Bohon v. Federal Energy Regulatory Commission

District Court, District of Columbia·Decided May 6, 2020·No. Civil Action No. 2020-0006·Published

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

CLETUS WOODROW & BEVERLY BOHON, et al.,

Plaintiffs, v. Civil Action No. 20-6 (JEB)

FEDERAL ENERGY REGULATORY COMMISSION, et al.,

Defendants.

MEMORANDUM OPINION

This case presents the latest trickle in a veritable flood of litigation relating to Defendant Mountain Valley Pipeline, LLC’s proposed construction of a natural-gas pipeline through Virginia and West Virginia. In October 2017, Defendant Federal Energy Regulatory Commission granted MVP a certificate that permitted the company to build the pipeline and enabled it to exercise the agency’s eminent-domain authority to do so. That approval has thus far withstood various administrative challenges as well as review in multiple federal courts of appeals.

Not easily deterred, Plaintiffs –– homeowners along the proposed pipeline’s path –– bring another suit, this one featuring constitutional challenges to FERC’s enabling statute, the Natural Gas Act. They seek, among other things, a nationwide injunction ending the existing FERC pipeline-approval process and voiding all pipeline certificates, including the one issued to MVP. The NGA, however, channels review of FERC decisions relating to pipelines –– including constitutional claims inhering in those controversies –– to the agency, not to a district court. Plaintiffs’ attempt to transform their grievance with FERC over the MVP certificate into a facial

constitutional challenge cannot save them from the statutorily mandated administrative-review process. The Court will therefore dismiss the case for lack of subject-matter jurisdiction. I. Background A. Statutory Background Congress enacted the NGA, 15 U.S.C. § 717, et seq., “with the ‘principal purpose’ of ‘encouraging the orderly development of plentiful supplies of natural gas at reasonable prices.’” Myersville Citizens for a Rural Cmty., Inc. v. FERC, 783 F.3d 1301, 1307 (D.C. Cir. 2015) (alterations omitted) (quoting NAACP v. Fed. Power Comm’n, 425 U.S. 662, 669–70 (1976)). “The Act vests FERC with broad authority to regulate the transportation and sale of natural gas in interstate commerce.” Minisink Residents for Envtl. Pres. & Safety v. FERC, 762 F.3d 97, 101 (D.C. Cir. 2014). The agency’s responsibilities include the authorization of interstate natural-gas pipelines, such as the MVP project at issue here. See 15 U.S.C. § 717f(c)).

The “keystone” of FERC’s pipeline-authorization process is the so-called “certificate of public convenience and necessity.” Bold All. v. FERC, No. 17-1822, 2018 WL 4681004, at *1 (D.D.C. Sept. 28, 2018) (quoting 15 U.S.C. § 717f(d)). These certificates, which permit “the construction or extension of natural gas transportation facilities,” are a prerequisite for the construction of any interstate natural-gas pipeline. Myersville, 783 F.3d at 1307 (citing 15 U.S.C. § 717f(c)). According to the NGA, FERC “shall” issue a certificate “to any qualified applicant” upon a finding that “the applicant is able and willing properly to do the acts and to perform the service proposed,” and that the proposed service or construction “is or will be required by the present or future public convenience and necessity.” 15 U.S.C. § 717f(e). FERC’s issuance of a certificate, moreover, conveys the power of eminent domain to its holder.

Id. § 717f(h). Armed with that authority, the certificate holder can initiate condemnation proceedings as necessary. Id.

FERC’s issuance of a certificate represents the culmination of an extensive application process and sets into motion elaborate review mechanisms. First, in order to receive the certificate, the applicant must submit reams of technical, economic, and environmental information concerning the project. See 18 C.F.R. § 157.6(b) (application content requirements including “detailed cost of service data”). The applicant must also make a “good faith effort to notify all affected” landowners, towns, communities, and government agencies, and any interested party, including environmental and tribal groups may intervene in the proceeding to file comments of their own. Id. §§ 157.6(d), 157.10. After a lengthy review of these materials — along with the consideration of a number of factors, such as the project’s environmental impact and whether its “public benefits” outweigh the “potential adverse consequences” ––– the agency may grant the certificate. Certification of New Interstate Natural Gas Pipeline Facilities, 88 FERC ¶ 61,227 (Sept. 15, 1999), clarified, 90 FERC ¶ 61,128 (Feb. 9, 2000), further clarified, 92 FERC ¶ 61,094 (July 28, 2000) (FERC’s policy statement outlining certificate-issuance criteria).

