Del. Riverkeeper Network v. Fed. Energy Regulatory Comm'n

895 F.3d 102
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 10, 2018
Docket17-5084
StatusPublished
Cited by18 cases

This text of 895 F.3d 102 (Del. Riverkeeper Network v. Fed. Energy Regulatory Comm'n) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Del. Riverkeeper Network v. Fed. Energy Regulatory Comm'n, 895 F.3d 102 (D.C. Cir. 2018).

Opinion

Opinion for the Court filed by Circuit Judge Katsas.

This appeal presents broad due-process challenges to how the Federal Energy Regulatory Commission conducts business. By statute, FERC is required to recover its costs from regulated industries. The appellants contend that this improperly incentivizes the Commission to approve new natural-gas pipelines, in order to ensure itself future funding sources. The appellants *106 also challenge FERC's use of tolling orders to meet its statutory deadlines for acting on applications for rehearing.

I

The Natural Gas Act requires companies to obtain a "certificate of public convenience and necessity" before constructing facilities to transport natural gas in interstate commerce. 15 U.S.C. § 717f(c)(1)(A). FERC must issue a certificate to a qualified applicant if the proposed project is "required by the present or future public convenience and necessity," subject to any reasonable terms and conditions imposed by the Commission. Id. § 717f(e).

FERC, a Commission within the Department of Energy, receives annual appropriations fixed by Congress. 42 U.S.C. § 7171 (j). However, the Omnibus Budget Reconciliation Act of 1986 ("Budget Act") requires FERC to "assess and collect" from the various industries that it regulates, including the natural-gas industry, "fees and annual charges in any fiscal year in amounts equal to all of the costs incurred by the Commission in that fiscal year." Id. § 7178(a)(1). These receipts must be "credited to the general fund of the Treasury." Id. § 7178(f).

A party "aggrieved by an order issued by the Commission in a proceeding under" the Natural Gas Act may seek rehearing. 15 U.S.C. § 717r(a). "Unless the Commission acts upon the application for rehearing within thirty days after it is filed, such application may be deemed to have been denied." Id. The aggrieved party then may seek judicial review, in the court of appeals, "within sixty days after the order of the Commission upon the application for rehearing." Id. § 717r(b).

In 2015, intervenor PennEast Pipeline Co. sought a certificate to build a 114-mile natural-gas pipeline running through Pennsylvania and New Jersey. Appellants Delaware Riverkeeper Network and its director Maya van Rossum (collectively "Riverkeeper") intervened to oppose the project.

In 2016, while FERC was still reviewing the proposal, Riverkeeper filed a complaint seeking declaratory relief against the Commission and its members. The complaint alleges that FERC's funding structure creates structural bias, in violation of the Due Process Clause of the Fifth Amendment, by incentivizing the Commission to approve new pipelines in order to secure additional sources for its future funding. The complaint also challenges the Commission's use of tolling orders to satisfy its 30-day deadline for acting on rehearing applications. Those tolling orders grant rehearing for the limited purpose of giving the Commission more time to consider pending applications. In the meantime, the complaint alleges, FERC routinely allows construction to proceed on approved projects. According to Riverkeeper, this frustrates judicial review, again in violation of the Due Process Clause.

After PennEast intervened as a defendant in the district court, the Commission and PennEast moved to dismiss the complaint. They argued that Riverkeeper had not identified any liberty or property interest protected by the Due Process Clause and that, in any event, FERC provides all the process that is due. The district court agreed with both points and dismissed the complaint for failure to state a claim. Del. Riverkeeper Network v. FERC , 243 F.Supp.3d 141 (D.D.C. 2017). This appeal followed.

II

Cases involving the Commission typically come to us as petitions for review of final agency orders, not as appeals from the district court. We therefore begin by *107 explaining why this case is properly before us.

In NO Gas Pipeline v. FERC , 756 F.3d 764 (D.C. Cir. 2014), this Court held that the judicial-review provision in the Natural Gas Act does not apply to the kind of structural-bias claim at issue here. We reasoned that such a claim "does not target any aspect of FERC's actual decision" in any individual proceeding under the Natural Gas Act, but instead "centers wholly on" the Budget Act. Id. at 769 . Therefore, we concluded, such a claim may be brought only in district court. See id. We emphasized the "narrowness of our jurisdictional holding," and we distinguished structural-bias claims from claims that a specific FERC decision "was tainted by actual bias or some other improper motivation." Id.

Under NO Gas Pipeline , Riverkeeper properly filed this case in the district court. Its principal claim targets the Budget Act's funding mechanism rather than any individual decision to award a certificate of public necessity. Therefore, the Natural Gas Act does not channel judicial review directly to the courts of appeals, and so the district court retained its federal-question jurisdiction under 28 U.S.C. § 1331 .

We also conclude that Riverkeeper established Article III standing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
895 F.3d 102, Counsel Stack Legal Research, https://law.counselstack.com/opinion/del-riverkeeper-network-v-fed-energy-regulatory-commn-cadc-2018.