inc. v. United States
843 F.3d 1355 (Federal Circuit, 2016)
Mattson v. Bowen
824 F.2d 655 (Eighth Circuit, 1987)