Next, “aggrieved” persons, ranging from the applicants themselves to interested homeowners, advocacy groups, and state and local governments, may challenge FERC’s decision or ask for modifications of its order. See 15 U.S.C. § 717r(a). To do so, they must first file for rehearing before the agency. Id. If FERC declines to rehear the matter or issues a final order regarding it, the parties may then file a petition for review in the appropriate court of appeals. Id. Upon the filing of such a petition, the court of appeals retains “exclusive” jurisdiction to affirm, modify, or set aside such an order “in whole or in part.” Id. § 717r(b)

(emphasis added). The petitioners may not raise new objections to the agency’s order in the court of appeals unless “there is reasonable ground for [the] failure” to offer them previously. Id.

B. MVP Project and Related Litigation This dispute traces its roots to October 2015, when MVP set the above-described process in motion by filing an application with FERC to maintain, construct, and operate a pipeline running from Wetzel County, West Virginia, to Pittsylvania County, Virginia. See Mountain Valley Pipeline, LLC Equitrans, L.P., 161 FERC ¶ 61043 p. 1 (Oct. 13, 2017). After two years of review, including reflection on hundreds of comments from interested parties, FERC issued MVP the coveted certificate of authorization. Id.

Over twenty affected landowners, environmental organizations, and tribal groups sought rehearing of FERC’s issuance of the certificate, which the agency rejected in a lengthy opinion affirming its prior conclusions. See Mountain Valley Pipeline, LLC Equitrans, L.P., 163 FERC ¶ 61197 (June 15, 2018). Many of those same parties then petitioned for review in the D.C. Circuit, lodging sixteen different challenges, both statutory and constitutional, relating to the certificate’s issuance. See Appalachian Voices v. FERC, No. 17-1271, 2019 WL 847199, at *1 (D.C. Cir. Feb. 19, 2019). The Court of Appeals affirmed the agency’s decision and, in doing so, rejected the petitioners’ constitutional claims grounded in the Fifth Amendment’s Due Process and Takings Clauses. Id. at *2–3.

While the MVP project flowed through the agency and into the Circuit, a separate group of landowners along the pipeline’s path brought suit in the Western District of Virginia arguing –– as Plaintiffs do here –– that the NGA constitutes an impermissible delegation of legislative authority to the agency. Berkley v. Mountain Valley Pipeline, LLC, No. 17-357, 2017 WL 6327829, at *2 (W.D. Va. Dec. 11, 2017). The district court dismissed the case, concluding that

the NGA stripped it of jurisdiction over those claims, id. at *1, and the Fourth Circuit affirmed. See 896 F.3d 624, 627 (4th Cir. 2018), cert. den. sub nom. Berkley v. FERC, 139 S. Ct. 941 (2019).

Free access — add to your briefcase to read the full text and ask questions with AI

Bohon v. Federal Energy Regulatory Commission, (D.D.C. 2020).

Bohon v. Federal Energy Regulatory Commission (Bohon v. Federal Energy Regulatory Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

City of Tacoma v. Taxpayers of Tacoma
357 U.S. 320 (Supreme Court, 1958)
Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)
Bowles v. Russell
551 U.S. 205 (Supreme Court, 2007)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
MedImmune, Inc. v. Genentech, Inc.
549 U.S. 118 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Sturm Ruger Co Inc v. Chao, Elaine
300 F.3d 867 (D.C. Circuit, 2002)
Victor Herbert v. National Academy of Sciences
974 F.2d 192 (D.C. Circuit, 1992)
Elgin v. Department of the Treasury
132 S. Ct. 2126 (Supreme Court, 2012)
Grand Lodge of the Fraternal Order of Police v. Ashcroft
185 F. Supp. 2d 9 (District of Columbia, 2001)
Jarkesy v. Securities & Exchange Commission
803 F.3d 9 (D.C. Circuit, 2015)
Lucia v. SEC
585 U.S. 237 (Supreme Court, 2018)