Protecting Air for Waterville v. Ohio EPA

Court of Appeals for the Sixth Circuit·Decided February 21, 2019·No. 18-3025·Unpublished

Opinion

NOT RECOMMENDED FOR FULL-TEXT PUBLICATION File Name: 19a0088n.06

No. 18-3025

UNITED STATES COURT OF APPEALS FOR THE SIXTH CIRCUIT

PROTECTING AIR FOR WATERVILLE; ) NEIGHBORS AGAINST NEXUS; SUSTAINABLE ) FILED MEDINA COUNTY, ) Feb 21, 2019 ) DEBORAH S. HUNT, Clerk Petitioners, )

)

v. ) ON APPEAL FROM THE ) ENVIRONMENTAL OHIO ENVIRONMENTAL PROTECTION ) PROTECTION AGENCY, Craig Butler, Director; WADSWORTH ) ADMINISTRATION COMPRESSOR STATION; WATERVILLE ) COMPRESSOR STATION, )

)

Respondents. )

Before: MERRITT, COOK, and LARSEN, Circuit Judges.

LARSEN, Circuit Judge. Three citizen groups, Protecting Air for Waterville, Neighbors Against NEXUS, and Sustainable Medina County, challenge air pollution permits issued to NEXUS Gas Transmission for two natural gas compressor stations along NEXUS’s natural gas pipeline. But the citizen groups have not demonstrated standing to challenge the permits. We are therefore required to DISMISS their petition for review for lack of jurisdiction.

I.

The $2.1 billion NEXUS pipeline project involves the construction, operation, and maintenance of a 257-mile natural gas pipeline system originating in Ohio and running into Michigan. The project also includes the construction and operation of four natural gas compressor

stations along the pipeline. Two of those compressor stations—one located near Waterville, Ohio and another located near Wadsworth, Ohio—are at issue in this case.

Before transporting or selling natural gas, the federal Natural Gas Act required that NEXUS obtain a certificate of public convenience and necessity through the Federal Energy Regulatory Commission (FERC). See 15 U.S.C. § 717f(c). In August 2017, FERC granted NEXUS this certificate, subject to several conditions. One condition was that NEXUS obtain the air pollution-control permits required by the federal Clean Air Act. NEXUS had, in fact, already received the necessary permits from the Ohio EPA, which was authorized by federal law to issue such permits. See 42 U.S.C. § 7661(4); 40 C.F.R. § 52.1870; 15 U.S.C. § 717b(d)(2). The Ohio EPA Director had issued the permits in September 2016 pursuant to chapter 3745-31 of the Ohio Administrative Code, part of Ohio’s implementation of the federal Clean Air Act. See 40 C.F.R. § 52.1870. Before these permits were issued, members of the public had the opportunity to attend public hearings, which were publicized in the local papers, and to submit written comments on the subject; the Ohio EPA made written replies to the submitted comments.

In October 2016, Protecting Air for Waterville and Neighbors Against NEXUS appealed the Ohio EPA’s permit issuance for the Waterville Compressor Station; Sustainable Medina County appealed the Ohio EPA’s permit issuance for the Wadsworth Compressor Station. All three citizen groups appealed to the Ohio Environmental Review Appeals Commission (ERAC), which has jurisdiction to hear appeals from certain actions of the Ohio EPA Director. See Ohio Rev. Code §§ 3745.04, 3745.07. In August 2017, while discovery was ongoing, NEXUS filed motions to dismiss the ERAC proceedings for lack of subject-matter jurisdiction, claiming that the Natural Gas Act, 15 U.S.C. § 717r(d)(1), vests jurisdiction over such appeals exclusively with the United States Courts of Appeal. ERAC agreed and dismissed the appeals.

In January 2018, the three citizen groups filed a petition for review in this court. They argued first that ERAC had jurisdiction to hear their appeal and that termination of the ERAC proceedings violated their rights to due process. With respect to these claims, petitioners requested that this court “remand the contested permit issuances to [ERAC] with instructions for them to be fully adjudicated.” In the alternative, petitioners argued that the permits were invalid because the Ohio EPA Director had issued them in violation of Ohio’s “de minimis” exemption and asked that the permits be revoked and the proceedings remanded to the Ohio EPA Director.

II.

