D & E Construction Co. v. Robert J. Denley Co.

38 S.W.3d 513, 2001 Tenn. LEXIS 59
CourtTennessee Supreme Court
DecidedJanuary 19, 2001
StatusPublished
Cited by62 cases

This text of 38 S.W.3d 513 (D & E Construction Co. v. Robert J. Denley Co.) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D & E Construction Co. v. Robert J. Denley Co., 38 S.W.3d 513, 2001 Tenn. LEXIS 59 (Tenn. 2001).

Opinion

OPINION

BARKER, J.,

delivered the opinion of the court,

in which ANDERSON, C.J., and DROWOTA, BIRCH, and HOLDER, JJ., joined.

The contractor submitted to arbitration a contractual payment dispute with the project owner arising from a contract to build a subdivision in Collierville. The arbitrators found in favor of the contractor and included an award of attorney’s fees. The trial court determined that the arbitration panel • exceeded its authority in awarding attorney’s fees and vacated the arbitration award. The Court of Appeals reversed, reinstating the entire award. We hold that when the arbitrators award *515 ed attorney’s fees, they exceeded their authority by awarding upon a matter not within the scope of the contract’s arbitration provision. Therefore, we reverse in part the judgment of the Court of Appeals and vacate the award of attorney’s fees.

On October 5, 1995, Robert J. Denley Company, Inc. (“Denley”), the project owner, entered into a construction agreement with contractor D <& E Construction Company, Inc. (“D & E”) to develop the Cottonwood Estates Subdivision in Collier-ville, Tennessee. In the contract, D & E agreed to provide all necessary labor, utilities, services, and materials for the building project. The contract also contains a provision providing for a retainage fund to be withheld until the completion of the contracted work. The agreement requires the arbitration of “all claims or disputes” relating to the contract that arise between the contractor and the owner. Specifically, the arbitration provision of this contract states in pertinent part:

10.8 All claims or disputes between the Contractor and the Owner arising out [of] or relating to the Contract, or the breach thereof, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect unless the parties mutually agree otherwise and subject to an initial presentation of the claim or dispute to the Architect.... Notice of the demand for arbitration shall be filed in writing with the other party to this Agreement and with the American Arbitration Association and shall be made within a reasonable time after the dispute has arisen. The award rendered by the arbitrator or arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.... The agreement herein among the parties to the Agreement and any other written agreement to arbitrate referred to herein shall be specifically enforceable under applicable law in any court having jurisdiction thereof.

In addition, the contract contains a choice-of-law clause requiring all provisions of the contract to be decided in accordance with Tennessee law. 1

During the course of construction, disputes arose between the parties. Consequently, after the project was completed, Denley refused to pay the contract retain-age. amount of $64,756.09 to D & E. In response, D & E filed with the American Arbitration Association a demand for arbitration to resolve the contractual payment dispute. Denley thereafter filed a response to the demand for arbitration and a counterclaim requesting damages. Although neither party requested attorney’s fees in their written submissions for relief, it is undisputed that D & E orally notified Denley prior to the arbitration hearing that it would be seeking attorney’s fees.

In December 1997, a three-person arbitration panel, chosen in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association, conducted the arbitration hearing. 2 At the hearing D & E requested attorney’s fees as additional compensation for Den-ley’s breach of contract. Denley objected to the arbitrators’ consideration of this issue. On January 15, 1998, the panel issued a written award, itemizing on separate lines the distinct categories of its compensatory awards to D & E: the total contract retainage amount, interest, and attorney’s fees. The panel also directed Denley to pay the administrative fees and expenses of the American Arbitration Association and the compensation and expenses of the arbitrators. The Panel denied Denley’s counterclaim in its entirety, awarding Denley none of the relief it requested.

*516 Subsequently, D & E filed a petition to confirm the arbitration award pursuant to Tennessee Code Annotated section 29-5-312. 3 In response, Denley filed a petition for an order vacating or, in the alternative, modifying the arbitration award pursuant to sections 29-5-313 4 and -314 5 respectively. The two causes of action were consolidated.

On July 23, 1998, D & E filed a motion for summary judgment confirming the arbitration award rendered in favor of D & E and requested a judgment against Den-ley for the amount of the award, prejudgment interest, and attorney’s fees incurred by D & E in confirming the arbitration award. 6 At the initial hearing on the motion for summary judgment, the trial court indicated that it desired additional evidence with respect to any modifications that were made to the written arbitration provision regarding the payment of administrative expenses and attorney’s fees. Therefore, the motion hearing was continued to a later date.

At the continued hearing, the chancellor received three exhibits into evidence: the parties’ construction agreement, the demand for arbitration filed by D & E, and the arbitrators’ written award. Although the court did not address the summary judgment motion specifically, it ultimately ruled that the arbitration panel exceeded its authority in awarding $13,000 in attorney’s fees to D & E. Specifically, the court explained:

In the contract, there is no reference whatsoever as to attorney fees, and it’s the Court’s opinion that the law of the *517 State of Tennessee is that unless the attorney fees have been agreed to between the parties in a contractual matter, that the award of attorney fees is not appropriate under the circumstances, and therefore, the Court can find nothing in this agreement which makes Mr. Denley liable for attorney fees that may be awarded as a result of a breach.
[[Image here]]
The Court is of the opinion that even if there is a breach unless there is a provision where Mr. Denley has agreed to pay attorney fees, then that is not a proper matter for the arbitrators to decide.
[[Image here]]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CARBON FIBER RECYCLING, LLC v. TIMOTHY SPAHN
Court of Appeals of Tennessee, 2025
MidSouth Construction, LLC v. Daniel Burstiner
Court of Appeals of Tennessee, 2025
Delisa Roose v. Bath Fitter Tennessee, Inc.
Court of Appeals of Tennessee, 2025
Coal Network, LLC
E.D. Kentucky, 2023
Nathaniel Hicks v. Thomas Chears
Court of Appeals of Tennessee, 2021
Perkins LLC. v. Fille, Inc.
N.D. Georgia, 2021
LVH, LLC v. Freeman Investment, LLC
Court of Appeals of Tennessee, 2021
Cates v. Crystal Clear Technologies, LLC
874 F.3d 530 (Sixth Circuit, 2017)
Akilah Louise Wofford v. M.J. Edwards & Sons Funeral Home Inc.
490 S.W.3d 800 (Court of Appeals of Tennessee, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
38 S.W.3d 513, 2001 Tenn. LEXIS 59, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-e-construction-co-v-robert-j-denley-co-tenn-2001.