Petitioners claim that ERAC erred when it determined that it lacked jurisdiction over their appeal, and that ERAC’s dismissal of their appeal deprived them of due process. These claims are not properly before us. Even assuming statutory authority permitting our review of ERAC’s decision,1 petitioners have not appealed ERAC’s decision to this court. Petitioners failed to name ERAC as a respondent in this appeal, see Fed. R. App. P. 15(a)(2)(B); and ERAC was not served with a copy of the petition, see Fed. R. App. P. 15(c). The record of the ERAC proceedings was, therefore, never filed in this court, see Fed. R. App. P. 17(a).

After the Ohio EPA pointed out these problems, petitioners stated in their reply brief that they had filed, “contemporaneously to the filing of their Reply Brief,” a motion to name ERAC as a responding party and to expand the record to include the ERAC proceedings. But petitioners did not file this motion with their reply brief, or even shortly thereafter; they instead asked to name ERAC as a respondent nearly three months later, approximately three weeks before oral argument

1 Petitioners assert that ERAC’s decisions may be reviewed in this court pursuant to Section 19 of the Natural Gas Act, 15 U.S.C. § 717r(d)(1). Nexus and the Ohio EPA contest that assertion, arguing that, under Ohio law, appellate review of ERAC’s decisions lies in the Court of Appeals of Franklin County.

was scheduled in this case. Their motion offered no explanation for the delay. This court denied that untimely motion; ERAC is thus not a party before us and we may not review its decision.

III.

Petitioners next argue that the permits are invalid because they were issued in violation of Ohio’s “de minimis” exemption rule, OAC 3745-15-05 (C)(3) and (4). They ask this court to revoke the permits and remand the proceedings to the Ohio EPA Director. We cannot reach the merits of this claim, however, because petitioners have failed to establish standing.

In Sierra Club v. EPA, this court addressed what was then a question of first impression in this circuit: the “manner and degree of evidence necessary to prove standing upon direct [appellate] review” of final2 agency action. 793 F.3d 656, 662 (6th Cir. 2015) (quotations omitted). Agreeing with our sister circuits, this court held that to establish standing, “the petitioner carries a burden of production similar to that required at summary judgment.” Id.; see also N. Laramie Range All. v. FERC, 733 F.3d 1030, 1034 (10th Cir. 2013); Iowa League of Cities v. EPA, 711 F.3d 844, 869 (8th Cir. 2013); Citizens Against Ruining the Env’t v. EPA, 535 F.3d 670, 675 (7th Cir. 2008); Sierra Club v. EPA, 292 F.3d 895, 899 (D.C. Cir. 2002). Our law makes clear, therefore, that “the petitioner [must] present specific facts supporting standing through citations to the administrative record or ‘affidavits or other evidence’ attached to its opening brief, unless

2 Although this circuit has not addressed the question, all parties agree that we lack statutory jurisdiction to review the Director’s permitting decisions unless the issuance of the permits constituted “final” agency action. See Del. Riverkeeper Network v. Sec’y Pa. Dep’t of Envtl. Prot., 903 F.3d 65, 71 (3d Cir. 2018) (joining “the First Circuit in holding that the Natural Gas Act provides jurisdiction to review only ‘final agency action of a type that is customarily subject to judicial review’” (quoting Berkshire Envtl. Action Team, Inc. v. Tenn. Gas Pipeline Co., 851 F.3d 105, 111 (1st Cir. 2017))). They dispute whether the Director’s decision was final. We need not decide the finality question. If the Director’s decision was not final, the parties agree that we lack statutory jurisdiction; if the Director’s decision was final, we still lack jurisdiction because petitioners have failed to establish standing for purposes of Article III.

Free access — add to your briefcase to read the full text and ask questions with AI

Protecting Air for Waterville v. Ohio EPA, (6th Cir. 2019).

Protecting Air for Waterville v. Ohio EPA (Protecting Air for Waterville v. Ohio EPA) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Baker v. Carr
369 U.S. 186 (Supreme Court, 1962)
Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)
Summers v. Earth Island Institute
555 U.S. 488 (Supreme Court, 2009)
Sierra Club v. Environmental Protection Agency
292 F.3d 895 (D.C. Circuit, 2002)
Sierra Club v. U.S. Environmental Protection Agency
762 F.3d 971 (Ninth Circuit, 2014)
Spokeo, Inc. v. Robins
578 U.S. 330 (Supreme Court, 2016)
Sierra Club v. Federal Energy Regulatory Commission
867 F.3d 1357 (D.C. Circuit, 2017)
Sierra Club v. State Water Control Board
898 F.3d 383 (Fourth Circuit, 2018)
American Canoe Ass'n v. Murphy Farms, Inc.
326 F.3d 505 (Fourth Circuit, 2003)